Residential / Group Housing · 6 buildings · 1,110 unitsRERA P51700079712 +4

Lily

Completion was pushed back 4 months, to Jan 2036; no MahaRERA orders on record; 0% of its units are booked.

Khoni, Thane 421204 · Promoter: Lodha Developers Limited

DeliveryExtended 4 moPromised Sep 2035 · now due Jan 2036RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales0% booked0 of 1,110 units · as the promoter reported to MahaRERA
Lily project report cardPDF: delivery, regulatory orders, people on record, every tower and the registered deals — for your bank or lawyerSee what's inside · from ₹1,499

Completion was pushed back 4 months, to Jan 2036

  • P51700079712Registered 21 Mar 2025, completion promised 30 Sep 2030, revised to 30 Jan 2031.
  • P51700079715Registered 21 Mar 2025, completion promised 30 Sep 2030, revised to 30 Jan 2031.
  • P51700079771Registered 26 Mar 2025, completion promised 30 Sep 2030, revised to 30 Jan 2031.
  • P51700079810Registered 27 Mar 2025, completion promised 30 Sep 2035, revised to 30 Jan 2036.
  • P51700079844Registered 27 Mar 2025, completion promised 30 Sep 2030, revised to 30 Jan 2031.

No extension certificate on record.

5 registrations · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

6 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrations5
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5170007971221 Mar 202530 Sep 203030 Jan 2031Lodha Developers LimitedProject page
P5170007971521 Mar 202530 Sep 203030 Jan 2031Lodha Developers LimitedProject page
P5170007977126 Mar 202530 Sep 203030 Jan 2031Lodha Developers LimitedProject page
P5170007981027 Mar 202530 Sep 203530 Jan 2036Lodha Developers LimitedProject page
P5170007984427 Mar 202530 Sep 203030 Jan 2031Lodha Developers LimitedProject page
Documents329

5 documents held by Deedo, 324 filings listed on MahaRERA's project page

Registration certificate (5)

  • Registration certificateP51700079712 · 1 Oct 2025ViewSource
  • Registration certificateP51700079715 · 1 Oct 2025ViewSource
  • Registration certificateP51700079771 · 1 Oct 2025ViewSource
  • Registration certificateP51700079810 · 1 Oct 2025ViewSource
  • Registration certificateP51700079844 · 1 Oct 2025ViewSource

Finance

  • PAN CardP51700079844 · Pan Card.pdf · uploaded 3 Mar 2025Source
  • PAN CardP51700079771 · Pan Card.pdf · uploaded 4 Mar 2025Source
  • PAN CardP51700079810 · Pan Card.pdf · uploaded 4 Mar 2025Source
Show all 329 documentsShow fewer documents

Legal

  • Legal Title reportP51700079844 · RERA New Format-Lily Social Housing - Title Report.pdf · uploaded 3 Mar 2025Source
  • Declaration Form BP51700079844 · Lily C - D (Sector I1 - I2)Wing C -D - Notary.pdf · uploaded 3 Mar 2025Source
  • Legal Title reportP51700079771 · RERA New Format-Lily Social Housing - Title Report.pdf · uploaded 4 Mar 2025Source
  • Declaration Form BP51700079771 · Lily I- J (Sector I1 - I2) Wing I-J - notary.pdf · uploaded 4 Mar 2025Source
  • Legal Title reportP51700079810 · RERA New Format-Lily Social Housing - Title Report.pdf · uploaded 4 Mar 2025Source
  • Declaration Form BP51700079810 · Lily K - L (Sector I1 - I2)Wing K -L - Notary.pdf · uploaded 4 Mar 2025Source
  • Other – LegalP51700079844 · ilovepdf_merged (29).pdf · uploaded 10 Mar 2025Source
  • Other – LegalP51700079844 · 1 Other – Legal (9).pdf · uploaded 10 Mar 2025Source
  • Other – LegalP51700079844 · 2 Other – Legal (9).pdf · uploaded 10 Mar 2025Source
  • Other – LegalP51700079771 · A.pdf · uploaded 12 Mar 2025Source
  • Other – LegalP51700079771 · 2 Other – Legal (6).pdf · uploaded 12 Mar 2025Source
  • Other – LegalP51700079771 · ilovepdf_merged (33).pdf · uploaded 12 Mar 2025Source
  • Other – LegalP51700079810 · ilovepdf_merged (34).pdf · uploaded 13 Mar 2025Source
  • Other – LegalP51700079810 · 2 Other – Legal (11).pdf · uploaded 13 Mar 2025Source
  • Other – LegalP51700079810 · Legal 1.pdf · uploaded 24 Mar 2025Source
  • Declaration Form BP51700079771 · Form B Lily I - J.pdf · uploaded 31 Mar 2025Source
  • Declaration Form BP51700079715 · Form B Lily H - G.pdf · uploaded 31 Mar 2025Source
  • Declaration Form BP51700079844 · Form B Lily C - D.pdf · uploaded 31 Mar 2025Source
  • Declaration Form BP51700079844 · Form B Lily C - D.pdf · uploaded 31 Mar 2025Source
  • Declaration Form BP51700079712 · Form B Lily A -B.pdf · uploaded 31 Mar 2025Source

Migrated

  • 1 PAN CardP51700079844 · Pan Card.pdf · uploaded 3 Mar 2025Source
  • 1 Copy of the legal title reportP51700079844 · RERA New Format-Lily Social Housing - Title Report.pdf · uploaded 3 Mar 2025Source
  • 1 Proforma of Allotment letterP51700079844 · Proforma of Allotment letter.pdf · uploaded 3 Mar 2025Source
  • 1 Declaration in FORM BP51700079844 · Lily C - D (Sector I1 - I2)Wing C -D - Notary.pdf · uploaded 3 Mar 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700079844 · Lily - C and D - New Registration - Form1.pdf · uploaded 3 Mar 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700079844 · Form 3 - Lily C D.pdf · uploaded 3 Mar 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700079844 · Form 2 - Lily C D.pdf · uploaded 3 Mar 2025Source
  • 1 Commencement Certificates / NA Order for plotted developmentP51700079844 · Palava 2_Amended CC - Compress.pdf · uploaded 3 Mar 2025Source
  • 1 Building Plan Approval / NA Order for plotted developmentP51700079844 · 2024 12 30 - Palava 2 - Waterfall CC Type -SH A1(Sheet No - 51) - 3 5 7 - Compress.pdf · uploaded 3 Mar 2025Source
  • 1 Declaration about all RERA Designated Bank Accounts (Format A)P51700079844 · Format A - Bank Declartion - by Lodha.pdf · uploaded 3 Mar 2025Source
  • 1 Deviation Report with respect to Allotment letterP51700079844 · Deviation Report with respect to Allotment letter.pdf · uploaded 3 Mar 2025Source
  • 1 Deviation Report with respect to model copy of AgreementP51700079844 · Deviation Report with respect to model copy of Agreement.pdf · uploaded 3 Mar 2025Source
  • 1 Proforma of Agreement for saleP51700079844 · Agreement for sale Final.pdf · uploaded 3 Mar 2025Source
  • 1 Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)P51700079844 · Format B - Lily C and D - by Bank.pdf · uploaded 3 Mar 2025Source
  • 1 Disclosure for secured/unsecured finance availed for the projectP51700079844 · Secured - Unsecured.pdf · uploaded 3 Mar 2025Source
  • 1 PAN CardP51700079771 · Pan Card.pdf · uploaded 4 Mar 2025Source
  • 1 Copy of the legal title reportP51700079771 · RERA New Format-Lily Social Housing - Title Report.pdf · uploaded 4 Mar 2025Source
  • 1 Proforma of Allotment letterP51700079771 · Proforma of Allotment letter.pdf · uploaded 4 Mar 2025Source
  • 1 Declaration in FORM BP51700079771 · Lily I- J (Sector I1 - I2) Wing I-J - notary.pdf · uploaded 4 Mar 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700079771 · Lily I and j - Form1.pdf · uploaded 4 Mar 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700079771 · Form 3 - Lily I J.pdf · uploaded 4 Mar 2025Source
  • 1 Commencement Certificates / NA Order for plotted developmentP51700079771 · Palava 2_Amended CC - Compress.pdf · uploaded 4 Mar 2025Source
  • 1 Building Plan Approval / NA Order for plotted developmentP51700079771 · 2024 12 30 - Palava 2 - Waterfall CC Type -SH A1(Sheet No - 51) - 3 5 7 - Compress.pdf · uploaded 4 Mar 2025Source
  • 1 Declaration about all RERA Designated Bank Accounts (Format A)P51700079771 · Format A - Bank by lodha.pdf · uploaded 4 Mar 2025Source
  • 1 Deviation Report with respect to Allotment letterP51700079771 · Deviation Report with respect to Allotment letter.pdf · uploaded 4 Mar 2025Source
  • 1 Deviation Report with respect to model copy of AgreementP51700079771 · Deviation Report with respect to model copy of Agreement.pdf · uploaded 4 Mar 2025Source
  • 1 Proforma of Agreement for saleP51700079771 · Agreement for sale Final.pdf · uploaded 4 Mar 2025Source
  • 1 Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)P51700079771 · Format B - Lily I and J - By Bank.pdf · uploaded 4 Mar 2025Source
  • 1 Disclosure for secured/unsecured finance availed for the projectP51700079771 · Secured - Unsecured Finance.pdf · uploaded 4 Mar 2025Source
  • 1 PAN CardP51700079810 · Pan Card.pdf · uploaded 4 Mar 2025Source
  • 1 Copy of the legal title reportP51700079810 · RERA New Format-Lily Social Housing - Title Report.pdf · uploaded 4 Mar 2025Source
  • 1 Proforma of Allotment letterP51700079810 · Proforma of Allotment letter.pdf · uploaded 4 Mar 2025Source
  • 1 Declaration in FORM BP51700079810 · Lily K - L (Sector I1 - I2)Wing K -L - Notary.pdf · uploaded 4 Mar 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700079810 · Form1 - Lily K and L - New Registration.pdf · uploaded 4 Mar 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700079810 · Form 2 - Lily K L.pdf · uploaded 4 Mar 2025Source
  • 1 Commencement Certificates / NA Order for plotted developmentP51700079810 · Palava 2_Amended CC - Compress.pdf · uploaded 4 Mar 2025Source
  • 1 Building Plan Approval / NA Order for plotted developmentP51700079810 · 2024 12 30 - Palava 2 - Waterfall CC Type -SH C1 (Sheet No - 63) - 8 - Compress.pdf · uploaded 4 Mar 2025Source
  • 2 Building Plan Approval / NA Order for plotted developmentP51700079810 · 2024 12 30 - Palava 2 - Waterfall CC Type -SH C1 (Sheet No - 64) - 8 - Compress.pdf · uploaded 4 Mar 2025Source
  • 3 Building Plan Approval / NA Order for plotted developmentP51700079810 · 2024 12 30 - Palava 2 - Waterfall CC Type -SH C1 (Sheet No - 65) - 8 - Compress.pdf · uploaded 4 Mar 2025Source
  • 1 Declaration about all RERA Designated Bank Accounts (Format A)P51700079810 · Format A - Bank by Lodha.pdf · uploaded 4 Mar 2025Source
  • 1 Deviation Report with respect to Allotment letterP51700079810 · Deviation Report with respect to Allotment letter.pdf · uploaded 4 Mar 2025Source
  • 1 Deviation Report with respect to model copy of AgreementP51700079810 · Deviation Report with respect to model copy of Agreement.pdf · uploaded 4 Mar 2025Source
  • 1 Proforma of Agreement for saleP51700079810 · Agreement for sale Final.pdf · uploaded 4 Mar 2025Source
  • 1 Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)P51700079810 · Format B - Lily K and L - By Bank.pdf · uploaded 4 Mar 2025Source
  • 1 Disclosure for secured/unsecured finance availed for the projectP51700079810 · Secured - Unsecured Finance.pdf · uploaded 4 Mar 2025Source
  • 1 a Details of encumbrances concerned to FinanceP51700079844 · Leal encurance.pdf · uploaded 10 Mar 2025Source
  • 2 a Details of encumbrances concerned to FinanceP51700079844 · 0894_001.pdf · uploaded 10 Mar 2025Source
  • 1 Copy of Layout Approval (in case of layout)P51700079844 · 1 Copy of Layout Approval (in case of layout) CD.pdf · uploaded 10 Mar 2025Source
  • 1 Other – LegalP51700079844 · ilovepdf_merged (29).pdf · uploaded 10 Mar 2025Source
  • 3 Other – LegalP51700079844 · 2 Other – Legal (9).pdf · uploaded 10 Mar 2025Source
  • 2 Other – LegalP51700079844 · 1 Other – Legal (9).pdf · uploaded 10 Mar 2025Source
  • 1 Declaration about Commencement CertificateP51700079844 · Format D CC.pdf · uploaded 10 Mar 2025Source
  • 1 CERSAI detailsP51700079844 · Cersai Report.pdf · uploaded 10 Mar 2025Source
  • 1 b Details of encumbrances concerned to LegalP51700079844 · Leal encurance.pdf · uploaded 10 Mar 2025Source
  • 2 b Details of encumbrances concerned to LegalP51700079844 · 0894_001.pdf · uploaded 10 Mar 2025Source
  • 1 Other – TechnicalP51700079844 · order 50.pdf · uploaded 10 Mar 2025Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsP51700079844 · New Director Interest Disclouser.pdf · uploaded 10 Mar 2025Source
  • 1 a Details of encumbrances concerned to FinanceP51700079771 · Lily I-J ( Details of ECF).pdf · uploaded 12 Mar 2025Source
  • 2 a Details of encumbrances concerned to FinanceP51700079771 · 0933_001.pdf · uploaded 12 Mar 2025Source
  • 1 Copy of Layout Approval (in case of layout)P51700079771 · 1 Copy of Layout Approval (in case of layout) (55).pdf · uploaded 12 Mar 2025Source
  • 1 Other – LegalP51700079771 · A.pdf · uploaded 12 Mar 2025Source
  • 3 Other – LegalP51700079771 · ilovepdf_merged (33).pdf · uploaded 12 Mar 2025Source
  • 2 Other – LegalP51700079771 · 2 Other – Legal (6).pdf · uploaded 12 Mar 2025Source
  • 1 Declaration about Commencement CertificateP51700079771 · Lily I-J ( Format D ).pdf · uploaded 12 Mar 2025Source
  • 1 CERSAI detailsP51700079771 · Lily I-J ( Cersai Declaration ).pdf · uploaded 12 Mar 2025Source
  • 1 b Details of encumbrances concerned to LegalP51700079771 · Lily I-J ( Details of ECF).pdf · uploaded 12 Mar 2025Source
  • 2 b Details of encumbrances concerned to LegalP51700079771 · 0933_001.pdf · uploaded 12 Mar 2025Source
  • 1 Other – TechnicalP51700079771 · Lily I-J ( Order 50).pdf · uploaded 12 Mar 2025Source
  • 2 Other – TechnicalP51700079771 · 0939_001.pdf · uploaded 12 Mar 2025Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsP51700079771 · New Director Interest Disclouser Final.pdf · uploaded 12 Mar 2025Source
  • 1 a Details of encumbrances concerned to FinanceP51700079810 · Finance Encum.pdf · uploaded 13 Mar 2025Source
  • 2 a Details of encumbrances concerned to FinanceP51700079810 · Legal Encum.pdf · uploaded 13 Mar 2025Source
  • 1 Copy of Layout Approval (in case of layout)P51700079810 · 1 Copy of Layout Approval (in case of layout) KL.pdf · uploaded 13 Mar 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700079810 · Form 3.pdf · uploaded 13 Mar 2025Source
  • 2 Other – LegalP51700079810 · 2 Other – Legal (11).pdf · uploaded 13 Mar 2025Source
  • 1 Other – LegalP51700079810 · ilovepdf_merged (34).pdf · uploaded 13 Mar 2025Source
  • 1 Declaration about Commencement CertificateP51700079810 · CC Declaration.pdf · uploaded 13 Mar 2025Source
  • 1 CERSAI detailsP51700079810 · Cersai.pdf · uploaded 13 Mar 2025Source
  • 1 b Details of encumbrances concerned to LegalP51700079810 · Finance Encum.pdf · uploaded 13 Mar 2025Source
  • 2 b Details of encumbrances concerned to LegalP51700079810 · Legal Encum.pdf · uploaded 13 Mar 2025Source
  • 1 Other – TechnicalP51700079810 · Order 50.pdf · uploaded 13 Mar 2025Source
  • 2 Other – TechnicalP51700079810 · 0942_001.pdf · uploaded 13 Mar 2025Source
  • 3 Other – TechnicalP51700079810 · Lily K and L.pdf · uploaded 13 Mar 2025Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsP51700079810 · New Director Interest Disclouser Final.pdf · uploaded 13 Mar 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700079771 · Form 2 - Lily I J.pdf · uploaded 18 Mar 2025Source
  • 2 Building Plan Approval / NA Order for plotted developmentP51700079771 · 55 - converted.pdf · uploaded 24 Mar 2025Source
  • 3 Building Plan Approval / NA Order for plotted developmentP51700079771 · 56 - converted (1).pdf · uploaded 24 Mar 2025Source
  • 4 Building Plan Approval / NA Order for plotted developmentP51700079771 · 57 - converted.pdf · uploaded 24 Mar 2025Source
  • 3 Other – LegalP51700079810 · Legal 1.pdf · uploaded 24 Mar 2025Source
  • 2 Building Plan Approval / NA Order for plotted developmentP51700079844 · 56 - converted (1).pdf · uploaded 24 Mar 2025Source
  • 3 Building Plan Approval / NA Order for plotted developmentP51700079844 · 55 - converted.pdf · uploaded 24 Mar 2025Source
  • 4 Building Plan Approval / NA Order for plotted developmentP51700079844 · 57 - converted.pdf · uploaded 24 Mar 2025Source
  • 2 Other – TechnicalP51700079844 · Architect letter - lily C and D_Signed.pdf · uploaded 24 Mar 2025Source
  • 4 Building Plan Approval / NA Order for plotted developmentP51700079810 · 2024 12 30 - Sheet 66 - Sec I2_Type SH 08 (K L) (1).pdf · uploaded 25 Mar 2025Source
  • 4 Other – TechnicalP51700079810 · K and H merged.pdf · uploaded 25 Mar 2025Source
  • 3 Other – TechnicalP51700079844 · Lily C and D.pdf · uploaded 27 Mar 2025Source
  • 1 Other – TechnicalP51700079844 · Lily C and D.pdf · uploaded 27 Mar 2025Source
  • 1 Declaration in FORM BP51700079771 · Form B Lily I - J.pdf · uploaded 31 Mar 2025Source
  • 1 Declaration in FORM BP51700079715 · Form B Lily H - G.pdf · uploaded 31 Mar 2025Source
  • 2 Declaration in FORM BP51700079844 · Form B Lily C - D.pdf · uploaded 31 Mar 2025Source
  • 1 Declaration in FORM BP51700079844 · Form B Lily C - D.pdf · uploaded 31 Mar 2025Source
  • 1 Declaration in FORM BP51700079712 · Form B Lily A -B.pdf · uploaded 31 Mar 2025Source
  • 1 Disclosure of sold/ booked inventoryP51700079771 · Lily I and J - Sold unsold.pdf · uploaded 2 Apr 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700079712 · New Form 3 Lily A and B - Mar-25.pdf · uploaded 2 Apr 2025Source
  • 1 Disclosure of sold/ booked inventoryP51700079712 · Lily A and B - Sold Unsold.pdf · uploaded 2 Apr 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700079771 · Lily I and J.pdf · uploaded 2 May 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700079715 · Lily G and H.pdf · uploaded 2 May 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700079810 · Lily K and L.pdf · uploaded 2 May 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700079844 · Lily C and D.pdf · uploaded 2 May 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700079712 · Lily A and B.pdf · uploaded 2 May 2025Source
  • Form 1P51700079771 · Form1 -Lily I and J.pdf · uploaded 9 Jun 2025Source
  • Form 2P51700079771 · Self Certification - Form 2 (Lily I - J).pdf · uploaded 9 Jun 2025Source
  • Form 3P51700079771 · Self Certification - Form 3 (Lily I - J).pdf · uploaded 9 Jun 2025Source
  • Disclosure of Sold and Booked InventoryP51700079771 · Disclosure of Sold ( Lily I - J).pdf · uploaded 9 Jun 2025Source
  • Self-declaration of Quarterly ProgressP51700079771 · Declaration.pdf · uploaded 9 Jun 2025Source
  • Form 1P51700079715 · Form 1-Lily G and H.pdf · uploaded 9 Jun 2025Source
  • Form 2P51700079715 · Self Certification - Form 2 ( Lily G-H).pdf · uploaded 9 Jun 2025Source
  • Form 3P51700079715 · Self Certification - Form 3 ( Lily G-H).pdf · uploaded 9 Jun 2025Source
  • Disclosure of Sold and Booked InventoryP51700079715 · Disclosure of Sold ( Lily G - H).pdf · uploaded 9 Jun 2025Source
  • Self-declaration of Quarterly ProgressP51700079715 · Declaration.pdf · uploaded 9 Jun 2025Source
  • Form 1P51700079810 · Form1 -Lily K and L.pdf · uploaded 9 Jun 2025Source
  • Form 2P51700079810 · Self Certification - Form 2 (Lily K - L).pdf · uploaded 9 Jun 2025Source
  • Form 3P51700079810 · Self Certification - Form 3 (Lily K - L).pdf · uploaded 9 Jun 2025Source
  • Disclosure of Sold and Booked InventoryP51700079810 · Disclosure of Sold ( Lily K - L).pdf · uploaded 9 Jun 2025Source
  • Self-declaration of Quarterly ProgressP51700079810 · Declaration.pdf · uploaded 9 Jun 2025Source
  • Form 1P51700079844 · Form 1-Lily C and D.pdf · uploaded 9 Jun 2025Source
  • Form 2P51700079844 · Self Certification - Form 2 (Lily C - D).pdf · uploaded 9 Jun 2025Source
  • Form 3P51700079844 · Self Certification - Form 3 (Lily C - D).pdf · uploaded 9 Jun 2025Source
  • Disclosure of Sold and Booked InventoryP51700079844 · Disclosure of Sold ( Lily C- D).pdf · uploaded 9 Jun 2025Source
  • Self-declaration of Quarterly ProgressP51700079844 · Declaration.pdf · uploaded 9 Jun 2025Source
  • Form 1P51700079712 · Form 1-Lily A and B.pdf · uploaded 9 Jun 2025Source
  • Form 2P51700079712 · Self Certification - Form 2 ( Lily A - B).pdf · uploaded 9 Jun 2025Source
  • Form 3P51700079712 · Self Certification - Form 3 ( Lily A - B).pdf · uploaded 9 Jun 2025Source
  • Disclosure of Sold and Booked InventoryP51700079712 · Disclosure of Sold ( Lily A- B).pdf · uploaded 9 Jun 2025Source
  • Self-declaration of Quarterly ProgressP51700079712 · Declaration.pdf · uploaded 9 Jun 2025Source
  • Form 1P51700079771 · Form 1 - Lily I & J ( June 25).pdf · uploaded 10 Jul 2025Source
  • Form 2P51700079771 · Form 2 - Lily I & J ( June 25).pdf · uploaded 10 Jul 2025Source
  • Form 3P51700079771 · Form 3 - Lily I & J ( June 25).pdf · uploaded 10 Jul 2025Source
  • Disclosure of Sold and Booked InventoryP51700079771 · Sold - Lily I & J ( June 25).pdf · uploaded 10 Jul 2025Source
  • Form 1P51700079715 · Form 1 - Lily G & H.pdf · uploaded 10 Jul 2025Source
  • Form 2P51700079715 · Form 2 - Lily G & H .pdf · uploaded 10 Jul 2025Source
  • Form 3P51700079715 · Form 3 - Lily G & H.pdf · uploaded 10 Jul 2025Source
  • Disclosure of Sold and Booked InventoryP51700079715 · Sold - Lily G & H.pdf · uploaded 10 Jul 2025Source
  • Form 1P51700079810 · Form 1 - Lily K & L ( June 25).pdf · uploaded 10 Jul 2025Source
  • Form 2P51700079810 · Form 2 - Lily K & L ( June 25).pdf · uploaded 10 Jul 2025Source
  • Form 3P51700079810 · Form 3 - Lily K & L ( June 25).pdf · uploaded 10 Jul 2025Source
  • Disclosure of Sold and Booked InventoryP51700079810 · Sold - Lily K & L ( June 25).pdf · uploaded 10 Jul 2025Source
  • Form 1P51700079844 · Form 1 - Lily C & D ( June 25).pdf · uploaded 10 Jul 2025Source
  • Form 2P51700079844 · Form 2 - Lily C & D ( June 25).pdf · uploaded 10 Jul 2025Source
  • Form 3P51700079844 · Form 3 - Lily C & D ( June 25).pdf · uploaded 10 Jul 2025Source
  • Disclosure of Sold and Booked InventoryP51700079844 · Sold - Lily C & D ( June 25).pdf · uploaded 10 Jul 2025Source
  • Form 1P51700079712 · Form 1 - Lily A & B .pdf · uploaded 10 Jul 2025Source
  • Form 2P51700079712 · Form 2 - Lily A & B .pdf · uploaded 10 Jul 2025Source
  • Form 3P51700079712 · Form 3 - Lily A & B.pdf · uploaded 10 Jul 2025Source
  • Disclosure of Sold and Booked InventoryP51700079712 · Sold - Lily A & B.pdf · uploaded 10 Jul 2025Source
  • Form 2A (FY 2024-2025)P51700079771 · Lily I and J - P51700079771 - Form 2A.pdf · uploaded 25 Jul 2025Source
  • Form 2A (FY 2024-2025)P51700079715 · Lily G and H - P51700079715 - Form 2A.pdf · uploaded 25 Jul 2025Source
  • Form 2A (FY 2024-2025)P51700079810 · Lily K and L - P51700079810 - Form 2A.pdf · uploaded 25 Jul 2025Source
  • Form 2A (FY 2024-2025)P51700079844 · Lily C and D - P51700079844 - Form 2A.pdf · uploaded 25 Jul 2025Source
  • Form 2A (FY 2024-2025)P51700079712 · Lily A and B - P51700079712 - Form 2A.pdf · uploaded 25 Jul 2025Source
  • Withdrawal Update Form 1P51700079712 · Form- 1 Declaration Architech Certificate.pdf · uploaded 6 Oct 2025Source
  • Withdrawal Update Form 2P51700079712 · Form 2- Engineer Certificate.pdf · uploaded 6 Oct 2025Source
  • Withdrawal Update Form 3P51700079712 · Form - 3 Chartered Accountant certificate.pdf · uploaded 6 Oct 2025Source
  • Form 5 (FY 2024-2025)P51700079771 · Lily I and J.pdf · uploaded 13 Oct 2025Source
  • Form 5 (FY 2024-2025)P51700079715 · Lily G and H.pdf · uploaded 13 Oct 2025Source
  • Form 5 (FY 2024-2025)P51700079810 · Lily K and L.pdf · uploaded 13 Oct 2025Source
  • Form 5 (FY 2024-2025)P51700079844 · Lily C and D.pdf · uploaded 13 Oct 2025Source
  • Form 5 (FY 2024-2025)P51700079712 · Lily A and B.pdf · uploaded 13 Oct 2025Source
  • Withdrawal Update Form 1P51700079771 · Lily I u0026 J.pdf · uploaded 25 Oct 2025Source
  • Withdrawal Update Form 2P51700079771 · Form 2- Engineer Certificate ( Lily I and J).pdf · uploaded 25 Oct 2025Source
  • Withdrawal Update Form 3P51700079771 · Form - 3 Chartered Accountant Certificate ( Lily I and J ).pdf · uploaded 25 Oct 2025Source
  • Withdrawal Update Form 1P51700079715 · Lily G and H.pdf · uploaded 25 Oct 2025Source
  • Withdrawal Update Form 2P51700079715 · Form 2- Engineer Certificate (Lily G and H).pdf · uploaded 25 Oct 2025Source
  • Withdrawal Update Form 3P51700079715 · Withdrawal Update Form 3 · uploaded 25 Oct 2025Source
  • Withdrawal Update Form 1P51700079810 · Lily K u0026 L.pdf · uploaded 25 Oct 2025Source
  • Withdrawal Update Form 2P51700079810 · Form 2- Engineer Certificate (Lily K and L).pdf · uploaded 25 Oct 2025Source
  • Withdrawal Update Form 3P51700079810 · Form - 3 Chartered Accountant Certificate( Lily K and L).pdf · uploaded 25 Oct 2025Source
  • Withdrawal Update Form 1P51700079844 · Lily C u0026 D.pdf · uploaded 25 Oct 2025Source
  • Withdrawal Update Form 2P51700079844 · Form 2- Engineer Certificate (Lily C and D).pdf · uploaded 25 Oct 2025Source
  • Withdrawal Update Form 3P51700079844 · Form - 3 Chartered Accountant certificate( Lily C and D).pdf · uploaded 25 Oct 2025Source
  • Withdrawal Update Form 1P51700079712 · Lily A u0026 B.pdf · uploaded 25 Oct 2025Source
  • Withdrawal Update Form 2P51700079712 · Form 2- Engineer Certificate.pdf · uploaded 25 Oct 2025Source
  • Withdrawal Update Form 3P51700079712 · Form - 3 Chartered Accountant certificate.pdf · uploaded 25 Oct 2025Source
  • Withdrawal Update Form 1P51700079771 · Form-1 Lily I and J Dec-25.pdf · uploaded 23 Jan 2026Source
  • Withdrawal Update Form 2P51700079771 · Form 2- Engineer Certificate ( Lily I and J).pdf · uploaded 23 Jan 2026Source
  • Withdrawal Update Form 3P51700079771 · Form 3 -Lily I and J.pdf · uploaded 23 Jan 2026Source
  • Withdrawal Update Form 1P51700079715 · Form-1 Lily G and H Dec-25.pdf · uploaded 23 Jan 2026Source
  • Withdrawal Update Form 2P51700079715 · Form 2 - Lily G and H.pdf · uploaded 23 Jan 2026Source
  • Withdrawal Update Form 3P51700079715 · Withdrawal Update Form 3 · uploaded 23 Jan 2026Source
  • Withdrawal Update Form 1P51700079810 · Form-1 Lily K and L Dec-25.pdf · uploaded 23 Jan 2026Source
  • Withdrawal Update Form 2P51700079810 · Form 2- Engineer Certificate (Lily K and L).pdf · uploaded 23 Jan 2026Source
  • Withdrawal Update Form 3P51700079810 · Form 3 - Lily K and L.pdf · uploaded 23 Jan 2026Source
  • Withdrawal Update Form 1P51700079844 · Form-1 Lily C and D Dec-25.pdf · uploaded 23 Jan 2026Source
  • Withdrawal Update Form 2P51700079844 · Form 2 -Lily C and D.pdf · uploaded 23 Jan 2026Source
  • Withdrawal Update Form 3P51700079844 · Form 3 - Lily C and D.pdf · uploaded 23 Jan 2026Source
  • Withdrawal Update Form 1P51700079712 · Form-1 Lily A and B Dec-25.pdf · uploaded 23 Jan 2026Source
  • Withdrawal Update Form 2P51700079712 · Form 2 - Lily A and B.pdf · uploaded 23 Jan 2026Source
  • Withdrawal Update Form 3P51700079712 · Form - 3 Chartered Accountant certificate.pdf · uploaded 23 Jan 2026Source
  • Withdrawal Update Form 1P51700079771 · Form1 - Lily I and J - P51700079771.pdf · uploaded 20 Apr 2026Source
  • Withdrawal Update Form 2P51700079771 · Form 2- Engineer Certificate ( Lily I and J).pdf · uploaded 20 Apr 2026Source
  • Withdrawal Update Form 3P51700079771 · Form 3 -Lily I and J.pdf · uploaded 20 Apr 2026Source
  • Withdrawal Update Form 1P51700079715 · Form1 -Lily G and H - P51700079715- mar-26.pdf · uploaded 20 Apr 2026Source
  • Withdrawal Update Form 2P51700079715 · Form 2 - Lily G and H.pdf · uploaded 20 Apr 2026Source
  • Withdrawal Update Form 3P51700079715 · Withdrawal Update Form 3 · uploaded 20 Apr 2026Source
  • Withdrawal Update Form 1P51700079810 · Form1 - Lily K and L - P51700079810.pdf · uploaded 20 Apr 2026Source
  • Withdrawal Update Form 2P51700079810 · Form 2 -Lily K and L.pdf · uploaded 20 Apr 2026Source
  • Withdrawal Update Form 3P51700079810 · Form 3 - Lily K and L.pdf · uploaded 20 Apr 2026Source
  • Withdrawal Update Form 1P51700079844 · Form1 -Lily C and D - P51700079844-Mar-26.pdf · uploaded 20 Apr 2026Source
  • Withdrawal Update Form 2P51700079844 · Form 2 -Lily C and D.pdf · uploaded 20 Apr 2026Source
  • Withdrawal Update Form 3P51700079844 · Form 3 -Lily C and D.pdf · uploaded 20 Apr 2026Source
  • Withdrawal Update Form 1P51700079712 · Form1 - Lily A and B - P51700079712- Mar-26.pdf · uploaded 20 Apr 2026Source
  • Withdrawal Update Form 2P51700079712 · Form 2 -Lily A and B.pdf · uploaded 20 Apr 2026Source
  • Withdrawal Update Form 3P51700079712 · Form 3 -Lily A and B.pdf · uploaded 20 Apr 2026Source
  • Form 2A (FY 2025-2026)P51700079771 · Form 2A - Lily I and J - P51700079771.pdf · uploaded 29 Jun 2026Source
  • Form 2A (FY 2025-2026)P51700079715 · Form 2A - Lily G and H - P51700079715.pdf · uploaded 29 Jun 2026Source
  • Form 2A (FY 2025-2026)P51700079810 · Form 2A - Lily K and L - P51700079810.pdf · uploaded 29 Jun 2026Source
  • Form 2A (FY 2025-2026)P51700079844 · Form 2A - Lily C and D - P51700079844.pdf · uploaded 29 Jun 2026Source
  • Form 2A (FY 2025-2026)P51700079712 · Form 2A - Lily A and B - P51700079712.pdf · uploaded 29 Jun 2026Source
  • Withdrawal Update Form 1P51700079771 · Form1 - Lily I and J - P51700079771.pdf · uploaded 18 Jul 2026Source
  • Withdrawal Update Form 2P51700079771 · Form 2 and 3 - Lily I and J - P51700079771.pdf · uploaded 18 Jul 2026Source
  • Withdrawal Update Form 3P51700079771 · Form 3 - Lily I and J - P51700079771.pdf · uploaded 18 Jul 2026Source
  • Withdrawal Update Form 1P51700079715 · Form1 - Lily G and H - P51700079715.pdf · uploaded 18 Jul 2026Source
  • Withdrawal Update Form 2P51700079715 · Form 2 and 3 - Lily G and H - P51700079715.pdf · uploaded 18 Jul 2026Source
  • Withdrawal Update Form 3P51700079715 · Withdrawal Update Form 3 · uploaded 18 Jul 2026Source
  • Withdrawal Update Form 1P51700079810 · Form1 - Lily K and L - P51700079810.pdf · uploaded 18 Jul 2026Source
  • Withdrawal Update Form 2P51700079810 · Form 2 and 3 - Lily K and L - P51700079810.pdf · uploaded 18 Jul 2026Source
  • Withdrawal Update Form 3P51700079810 · Form 3 - Lily K and L - P51700079810.pdf · uploaded 18 Jul 2026Source
  • Withdrawal Update Form 1P51700079844 · Form1 - Lily C and D - P51700079844.pdf · uploaded 18 Jul 2026Source
  • Withdrawal Update Form 2P51700079844 · Form 2 and 3 - Lily C and D - P51700079844.pdf · uploaded 18 Jul 2026Source
  • Withdrawal Update Form 3P51700079844 · Form 3 - Lily C and D - P51700079844.pdf · uploaded 18 Jul 2026Source
  • Withdrawal Update Form 1P51700079712 · Form1 - Lily A and B - P51700079712.pdf · uploaded 18 Jul 2026Source
  • Withdrawal Update Form 2P51700079712 · Form 2 and 3 - Lily A and B - P51700079712.pdf · uploaded 18 Jul 2026Source
  • Withdrawal Update Form 3P51700079712 · Form 3 - Lily A and B - P51700079712.pdf · uploaded 18 Jul 2026Source
  • Form 5 (FY 2025-2026)P51700079771 · Lily I and J.pdf · uploaded 29 Sep 2026Source
  • Form 5 (FY 2025-2026)P51700079715 · Lily G and H.pdf · uploaded 29 Sep 2026Source
  • Form 5 (FY 2025-2026)P51700079810 · Lily K and L.pdf · uploaded 29 Sep 2026Source
  • Form 5 (FY 2025-2026)P51700079844 · Lily C and D.pdf · uploaded 29 Sep 2026Source
  • Form 5 (FY 2025-2026)P51700079712 · Lily A and B.pdf · uploaded 29 Sep 2026Source

Technical

  • DocumentP51700079844 · 2024 12 30 - Palava 2 - Waterfall CC Type -SH A1(Sheet No - 51) - 3 5 7 - Compress.pdf · uploaded 3 Mar 2025Source
  • DocumentP51700079771 · 2024 12 30 - Palava 2 - Waterfall CC Type -SH A1(Sheet No - 51) - 3 5 7 - Compress.pdf · uploaded 4 Mar 2025Source
  • DocumentP51700079810 · 2024 12 30 - Palava 2 - Waterfall CC Type -SH C1 (Sheet No - 63) - 8 - Compress.pdf · uploaded 4 Mar 2025Source
  • DocumentP51700079810 · 2024 12 30 - Palava 2 - Waterfall CC Type -SH C1 (Sheet No - 64) - 8 - Compress.pdf · uploaded 4 Mar 2025Source
  • DocumentP51700079810 · 2024 12 30 - Palava 2 - Waterfall CC Type -SH C1 (Sheet No - 65) - 8 - Compress.pdf · uploaded 4 Mar 2025Source
  • DocumentP51700079844 · 1 Copy of Layout Approval (in case of layout) CD.pdf · uploaded 10 Mar 2025Source
  • Other – TechnicalP51700079844 · order 50.pdf · uploaded 10 Mar 2025Source
  • DocumentP51700079771 · 1 Copy of Layout Approval (in case of layout) (55).pdf · uploaded 12 Mar 2025Source
  • Other – TechnicalP51700079771 · Lily I-J ( Order 50).pdf · uploaded 12 Mar 2025Source
  • Other – TechnicalP51700079771 · 0939_001.pdf · uploaded 12 Mar 2025Source
  • DocumentP51700079810 · 1 Copy of Layout Approval (in case of layout) KL.pdf · uploaded 13 Mar 2025Source
  • Other – TechnicalP51700079810 · Order 50.pdf · uploaded 13 Mar 2025Source
  • Other – TechnicalP51700079810 · 0942_001.pdf · uploaded 13 Mar 2025Source
  • Other – TechnicalP51700079810 · Lily K and L.pdf · uploaded 13 Mar 2025Source
  • DocumentP51700079771 · 55 - converted.pdf · uploaded 24 Mar 2025Source
  • DocumentP51700079771 · 56 - converted (1).pdf · uploaded 24 Mar 2025Source
  • DocumentP51700079771 · 57 - converted.pdf · uploaded 24 Mar 2025Source
  • DocumentP51700079844 · 56 - converted (1).pdf · uploaded 24 Mar 2025Source
  • DocumentP51700079844 · 55 - converted.pdf · uploaded 24 Mar 2025Source
  • DocumentP51700079844 · 57 - converted.pdf · uploaded 24 Mar 2025Source
  • Other – TechnicalP51700079844 · Architect letter - lily C and D_Signed.pdf · uploaded 24 Mar 2025Source
  • DocumentP51700079810 · 2024 12 30 - Sheet 66 - Sec I2_Type SH 08 (K L) (1).pdf · uploaded 25 Mar 2025Source
  • Other – TechnicalP51700079810 · K and H merged.pdf · uploaded 25 Mar 2025Source
  • Other – TechnicalP51700079844 · Lily C and D.pdf · uploaded 27 Mar 2025Source
  • Other – TechnicalP51700079844 · Lily C and D.pdf · uploaded 27 Mar 2025Source
  • DocumentP51700079771 · O - 06 - Layout for Lily I and J.pdf · uploaded 25 Nov 2025Source
  • DocumentP51700079771 · O - 51.pdf · uploaded 25 Nov 2025Source
  • DocumentP51700079771 · O - 55.pdf · uploaded 25 Nov 2025Source
  • DocumentP51700079771 · O - 56.pdf · uploaded 25 Nov 2025Source
  • DocumentP51700079771 · O - 57.pdf · uploaded 25 Nov 2025Source
  • DocumentP51700079715 · O - 06 Layout for Lily G and H.pdf · uploaded 25 Nov 2025Source
  • DocumentP51700079715 · O - 50.pdf · uploaded 25 Nov 2025Source
  • DocumentP51700079715 · O - 55.pdf · uploaded 25 Nov 2025Source
  • DocumentP51700079715 · O - 56.pdf · uploaded 25 Nov 2025Source
  • DocumentP51700079715 · O - 57.pdf · uploaded 25 Nov 2025Source
  • DocumentP51700079810 · O - 06 - Layout.pdf · uploaded 25 Nov 2025Source
  • DocumentP51700079810 · O - 63.pdf · uploaded 25 Nov 2025Source
  • DocumentP51700079810 · O - 64.pdf · uploaded 25 Nov 2025Source
  • DocumentP51700079810 · O - 65.pdf · uploaded 25 Nov 2025Source
  • DocumentP51700079810 · O - 66.pdf · uploaded 25 Nov 2025Source
  • DocumentP51700079844 · Layout for Lily C and D - O - 06.pdf · uploaded 25 Nov 2025Source
  • DocumentP51700079844 · O - 51.pdf · uploaded 25 Nov 2025Source
  • DocumentP51700079844 · O - 55.pdf · uploaded 25 Nov 2025Source
  • DocumentP51700079844 · O -56.pdf · uploaded 25 Nov 2025Source
  • DocumentP51700079844 · O - 57.pdf · uploaded 25 Nov 2025Source
  • DocumentP51700079712 · O - 06 - Layout for Lily A and B.pdf · uploaded 25 Nov 2025Source
  • DocumentP51700079712 · O - 50.pdf · uploaded 25 Nov 2025Source
  • DocumentP51700079712 · O - 55.pdf · uploaded 25 Nov 2025Source
  • DocumentP51700079712 · O - 56.pdf · uploaded 25 Nov 2025Source
  • DocumentP51700079712 · O - 57.pdf · uploaded 25 Nov 2025Source

Technical (Architect)

  • DocumentP51700079771 · Lily I and J.pdf · uploaded 2 May 2025Source
  • DocumentP51700079810 · Lily K and L.pdf · uploaded 2 May 2025Source
  • DocumentP51700079844 · Lily C and D.pdf · uploaded 2 May 2025Source
  • DocumentP51700079771 · Form1 - Lily I and J - P51700079771.pdf · uploaded 18 Jul 2026Source
  • DocumentP51700079715 · Form1 - Lily G and H - P51700079715.pdf · uploaded 18 Jul 2026Source
  • DocumentP51700079810 · Form1 - Lily K and L - P51700079810.pdf · uploaded 18 Jul 2026Source
  • DocumentP51700079844 · Form1 - Lily C and D - P51700079844.pdf · uploaded 18 Jul 2026Source
  • DocumentP51700079712 · Form1 - Lily A and B - P51700079712.pdf · uploaded 18 Jul 2026Source

Technical (Engineer)

  • DocumentP51700079771 · Form 2 and 3 - Lily I and J - P51700079771.pdf · uploaded 1 Jul 2026Source
  • DocumentP51700079715 · Form 2 and 3 - Lily G and H - P51700079715.pdf · uploaded 1 Jul 2026Source
  • DocumentP51700079810 · Form 2 and 3 - Lily K and L - P51700079810.pdf · uploaded 1 Jul 2026Source
  • DocumentP51700079844 · Form 2 and 3 - Lily C and D - P51700079844.pdf · uploaded 1 Jul 2026Source
  • DocumentP51700079712 · Form 2 and 3 - Lily A and B - P51700079712.pdf · uploaded 1 Jul 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvals145/1(P), 145/2

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Phases
5
Unit types
A 2BHK, A Shop, B 2BHK, B shop, B Shop, I 2BHK, J 2BHK, K 2BHK, L 2BHK, Wing K Shop, Wing L Shop, C 2BHK, D 2BHK, G 2BHK, H 2BHK, Shop G Wing, Shop Wing G, Shop Wing H1,110 units in all
Address
56/1A(P), 56/1B(P), 56/1C(P), 145/2, 145/3(P), Kalyan, ThanePIN 421204
Village
Khoni, Kalyan taluka
Designated bank account
76
Developed in phases
No
Also registered as
Lily A and B, Lily G and H, Lily I and J, Lily K and L, Lily C and D

Survey, CTS, gat or plot numbers

145/1(P)145/2145/3(P)26/B(P)55/3(P)56/1A(P)56/1B(P)56/1C(P)56/7A(P)56/7B(P)56/8(P)

Boundaries

North
57-8a 57-8b 57-9
South
56-7 56-8
East
26 56-2
West
59-2p 145-1p

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking1,110 units

0 of 1,110 units booked (0%), as the promoter reported to MahaRERA

A 2BHK · 114 unitsA Shop · 3 unitsB 2BHK · 113 unitsB shop · 2 unitsB Shop · 1 unitI 2BHK · 113 unitsJ 2BHK · 114 unitsK 2BHK · 72 unitsL 2BHK · 113 unitsWing K Shop · 2 unitsWing L Shop · 3 unitsC 2BHK · 113 unitsD 2BHK · 114 unitsG 2BHK · 114 unitsH 2BHK · 113 unitsShop G Wing · 1 unitShop Wing G · 2 unitsShop Wing H · 3 units
RERABuildingTypeCarpet areaUnitsBooked
P51700079712Sector I2 Cluster SH 05 Wing A and BA 2BHK45.56 sq m · 490 sq ft1140
P51700079712Sector I2 Cluster SH 05 Wing A and BA Shop25.35 sq m · 273 sq ft10
P51700079712Sector I2 Cluster SH 05 Wing A and BA Shop25.52 sq m · 275 sq ft10
P51700079712Sector I2 Cluster SH 05 Wing A and BA Shop31.52 sq m · 339 sq ft10
P51700079712Sector I2 Cluster SH 05 Wing A and BB 2BHK45.56 sq m · 490 sq ft1130
P51700079712Sector I2 Cluster SH 05 Wing A and BB shop25.35 sq m · 273 sq ft10
P51700079712Sector I2 Cluster SH 05 Wing A and BB shop25.52 sq m · 275 sq ft10
P51700079712Sector I2 Cluster SH 05 Wing A and BB Shop38.28 sq m · 412 sq ft10
Show all 27 unit rowsShow fewer unit rows
RERABuildingTypeCarpet areaUnitsBooked
P51700079771Sector I2, Cluster SH 07 Wing I and JI 2BHK45.56 sq m · 490 sq ft1130
P51700079771Sector I2, Cluster SH 07 Wing I and JJ 2BHK45.56 sq m · 490 sq ft1140
P51700079810Sector I2, Cluster SH 08 Wing K and LK 2BHK45.56 sq m · 490 sq ft720
P51700079810Sector I2, Cluster SH 08 Wing K and LL 2BHK45.56 sq m · 490 sq ft1130
P51700079810Sector I2, Cluster SH 08 Wing K and LWing K Shop25.8 sq m · 278 sq ft10
P51700079810Sector I2, Cluster SH 08 Wing K and LWing K Shop39.23 sq m · 422 sq ft10
P51700079810Sector I2, Cluster SH 08 Wing K and LWing L Shop33.6 sq m · 362 sq ft10
P51700079810Sector I2, Cluster SH 08 Wing K and LWing L Shop38.21 sq m · 411 sq ft10
P51700079810Sector I2, Cluster SH 08 Wing K and LWing L Shop39.23 sq m · 422 sq ft10
P51700079844Wing C and DC 2BHK45.56 sq m · 490 sq ft1130
P51700079844Wing C and DD 2BHK45.56 sq m · 490 sq ft1140
P51700079715Wing G and HG 2BHK45.56 sq m · 490 sq ft1140
P51700079715Wing G and HH 2BHK45.56 sq m · 490 sq ft1130
P51700079715Wing G and HShop G Wing38.21 sq m · 411 sq ft10
P51700079715Wing G and HShop Wing G26 sq m · 280 sq ft10
P51700079715Wing G and HShop Wing G39.23 sq m · 422 sq ft10
P51700079715Wing G and HShop Wing H26 sq m · 280 sq ft10
P51700079715Wing G and HShop Wing H33.6 sq m · 362 sq ft10
P51700079715Wing G and HShop Wing H38.21 sq m · 411 sq ft10

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals20

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.RERA
ArchitectVilas Desai & Associate—P51700079810
ArchitectVilas Desai & Associate—P51700079712
ArchitectVilas Desai & Associate—P51700079771
ArchitectVilas Desai & Associate—P51700079844
ArchitectVilas Desai & Associate—P51700079715
Chartered accountantChirag Sarvaiya & Co—P51700079844
Chartered accountantChirag Sarvaiya & Co—P51700079712
Chartered accountantChirag Sarvaiya & Co—P51700079715
Show all 20 professionalsShow fewer professionals
RoleNameRegistration no.RERA
Chartered accountantChirag Sarvaiya & Co—P51700079771
Chartered accountantChirag Sarvaiya & Co—P51700079810
EngineerFrancis Jose—P51700079712
EngineerFrancis Jose—P51700079771
EngineerFrancis Jose—P51700079810
EngineerFrancis Jose—P51700079715
EngineerFrancis Jose—P51700079844
EngineerK C Shah Consultants—P51700079771
EngineerK C Shah Consultants—P51700079712
EngineerK C Shah Consultants—P51700079715
EngineerK C Shah Consultants—P51700079810
EngineerK C Shah Consultants—P51700079844

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology