Deedo IDDP-THN-HWVRCompletion was pushed back 4 months, to Jul 2034; no MahaRERA orders on record; 0% of its units are booked.
Manda, Thane 421605 · by Mayureshwar Developers
Buying a flat here?
See every deed registered on it.
Completion was pushed back 4 months, to Jul 2034
- This projectRegistered 7 Mar 2025, completion promised 31 Mar 2034, revised to 31 Jul 2034.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP51700079475
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51700079475 | 7 Mar 2025 | 31 Mar 2034 | 31 Jul 2034 | Mayureshwar Developers | Project page |
Documents63
1 document held by Deedo, 62 filings listed on MahaRERA's project page
Finance
Legal
Migrated
- 1 Commencement Certificates / NA Order for plotted developmentSKM_C364e24022607021.pdf · uploaded 30 Mar 2024Source
- 1 Building Plan Approval / NA Order for plotted developmentscan0724_2_11zon.pdf · uploaded 30 Mar 2024Source
- 1 Copy of Layout Approval (in case of layout)scan0723_1_11zon.pdf · uploaded 1 Apr 2024Source
Show all 63 documentsShow fewer documents
Migrated
- 2 Commencement Certificates / NA Order for plotted developmentscan0725_3_11zon.pdf · uploaded 4 Apr 2024Source
- 4 Building Plan Approval / NA Order for plotted developmentscan0727_5_11zon (1).pdf · uploaded 4 Apr 2024Source
- 3 Building Plan Approval / NA Order for plotted developmentscan0725_3_11zon.pdf · uploaded 4 Apr 2024Source
- 2 Building Plan Approval / NA Order for plotted developmentscan0726_4_11zon.pdf · uploaded 4 Apr 2024Source
- 1 Declaration about Commencement CertificateDeclaration about cc .pdf · uploaded 4 Apr 2024Source
- 2 Declaration about Commencement CertificateANNEXURE A_11zon.pdf · uploaded 4 Apr 2024Source
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameformat A.pdf · uploaded 4 Apr 2024Source
- 1 PAN CardMAYURESHWAR DEVELOPERS PAN CARD.pdf · uploaded 1 Jul 2024Source
- 1 Copy of the legal title reportTitle Report.pdf · uploaded 18 Jan 2025Source
- 1 a Details of encumbrances concerned to FinanceDetails of encumbrances concerned to Legal.pdf · uploaded 18 Jan 2025Source
- 1 Proforma of Allotment letterAllotment Letter.pdf · uploaded 18 Jan 2025Source
- 1 Declaration in FORM BForm B of Developer-output.pdf · uploaded 18 Jan 2025Source
- 1 Deviation Report with respect to Allotment letterDeviation of Allotment Letter.pdf · uploaded 18 Jan 2025Source
- 1 b Details of encumbrances concerned to LegalDetails of encumbrances concerned to Legal.pdf · uploaded 18 Jan 2025Source
- 1 Other – TechnicalDeclaration of One Plot One Registration.pdf · uploaded 18 Jan 2025Source
- 1 Deviation Report with respect to model copy of AgreementDeviation for AFS.pdf · uploaded 18 Jan 2025Source
- 2 a Details of encumbrances concerned to FinanceDetails of encumbrances concerned to Finance.pdf · uploaded 3 Feb 2025Source
- 3 a Details of encumbrances concerned to FinanceDetails of encumbrances concerned to Legal.pdf · uploaded 3 Feb 2025Source
- 1 CERSAI detailsDeclaration-Nil-CERSAI Report.pdf · uploaded 3 Feb 2025Source
- 2 b Details of encumbrances concerned to LegalDetails of encumbrances concerned to Finance.pdf · uploaded 3 Feb 2025Source
- 3 b Details of encumbrances concerned to LegalDetails of encumbrances concerned to Legal.pdf · uploaded 3 Feb 2025Source
- 2 Other – TechnicalDeclaration.pdf · uploaded 3 Feb 2025Source
- 1 Proforma of Agreement for saleAgreement for sale.pdf · uploaded 3 Feb 2025Source
- 1 Disclosure of Interest in Other Real Estate OrganizationsOther Real Estates.pdf · uploaded 3 Feb 2025Source
- 1 Other – FinanceClarification Letter - Land Cost.pdf · uploaded 10 Feb 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate_1.pdf · uploaded 18 Feb 2025Source
- Form 1Form-1.pdf · uploaded 22 Jul 2025Source
- Form 2Form-2.pdf · uploaded 22 Jul 2025Source
- Form 3Form-3.pdf · uploaded 22 Jul 2025Source
- Disclosure of Sold and Booked InventoryDisclosure of Sold Booked Inventory.pdf · uploaded 22 Jul 2025Source
- Withdrawal Update Form 1Form-1.pdf · uploaded 22 Jul 2025Source
- Withdrawal Update Form 2Form-2.pdf · uploaded 22 Jul 2025Source
- Withdrawal Update Form 3CA Certificate.pdf · uploaded 22 Jul 2025Source
- Withdrawal Update Form 1Form 1 Sep 25.pdf · uploaded 30 Oct 2025Source
- Withdrawal Update Form 2Form 2 Sep 25.pdf · uploaded 30 Oct 2025Source
- Withdrawal Update Form 3Form 3 Sep 25.pdf · uploaded 30 Oct 2025Source
- Form 5 (FY 2024-2025)RERA Audit Report_24-25.pdf · uploaded 10 Dec 2025Source
- Withdrawal Update Form 1Form 1 Dec- 25.pdf · uploaded 23 Jan 2026Source
- Withdrawal Update Form 2Form 2 Dec- 25.pdf · uploaded 23 Jan 2026Source
- Withdrawal Update Form 3Form 3 Dec-25.pdf · uploaded 23 Jan 2026Source
- Withdrawal Update Form 1Architect Certificate-Mar 26.pdf · uploaded 23 Jun 2026Source
- Withdrawal Update Form 2Engineer Certificate -Mar 26.pdf · uploaded 23 Jun 2026Source
- Withdrawal Update Form 3Ca Certificate_Mar 26.pdf · uploaded 23 Jun 2026Source
- Withdrawal Update Form 1Form 1_Jun 2026.pdf · uploaded 6 Aug 2026Source
- Withdrawal Update Form 2Form 2_Jun 2026.pdf · uploaded 6 Aug 2026Source
- Withdrawal Update Form 3Form 3_Jun 2026.pdf · uploaded 6 Aug 2026Source
Technical
- Documentscan0724_2_11zon.pdf · uploaded 30 Mar 2024Source
- Documentscan0723_1_11zon.pdf · uploaded 1 Apr 2024Source
- Documentscan0726_4_11zon.pdf · uploaded 4 Apr 2024Source
- Documentscan0725_3_11zon.pdf · uploaded 4 Apr 2024Source
- Documentscan0727_5_11zon (1).pdf · uploaded 4 Apr 2024Source
- Other – TechnicalDeclaration of One Plot One Registration.pdf · uploaded 18 Jan 2025Source
- Other – TechnicalDeclaration.pdf · uploaded 3 Feb 2025Source
Technical (Architect)
- DocumentForm 1_Jun 2026.pdf · uploaded 6 Aug 2026Source
Technical (Engineer)
- DocumentForm 2_Jun 2026.pdf · uploaded 6 Aug 2026Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel 2, Hissa No. 1
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- 1BHK, 1BHK Landowner Share, 2BHK Developer Share, 2BHK Landowner Share, Office, Shop111 units in all
- Address
- Survey No. 181, Hissa No. 1 & 2, Village - Manda, Kalyan West 421605, Khandu Sheth Chowk 90 Ft. Ring Road, Near Abhilasha Park, MandaPIN 421605
- Village
- Manda, Kalyan taluka
- Location
- 19.29784, 73.19991
- Designated bank account
- 43
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Boundaries
- North
- S No 175
- South
- S No 181 H No 2
- East
- S No 181 H No 2
- West
- 30 Meter Wide Road
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking111 units
0 of 111 units booked (0%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 42.47 sq m · 457 sq ft | 45 | 0 |
| 1BHK Landowner Share | 42.47 sq m · 457 sq ft | 25 | 0 |
| 2BHK Developer Share | 50.8 sq m · 547 sq ft | 32 | 0 |
| 2BHK Landowner Share | 50.8 sq m · 547 sq ft | 2 | 0 |
| Office | 206.85 sq m · 2,227 sq ft | 1 | 0 |
| Shop | 35.68 sq m · 384 sq ft | 5 | 0 |
| Shop | 42.5 sq m · 457 sq ft | 1 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals3
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Dilip Deshmukh | — |
| Chartered accountant | Nikhil Bhoite And Associates | — |
| Engineer | Bahubali Dhamane | — |
Source: MahaRERA project page. Contact details are not shown.