9 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects59
Registrations60some projects hold several
Completion still due3228 past their date
Median extension4 months55% of registrations extended
Regulatory cases0none on MahaRERA's lists

9 in 10 registrations run late here

60 MahaRERA registrations in Katemanevali

1 completed8 not yet due24 extended, not yet due27 past even the latest date

Extended registrations moved their completion date by a median of 4 months.

Projects in Katemanevali

59 projects registered with MahaRERA.

ProjectDeliveryMedian ₹/sq ftBooked
Royal HillsRoyal Builders and DevelopersDue Dec 2029——
Sai Dream World Building No 04 Sai Dream VertexSai Shrishti ConstructionsDue Dec 2029——
Sai Dream World Building No 01 (Sai Dream Signature)Sai Shrishti ConstructionDue Dec 2030——
Samarth AlturaPragati ConstructionsDue Dec 2031——
Ananntshree PearlAvighna KaranDue Apr 2030, extended 4 mo——
Madhu Nirmal HeightsMauli DeveloperDue Feb 2029, extended 4 mo——
Matrix By MadhavMadhav ConstructionsDue Apr 2028, extended 4 mo——
Ramayan Co-Operative Housing Society LimitedAshtavinayak EnterprisesDue Apr 2029, extended 4 mo——
Pawshe ArcadePawshe Group Builders And DevelopersDue Apr 2029, extended 4 mo——
Vaishnavi BlissVaishnavi DevelopersDue Dec 2027——
Sky HeritageDs Group DeveloperDue Apr 2031, extended 4 mo——
The Vaidiki CrownShree Jari Mari Realty LLPDue Apr 2030, extended 4 mo——
Tulip PearlSpace Edge Projects Private LimitedDue Apr 2029, extended 4 mo——
New SaraswatiShree Prabhat DeveloperDue Jul 2028, extended 4 mo——
Dattu HeightsGovind Dattu PawsheDue Jul 2027, extended 4 mo——
Sai Ratanlaxmi Co. Op. Hsg. Soc. Ltd.Laxmi EnterprisesDue Apr 2027, extended 4 mo——
Ashwathi HeightsPrachiti ConstructionsDue Dec 2026——
Vijay HeightsShree Jari Mari ResidencyDue Jul 2028, extended 4 mo——
The MilleniaMilan ConstructionsDue Dec 2028, extended 4 mo——
Trimurti OneTrimurti ConstructionDue Apr 2029, extended 4 mo—20%
Dattu EnclaveYash EnterprisesDue Apr 2029, extended 4 mo——
Gunjai DarshanLaxmi DevelopersDue Apr 2031, extended 4 mo—16%
Kulswamini AvenueKulswamini Builders And DevelopersDue Jun 2027—3%
AVS InsigniaReliable InfraDue Apr 2031, extended 4 mo—12%
Janki DhamRakesh Tapeshwar SinghDue Apr 2028, extended 4 mo——
Katemanevali market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Rai Residency Private Limited4 projects
  2. Pragati Constructions3 projects
  3. Avighna Karan2 projects
  4. Ganesh Developers2 projects
  5. Pawshe Group Builders And Developers2 projects
  6. Shree Prabhat Developer2 projects
  7. Aaradhana Construction1 project
  8. Alka Prakash Mhatre1 project
  9. Anil Shilpayatan Private Limited1 project
  10. Aradhna Construction1 project

Katemanevali, in questions

How many projects in Katemanevali run late?

9 in 10 MahaRERA registrations (51 of 60): their completion date was extended or has passed, data through 26 Nov 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Katemanevali by Deedo. Medians on fewer than 3 deeds are not shown.

Data through26 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology