Deedo IDDL-THN-KATEMANEVALI9 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects59
Registrations60some projects hold several
Completion still due3228 past their date
Median extension4 months55% of registrations extended
Regulatory cases0none on MahaRERA's lists
9 in 10 registrations run late here
60 MahaRERA registrations in Katemanevali
1 completed8 not yet due24 extended, not yet due27 past even the latest date
Extended registrations moved their completion date by a median of 4 months.
Projects in Katemanevali
59 projects registered with MahaRERA.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Royal HillsRoyal Builders and Developers | Due Dec 2029 | — | — |
| Sai Dream World Building No 04 Sai Dream VertexSai Shrishti Constructions | Due Dec 2029 | — | — |
| Sai Dream World Building No 01 (Sai Dream Signature)Sai Shrishti Construction | Due Dec 2030 | — | — |
| Samarth AlturaPragati Constructions | Due Dec 2031 | — | — |
| Ananntshree PearlAvighna Karan | Due Apr 2030, extended 4 mo | — | — |
| Madhu Nirmal HeightsMauli Developer | Due Feb 2029, extended 4 mo | — | — |
| Matrix By MadhavMadhav Constructions | Due Apr 2028, extended 4 mo | — | — |
| Ramayan Co-Operative Housing Society LimitedAshtavinayak Enterprises | Due Apr 2029, extended 4 mo | — | — |
| Pawshe ArcadePawshe Group Builders And Developers | Due Apr 2029, extended 4 mo | — | — |
| Vaishnavi BlissVaishnavi Developers | Due Dec 2027 | — | — |
| Sky HeritageDs Group Developer | Due Apr 2031, extended 4 mo | — | — |
| The Vaidiki CrownShree Jari Mari Realty LLP | Due Apr 2030, extended 4 mo | — | — |
| Tulip PearlSpace Edge Projects Private Limited | Due Apr 2029, extended 4 mo | — | — |
| New SaraswatiShree Prabhat Developer | Due Jul 2028, extended 4 mo | — | — |
| Dattu HeightsGovind Dattu Pawshe | Due Jul 2027, extended 4 mo | — | — |
| Sai Ratanlaxmi Co. Op. Hsg. Soc. Ltd.Laxmi Enterprises | Due Apr 2027, extended 4 mo | — | — |
| Ashwathi HeightsPrachiti Constructions | Due Dec 2026 | — | — |
| Vijay HeightsShree Jari Mari Residency | Due Jul 2028, extended 4 mo | — | — |
| The MilleniaMilan Constructions | Due Dec 2028, extended 4 mo | — | — |
| Trimurti OneTrimurti Construction | Due Apr 2029, extended 4 mo | — | 20% |
| Dattu EnclaveYash Enterprises | Due Apr 2029, extended 4 mo | — | — |
| Gunjai DarshanLaxmi Developers | Due Apr 2031, extended 4 mo | — | 16% |
| Kulswamini AvenueKulswamini Builders And Developers | Due Jun 2027 | — | 3% |
| AVS InsigniaReliable Infra | Due Apr 2031, extended 4 mo | — | 12% |
| Janki DhamRakesh Tapeshwar Singh | Due Apr 2028, extended 4 mo | — | — |
Nearby: other villages in Kalyan
Most active promoters
- Rai Residency Private Limited4 projects
- Pragati Constructions3 projects
- Avighna Karan2 projects
- Ganesh Developers2 projects
- Pawshe Group Builders And Developers2 projects
- Shree Prabhat Developer2 projects
- Aaradhana Construction1 project
- Alka Prakash Mhatre1 project
- Anil Shilpayatan Private Limited1 project
- Aradhna Construction1 project
Katemanevali, in questions
How many projects in Katemanevali run late?
9 in 10 MahaRERA registrations (51 of 60): their completion date was extended or has passed, data through 26 Nov 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Katemanevali by Deedo. Medians on fewer than 3 deeds are not shown.
Data through26 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology