RERA projects in Adharwadi

24 projects under 28 MahaRERA registrations, registered 2017–2025. 54% have a completion date extended beyond the one promised.

Locality
24RERA projects
28Registrationssome projects hold several
13Completion still due15 past their completion date
4 monthsMedian extension beyond promised date54% of registrations extended
0Regulatory casesnone on MahaRERA's lists
30Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20177
20184
20196
20200
20210
20223
20231
20242
20255

Projects in Adharwadi

24 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Earth ParkAastha Housing CorporationPM1331012500817, PM1331012500827, PM1331012500831 +211 Sep 202531 Dec 203130 Apr 2032Extended 4 mo0
Triveni PearlTrescon LimitedP517000556908 Apr 202431 Jan 202931 May 2029Extended 4 mo0
Midtown AdamMoon Star Developers LLPP517000551454 Mar 202431 Jul 202730 Nov 2027Extended 4 mo0
Midtown EveMoon Star Developers LLPP5170004909430 Jan 202330 Jun 202730 Oct 2027Extended 4 mo0
Raunak City Sector VI - F3Raunak CorporationP5170003397214 Mar 202231 Dec 202830 Apr 2029Extended 4 mo0
Raunak City Sector VI - F1Raunak CorporationP517000337628 Mar 202231 Dec 202830 Apr 2029Extended 4 mo0
Raunak City Sector VI - F2Raunak CorporationP517000337578 Mar 202231 Dec 202830 Apr 2029Extended 4 mo0
Raunak City Sector IV - D5Raunak CorporationP5170002024029 Mar 201930 Jun 202630 Jun 2026Promised date passed0
Raunak City Sector IV - D6Raunak CorporationP5170002026129 Mar 201930 Dec 202730 Dec 2027Not yet due0
Raunak City Sector IV - D7Raunak CorporationP5170002024129 Mar 201930 Jun 202630 Jun 2026Promised date passed0
Raunak City Sector IV - D8Raunak CorporationP5170002018229 Mar 201930 Dec 202530 Dec 2025Promised date passed0
Raunak City Sector IV - D4Raunak CorporationP5170001996215 Mar 201930 Jun 202530 Jun 2025Promised date passed0
Raunak City Sector IV - D3Raunak CorporationP517000197905 Mar 201930 Dec 202430 Dec 2025Extended 12 mo0
Raunak City Sector IV - D9Raunak CorporationP5170001748823 Aug 201830 Dec 202730 Dec 2027Not yet due0
Om Tanishq ResidencyM/S Laxmi RealtyP5170001717917 Jul 201830 Mar 202219 Jun 2024Extended 27 mo0
Nayan ApartmentNanda Santosh BhoirP5170001656923 May 201830 Jul 202120 Jan 2023Extended 18 mo0
Audumber ShrushtiKathod Dama BhoirP5170001596210 Apr 201830 Dec 202330 Dec 2023Promised date passed0
Krishna PrideGajanan Krupa DevelopersP5170001143931 Aug 201730 Jun 202230 Jun 2022Promised date passed0
Om ResidencyShree Ashapura CombinesP5170000944822 Aug 201730 Jun 202130 Jun 2022Extended 12 mo0
Raunak City Sector IV - D10Raunak CorporationP5170000933122 Aug 201730 Dec 202530 Dec 2025Promised date passed0
Raunak City Sector II - B7Raunak CorporationP5170000618214 Aug 201731 Dec 201831 Dec 2018Promised date passed0
Raunak City Sector IV - D1Raunak CorporationP517000033775 Aug 201730 Dec 202530 Dec 2025Promised date passed0
Raunak City Sector IV - D2Raunak CorporationP517000032105 Aug 201730 Dec 202530 Dec 2025Promised date passed0
Triveni Majesta - Wing A - Phase ITriveni Lifestyle Developers LLPP517000030794 Aug 201730 Dec 202130 Dec 2021Promised date passed0

Other localities in Kalyan

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Raunak Corporation14 projects
  2. Moon Star Developers LLP2 projects
  3. Aastha Housing Corporation1 project
  4. Gajanan Krupa Developers1 project
  5. Kathod Dama Bhoir1 project
  6. M/S Laxmi Realty1 project
  7. Nanda Santosh Bhoir1 project
  8. Shree Ashapura Combines1 project
  9. Trescon Limited1 project
  10. Triveni Lifestyle Developers LLP1 project
Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology