Skip to content
Residential / Group Housing · 1 buildingRERA P51700018933

Om Sai Residency Nx

Deedo IDDP-THN-1SBF

Its promised completion date, Dec 2022, has passed and MahaRERA does not show it completed; no MahaRERA orders on record.

Manda, Thane 421605 · by Om Sai Residency

Delivery3 yrs 11 mo past duePromised Dec 2022 · no extension on record · not shown completedRegulatoryNo ordersNot in any MahaRERA list or order Deedo has read

Buying a flat here?

See every deed registered on it.

Its promised completion date, Dec 2022, has passed and MahaRERA does not show it completed

  • This projectRegistered 17 Dec 2018, completion promised 30 Dec 2022, and still not shown completed today.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP51700018933
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5170001893317 Dec 201830 Dec 202230 Dec 2022Om Sai ResidencyProject page
Documents29

1 document held by Deedo, 28 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardPan Card Colour.pdf · uploaded 26 Aug 2018Source

Legal

  • Legal Title reportTitle Certificate.pdf · uploaded 26 Aug 2018Source
  • Declaration Form BForm B.pdf · uploaded 11 Dec 2018Source
  • OtherReviced CC Drawing 1.pdf · uploaded 12 Dec 2019Source
  • OtherRevised CC Drawing 2.pdf · uploaded 12 Dec 2019Source

Migrated

  • 1 PAN CardPan Card Colour.pdf · uploaded 26 Aug 2018Source
  • 1 Copy of the legal title reportTitle Certificate.pdf · uploaded 26 Aug 2018Source
Show all 29 documentsShow fewer documents

Migrated

  • 1 Commencement Certificates / NA Order for plotted developmentCC.pdf · uploaded 26 Aug 2018Source
  • 1 Details of encumbrancesEncrumbrance Certificate.pdf · uploaded 11 Dec 2018Source
  • 1 Copy of Layout Approval (in case of layout)CC Drawing-1.pdf · uploaded 11 Dec 2018Source
  • 2 Copy of Layout Approval (in case of layout)CC Drawing -2.pdf · uploaded 11 Dec 2018Source
  • 3 Copy of Layout Approval (in case of layout)CC Drawing-3.pdf · uploaded 11 Dec 2018Source
  • 1 Building Plan Approval (IOD)IOD.pdf · uploaded 11 Dec 2018Source
  • 1 Declaration in FORM BForm B.pdf · uploaded 11 Dec 2018Source
  • 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form-1.pdf · uploaded 11 Dec 2018Source
  • 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2.pdf · uploaded 11 Dec 2018Source
  • 1 Proforma of Allotment letterDraft Agrrement for flat sale and Allotment Letter.pdf · uploaded 11 Dec 2018Source
  • 1 Certificates of CA (Form 3)FORM 3 (CA Certificate for new registration and for withdrawal of Money) - OSR NX (1).pdf · uploaded 12 Dec 2018Source
  • 2 Commencement Certificates / NA Order for plotted developmentRevised CC_compressed.pdf · uploaded 12 Dec 2019Source
  • 1 OtherReviced CC Drawing 1.pdf · uploaded 12 Dec 2019Source
  • 2 OtherRevised CC Drawing 2.pdf · uploaded 12 Dec 2019Source
  • 1 Status of Formation of Legal Entity (Society/Co Op etc.)Om sai Residency NX - Society Registration.pdf · uploaded 9 Nov 2024Source

Technical

  • DocumentIOD.pdf · uploaded 11 Dec 2018Source
  • DocumentCC Drawing-1.pdf · uploaded 11 Dec 2018Source
  • DocumentCC Drawing -2.pdf · uploaded 11 Dec 2018Source
  • DocumentCC Drawing-3.pdf · uploaded 11 Dec 2018Source

Technical (Architect)

  • DocumentForm-1.pdf · uploaded 11 Dec 2018Source

Technical (Engineer)

  • DocumentForm 2.pdf · uploaded 11 Dec 2018Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 37/6

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Address
376, Near Sumukh Soceity, Near Regency SarvamPIN 421605
Village
Manda, Kalyan taluka
Land area for this project
2,630 sq m (28,309 sq ft)
Permissible built-up area
5,864 sq m (63,115 sq ft)
Sanctioned built-up area
1,919 sq m (20,652 sq ft)
Recreational open space
368 sq m (3,956 sq ft)
Designated bank account
21
Developed in phases
No

Survey, CTS, gat or plot numbers

37/6

Land as published on MahaRERA's project page

376

Boundaries

North
Goyal
South
Sumukh Soceity
East
Tandle
West
Bhoir

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals3

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectAnil R Nirgude—
EngineerAshok K Patel—
OtherKamlesh Ranpara—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology