Shreeman Residency
Certificate SignedManda, Thane 421605 |Promoter: Om Enterprises
Project summary
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- RERA registrations
- 2
- Phases
- 2
- Buildings
- 3
- Unit types
- —, Residential unit53 units in all
- Address
- Survey No 1 Hissa No 14/2, Manda, MandaPIN 421605
- Designated bank account
- 203
- Developed in phases
- No
Location
Coordinates as published by MahaRERA
Also registered as
Registered transactions
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion promised for 31 Dec 2018
P51700011833The latest completion date on record passed 7 years and 10 months ago.
- Registered
- 31 Aug 2017
- Promised
- 31 Dec 2018
Completion pushed back 4 months
P51700024873- Registered
- 9 Mar 2020
- Promised
- 30 Dec 2029
- Revised
- 30 Apr 2030
2 RERA registrations
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51700011833 | 31 Aug 2017 | 31 Dec 2018 | 31 Dec 2018 | Om Enterprises | Project page |
| P51700024873 | 9 Mar 2020 | 30 Dec 2029 | 30 Apr 2030 | Om Enterprises | Project page |
3 buildings
Buildings and wings named in the registration
| Building | Sanctioned floors | Units |
|---|---|---|
| B Wing | 5 | 24 |
| C Wing | 3 | 13 |
| Shreeman Residency | 6 | 16 |
Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.
Units and parking
9 of 53 units booked (17%), as the promoter reported to MahaRERA
| RERA | Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|---|
| P51700024873 | B Wing | — | — | 24 | — |
| P51700024873 | C Wing | — | — | 13 | — |
| P51700011833 | Shreeman Residency | Residential unit | 31.61 sq m · 340 sq ft | 4 | 2 |
| P51700011833 | Shreeman Residency | Residential unit | 31.66 sq m · 341 sq ft | 4 | 3 |
| P51700011833 | Shreeman Residency | Residential unit | 32.69 sq m · 352 sq ft | 4 | 1 |
| P51700011833 | Shreeman Residency | Residential unit | 32.74 sq m · 352 sq ft | 4 | 3 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Documents
2 documents held by Deedo, 108 filings listed on MahaRERA's project page
Registration certificate (2)
Finance
- PAN CardP51700024873 · PAN Card.pdf · uploaded 3 Mar 2020Source
Legal
- Legal Title reportP51700011833 · TITLE REPORT.pdf · uploaded 16 Aug 2017Source
- Declaration Form BP51700011833 · FORM-B.pdf · uploaded 16 Aug 2017Source
- Legal Title reportP51700024873 · title cert-tiwari.pdf · uploaded 3 Mar 2020Source
- Declaration Form BP51700024873 · om enterprises form b_compressed.pdf · uploaded 3 Mar 2020Source
Migrated
- 1 Copy of the legal title reportP51700011833 · TITLE REPORT.pdf · uploaded 16 Aug 2017Source
Show all 110 documentsShow fewer documents
Migrated
- 1 Details of encumbrancesP51700011833 · No Encumbrances.pdf · uploaded 16 Aug 2017Source
- 1 Copy of Layout Approval (in case of layout)P51700011833 · Copy of Layout.pdf · uploaded 16 Aug 2017Source
- 1 Building Plan Approval (IOD)P51700011833 · IOD.pdf · uploaded 16 Aug 2017Source
- 1 Commencement Certificates / NA Order for plotted developmentP51700011833 · COMMENCEMENT CERITIFICATE.pdf · uploaded 16 Aug 2017Source
- 1 Declaration in FORM BP51700011833 · FORM-B.pdf · uploaded 16 Aug 2017Source
- 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P51700011833 · FORM-1.pdf · uploaded 16 Aug 2017Source
- 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P51700011833 · FORM-2.pdf · uploaded 16 Aug 2017Source
- 1 Certificates of CA (Form 3)P51700011833 · Final FORM-3-ilovepdf-compressed.pdf · uploaded 16 Aug 2017Source
- 1 Proforma of Allotment letterP51700011833 · Final Proforma of Agrement for Sale and Allotment.pdf · uploaded 16 Aug 2017Source
- 2 Commencement Certificates / NA Order for plotted developmentP51700011833 · CC.pdf · uploaded 16 Feb 2019Source
- 1 Certificates of Architect (Form 4)P51700011833 · FORM-4.pdf · uploaded 16 Feb 2019Source
- 2 Certificates of CA (Form 3)P51700011833 · Form-3.pdf · uploaded 14 Mar 2019Source
- 1 Certificates of CA (Form 5)P51700011833 · FORM 5.pdf · uploaded 14 Mar 2019Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)P51700011833 · FORM -5.pdf · uploaded 29 Nov 2019Source
- 1 Copy of Layout Approval (in case of layout)P51700024873 · PLAN.pdf · uploaded 2 Mar 2020Source
- 1 Building Plan Approval / NA Order for plotted developmentP51700024873 · CC CERTIFICATE.pdf · uploaded 2 Mar 2020Source
- 1 Commencement Certificates / NA Order for plotted developmentP51700024873 · CC CERTIFICATE.pdf · uploaded 2 Mar 2020Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700024873 · ARCHITECT CERT.pdf · uploaded 2 Mar 2020Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700024873 · ENGINEER CERT.pdf · uploaded 2 Mar 2020Source
- 1 PAN CardP51700024873 · PAN Card.pdf · uploaded 3 Mar 2020Source
- 1 Copy of the legal title reportP51700024873 · title cert-tiwari.pdf · uploaded 3 Mar 2020Source
- 1 Details of encumbrancesP51700024873 · no encumbrance.pdf · uploaded 3 Mar 2020Source
- 1 Declaration in FORM BP51700024873 · om enterprises form b_compressed.pdf · uploaded 3 Mar 2020Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700024873 · FORM-3.pdf · uploaded 3 Mar 2020Source
- 1 Proforma of Allotment letterP51700024873 · Allotment Letter.pdf · uploaded 3 Mar 2020Source
- 2 Proforma of Allotment letterP51700024873 · Draft Agreement.pdf · uploaded 3 Mar 2020Source
- 2 Copy of Layout Approval (in case of layout)P51700024873 · Plan1.pdf · uploaded 13 Aug 2021Source
- 2 Commencement Certificates / NA Order for plotted developmentP51700024873 · Revised CC.pdf · uploaded 13 Aug 2021Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700024873 · FORM-1-Jun 21.pdf · uploaded 13 Aug 2021Source
- 2 Building Plan Approval / NA Order for plotted developmentP51700024873 · PLAN.pdf · uploaded 22 Oct 2021Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700024873 · form 1-c.pdf · uploaded 22 Oct 2021Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700024873 · FORM2.pdf · uploaded 22 Oct 2021Source
- 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P51700011833 · form1 -.pdf · uploaded 28 Jan 2022Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700024873 · form1 -.pdf · uploaded 28 Jan 2022Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700024873 · SCAN FORM 2.pdf · uploaded 1 Feb 2022Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)P51700024873 · Form 5.pdf · uploaded 22 Oct 2022Source
- 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700024873 · FORM-1.pdf · uploaded 9 Aug 2023Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700024873 · Om Enterprises - Form 2.pdf · uploaded 9 Aug 2023Source
- 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentP51700011833 · CC.pdf · uploaded 10 Oct 2023Source
- 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700024873 · FORM 1 06102023.pdf · uploaded 14 Oct 2023Source
- 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700024873 · FORM 2 08102023.pdf · uploaded 14 Oct 2023Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700024873 · Form-3 30-06-22.pdf · uploaded 22 Apr 2024Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700024873 · Form-3 30-09-22.pdf · uploaded 22 Apr 2024Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700024873 · Form-3 31-12-2022.pdf · uploaded 22 Apr 2024Source
- 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700024873 · Form-3 31-03-2023.pdf · uploaded 22 Apr 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)P51700024873 · Form-5 Fy 2022-23.pdf · uploaded 22 Apr 2024Source
- 3 Building Plan Approval / NA Order for plotted developmentP51700024873 · Revised Plan.pdf · uploaded 18 Jun 2024Source
- 3 Commencement Certificates / NA Order for plotted developmentP51700024873 · Revised CC.pdf · uploaded 18 Jun 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700024873 · Form 01 31-12-2024.pdf · uploaded 30 Jan 2025Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700024873 · Form-1 30-09-2024.pdf · uploaded 3 Feb 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700024873 · Form-3 30-06-2023 Sign.pdf · uploaded 3 Feb 2025Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700024873 · Form-3 30-09-2023 Sign.pdf · uploaded 3 Feb 2025Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700024873 · Form-3 31-12-2023 Sign.pdf · uploaded 3 Feb 2025Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700024873 · Form-3 31-03-2024 Sign.pdf · uploaded 3 Feb 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700024873 · Form-2 30-09-2024.pdf · uploaded 3 Feb 2025Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700024873 · Form-2 31-12-24-3-5.pdf · uploaded 3 Feb 2025Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)P51700024873 · Form-5 FY 2023-24 Sign.pdf · uploaded 3 Feb 2025Source
- 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700024873 · Form-3 30-06-2024 Sign.pdf · uploaded 8 Feb 2025Source
- 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700024873 · Form-3 30-09-2024 Sign.pdf · uploaded 8 Feb 2025Source
- 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700024873 · form-3 31-12-2024 Sign.pdf · uploaded 8 Feb 2025Source
- 1 Disclosure of sold/ booked inventoryP51700024873 · Sold Unsold List 30-06-2024.pdf · uploaded 8 Feb 2025Source
- 2 Disclosure of sold/ booked inventoryP51700024873 · Sold Unsold List 30-09-2024.pdf · uploaded 8 Feb 2025Source
- 3 Disclosure of sold/ booked inventoryP51700024873 · Sold Unsold List 31-12-2024.pdf · uploaded 8 Feb 2025Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700024873 · Form 01 31-12-2024.pdf · uploaded 12 Feb 2025Source
- Form 1P51700024873 · Form 1.pdf · uploaded 21 Aug 2025Source
- Form 2P51700024873 · Form 2.pdf · uploaded 21 Aug 2025Source
- Form 3P51700024873 · Signed Form 3.pdf · uploaded 21 Aug 2025Source
- Disclosure of Sold and Booked InventoryP51700024873 · Sold Unsold.pdf · uploaded 21 Aug 2025Source
- Form 5 (FY 2024-2025)P51700024873 · Form-5 FY 2024-25 Signed.pdf · uploaded 16 Oct 2025Source
- Form 1P51700024873 · Form 1 30-06-2025.pdf · uploaded 15 Jan 2026Source
- Form 2P51700024873 · Form 2 30-06-2025.pdf · uploaded 15 Jan 2026Source
- Form 3P51700024873 · Form 3 30-06-2025.pdf · uploaded 15 Jan 2026Source
- Disclosure of Sold and Booked InventoryP51700024873 · Sold Unsold List 30-06-2025.pdf · uploaded 15 Jan 2026Source
- Form 1P51700024873 · Signed Form 1 Q2.pdf · uploaded 14 Feb 2026Source
- Form 2P51700024873 · Signed Form 2 Q2.pdf · uploaded 14 Feb 2026Source
- Form 3P51700024873 · Signed Form 3 - Q2.pdf · uploaded 14 Feb 2026Source
- Disclosure of Sold and Booked InventoryP51700024873 · Sold Unsold Q2.pdf · uploaded 14 Feb 2026Source
- Form 1P51700024873 · Form 1.pdf · uploaded 18 Feb 2026Source
- Form 2P51700024873 · Form 2.pdf · uploaded 18 Feb 2026Source
- Form 3P51700024873 · form 3 final signed.pdf · uploaded 18 Feb 2026Source
- Disclosure of Sold and Booked InventoryP51700024873 · sold unsold.pdf · uploaded 18 Feb 2026Source
- Form 1P51700024873 · Form-1 31-03-2026 Signed.pdf · uploaded 19 May 2026Source
- Form 2P51700024873 · Form-2 31-03-2026 Signed.pdf · uploaded 19 May 2026Source
- Form 3P51700024873 · Form-3 31-03-2026 Signed.pdf · uploaded 19 May 2026Source
- Disclosure of Sold and Booked InventoryP51700024873 · Sold Unsold Inventory 31-03-2026 Signed.pdf · uploaded 19 May 2026Source
- Form 5 (FY 2025-2026)P51700024873 · form-5 om enterprises_0001.pdf · uploaded 13 Jul 2026Source
Technical
- DocumentP51700011833 · IOD.pdf · uploaded 16 Aug 2017Source
- DocumentP51700011833 · Copy of Layout.pdf · uploaded 16 Aug 2017Source
- DocumentP51700024873 · CC CERTIFICATE.pdf · uploaded 2 Mar 2020Source
- DocumentP51700024873 · PLAN.pdf · uploaded 2 Mar 2020Source
- DocumentP51700024873 · Plan1.pdf · uploaded 13 Aug 2021Source
- DocumentP51700024873 · PLAN.pdf · uploaded 22 Oct 2021Source
- DocumentP51700024873 · Revised Plan.pdf · uploaded 18 Jun 2024Source
Technical (Architect)
- DocumentP51700011833 · form1 -.pdf · uploaded 28 Jan 2022Source
- DocumentP51700024873 · FORM 1 06102023.pdf · uploaded 14 Oct 2023Source
- DocumentP51700024873 · Form 01 31-12-2024.pdf · uploaded 30 Jan 2025Source
- DocumentP51700024873 · Form-1 30-09-2024.pdf · uploaded 3 Feb 2025Source
- DocumentP51700024873 · Form 01 31-12-2024.pdf · uploaded 12 Feb 2025Source
Technical (Engineer)
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
Land
In Manda, Kalyan taluka
Survey, CTS, gat or plot numbers
Boundaries
- North
- Survey No 1 Hissa No 10
- South
- Survey No 1 Hissa No 11
- East
- Survey No 1 Hissa No 10
- West
- Survey No 1 Hissa No 14
Source: registration certificates and MahaRERA's project page, as stated there.
Professionals
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. | RERA |
|---|---|---|---|
| Architect | Arc Aniruddha S Dastane | — | P51700011833 |
| Engineer | Atul Kudtarkar And Associates | — | P51700011833 |
Source: MahaRERA project page. Contact details are not shown.