24 projects under 26 MahaRERA registrations, registered 2017–2026. 12% have a completion date extended beyond the one promised.

24RERA projects
26Registrationssome projects hold several
21Completion still due5 past their completion date
41 monthsMedian extension beyond promised date12% of registrations extended
1Regulatory caseson 1 project
4Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20171
20181
20191
20202
20213
20222
20234
20243
20254
20265

Projects in Pisavali

24 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
The Vaidiki BlissShree Jari Mari Infra LLPPM133000260172031 Aug 202631 Dec 2031—Not yet due0
Rekhaai ResidencyShree Malhar DevelopersPR133000260072910 Jun 202631 Dec 2031—Not yet due0
Balaram ElevateShree Siddhivinayak BuildconPR13300026006041 Jun 202631 Mar 2030—Not yet due0
Chhaya Central GreensMalhar BuildmasterPR133000260008815 Apr 202631 Mar 2032—Not yet due0
Trimurti BlissShree Krupa Builders And DevelopersPR13310126000041 Apr 202631 Dec 2028—Not yet due0
Landmark AristoLandmark LifestylePM133000250136131 Oct 202531 Dec 2030—Not yet due0
Madan HeightsAdiyogi Housing LLPPM133000250133527 Oct 202531 Dec 2027—Not yet due0
Balaram HeightsGanesh Tukaram BhaneP5170008085221 Jul 202531 Dec 2029—Not yet due0
Empire World A And B WingAmpire One Residency LLPP5170007897124 Jan 202530 Apr 2027—Not yet due0
Anandi VrindavanShree Sai Malhar DevelopersP5170007695810 Jul 202430 Jun 2029—Not yet due0
Sahyadri EliteSikeria Shelter Private LimitedP5170005615616 May 202431 Mar 2028—Not yet due0
Palm GalaxySai LifestyleP5170005429915 Jan 202431 Dec 2026—Not yet due0
Empire City Building No. 1Empire DevelopersP5170005354410 Nov 202331 Dec 2026—Not yet due0
Sai ParadiseSai EnterprisesP517000524738 Sep 202331 Dec 2028—Not yet due0
Giriraj DarshanGiriraj DarshanP5170005097116 May 202331 Dec 202330 Dec 2024Extended 12 mo0
Shree Balaji ClassicShri Balaji NeomP5170005040012 Apr 202331 Dec 2026—Not yet due0
Pride HeightsPride EnterprisesP5170004630522 Jun 202231 Dec 2027—Not yet due0
Orchid TowerSkyview Builders & DevelopersP517000343534 Apr 202231 Jan 2027—Not yet due0
Ahmahf EmpireEmpire ResidencyP5170003157031 Oct 202131 Dec 2027—Not yet due0
Seasons Sahara Building No 2Samarth Sai Builders & DevelopersP5170002521823 Mar 202030 Dec 2024—Promised date passed0
Saket WorldAnand AssociatesP51700024797, P51700030224, P517000321809 Mar 202030 Jun 2027—Not yet due0
Seasons SaharaSamarth Sai Builders & DevelopersP5170002064430 Apr 201930 Dec 2023—Promised date passed0
Davakhar EleganceDavakhar Infrastructure Private LimitedP5170001612417 Apr 201830 Dec 202231 Mar 2027Extended 51 mo1
Nirman AakashDeepak Shankar YashwanteP5170001117431 Aug 201731 Oct 201830 Mar 2022Extended 41 mo0

Other localities in Kalyan

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Samarth Sai Builders & Developers2 projects
  2. Adiyogi Housing LLP1 project
  3. Ampire One Residency LLP1 project
  4. Anand Associates1 project
  5. Davakhar Infrastructure Private Limited1 project
  6. Deepak Shankar Yashwante1 project
  7. Empire Developers1 project
  8. Empire Residency1 project
  9. Ganesh Tukaram Bhane1 project
  10. Giriraj Darshan1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology