RERA projects in Pisavali
24 projects under 26 MahaRERA registrations, registered 2017–2026. 12% have a completion date extended beyond the one promised.
24RERA projects
26Registrationssome projects hold several
21Completion still due5 past their completion date
41 monthsMedian extension beyond promised date12% of registrations extended
1Regulatory caseson 1 project
4Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 1 |
| 2018 | 1 |
| 2019 | 1 |
| 2020 | 2 |
| 2021 | 3 |
| 2022 | 2 |
| 2023 | 4 |
| 2024 | 3 |
| 2025 | 4 |
| 2026 | 5 |
Projects in Pisavali
24 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| The Vaidiki BlissShree Jari Mari Infra LLP | PM1330002601720 | 31 Aug 2026 | 31 Dec 2031 | — | Not yet due | 0 |
| Rekhaai ResidencyShree Malhar Developers | PR1330002600729 | 10 Jun 2026 | 31 Dec 2031 | — | Not yet due | 0 |
| Balaram ElevateShree Siddhivinayak Buildcon | PR1330002600604 | 1 Jun 2026 | 31 Mar 2030 | — | Not yet due | 0 |
| Chhaya Central GreensMalhar Buildmaster | PR1330002600088 | 15 Apr 2026 | 31 Mar 2032 | — | Not yet due | 0 |
| Trimurti BlissShree Krupa Builders And Developers | PR1331012600004 | 1 Apr 2026 | 31 Dec 2028 | — | Not yet due | 0 |
| Landmark AristoLandmark Lifestyle | PM1330002501361 | 31 Oct 2025 | 31 Dec 2030 | — | Not yet due | 0 |
| Madan HeightsAdiyogi Housing LLP | PM1330002501335 | 27 Oct 2025 | 31 Dec 2027 | — | Not yet due | 0 |
| Balaram HeightsGanesh Tukaram Bhane | P51700080852 | 21 Jul 2025 | 31 Dec 2029 | — | Not yet due | 0 |
| Empire World A And B WingAmpire One Residency LLP | P51700078971 | 24 Jan 2025 | 30 Apr 2027 | — | Not yet due | 0 |
| Anandi VrindavanShree Sai Malhar Developers | P51700076958 | 10 Jul 2024 | 30 Jun 2029 | — | Not yet due | 0 |
| Sahyadri EliteSikeria Shelter Private Limited | P51700056156 | 16 May 2024 | 31 Mar 2028 | — | Not yet due | 0 |
| Palm GalaxySai Lifestyle | P51700054299 | 15 Jan 2024 | 31 Dec 2026 | — | Not yet due | 0 |
| Empire City Building No. 1Empire Developers | P51700053544 | 10 Nov 2023 | 31 Dec 2026 | — | Not yet due | 0 |
| Sai ParadiseSai Enterprises | P51700052473 | 8 Sep 2023 | 31 Dec 2028 | — | Not yet due | 0 |
| Giriraj DarshanGiriraj Darshan | P51700050971 | 16 May 2023 | 31 Dec 2023 | 30 Dec 2024 | Extended 12 mo | 0 |
| Shree Balaji ClassicShri Balaji Neom | P51700050400 | 12 Apr 2023 | 31 Dec 2026 | — | Not yet due | 0 |
| Pride HeightsPride Enterprises | P51700046305 | 22 Jun 2022 | 31 Dec 2027 | — | Not yet due | 0 |
| Orchid TowerSkyview Builders & Developers | P51700034353 | 4 Apr 2022 | 31 Jan 2027 | — | Not yet due | 0 |
| Ahmahf EmpireEmpire Residency | P51700031570 | 31 Oct 2021 | 31 Dec 2027 | — | Not yet due | 0 |
| Seasons Sahara Building No 2Samarth Sai Builders & Developers | P51700025218 | 23 Mar 2020 | 30 Dec 2024 | — | Promised date passed | 0 |
| Saket WorldAnand Associates | P51700024797, P51700030224, P51700032180 | 9 Mar 2020 | 30 Jun 2027 | — | Not yet due | 0 |
| Seasons SaharaSamarth Sai Builders & Developers | P51700020644 | 30 Apr 2019 | 30 Dec 2023 | — | Promised date passed | 0 |
| Davakhar EleganceDavakhar Infrastructure Private Limited | P51700016124 | 17 Apr 2018 | 30 Dec 2022 | 31 Mar 2027 | Extended 51 mo | 1 |
| Nirman AakashDeepak Shankar Yashwante | P51700011174 | 31 Aug 2017 | 31 Oct 2018 | 30 Mar 2022 | Extended 41 mo | 0 |
Other localities in Kalyan
- Dombivli404 projects
- Kalyandombivali (M Corp.)208 projects
- Kalyan137 projects
- Chikanghar107 projects
- Titwala89 projects
- Kalyan-Dombivali (M Corp.)83 projects
- Khoni71 projects
- Katemanevali55 projects
- Manda52 projects
- Tisgaon48 projects
- Gandhare43 projects
- Adharwadi24 projects
Most active promoters
By projects registered here, as named on MahaRERA.
- Samarth Sai Builders & Developers2 projects
- Adiyogi Housing LLP1 project
- Ampire One Residency LLP1 project
- Anand Associates1 project
- Davakhar Infrastructure Private Limited1 project
- Deepak Shankar Yashwante1 project
- Empire Developers1 project
- Empire Residency1 project
- Ganesh Tukaram Bhane1 project
- Giriraj Darshan1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology