Deedo IDDL-THN-KATEMANEVALI9 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects59
Registrations60some projects hold several
Completion still due3228 past their date
Median extension4 months55% of registrations extended
Regulatory cases0none on MahaRERA's lists
9 in 10 registrations run late here
60 MahaRERA registrations in Katemanevali
1 completed8 not yet due24 extended, not yet due27 past even the latest date
Extended registrations moved their completion date by a median of 4 months.
Projects in Katemanevali
59 projects registered with MahaRERA.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Krishna EmpireTirumala Developers | Due Oct 2027, extended 4 mo | — | — |
| Sai ArcadeGanesh Developers | Due Apr 2028, extended 4 mo | — | — |
| Vrindavan HomesShree Prabhat Developer | Due Oct 2027, extended 4 mo | — | 46% |
| Pawshe PridePawshe Group Builders And Developers | Due Aug 2028, extended 4 mo | — | — |
| Vinayak PreranaShreeram Developers | Completed | — | — |
| Sai Vikrant HeightsVikrant Construction | Due Apr 2027, extended 4 mo | — | 23% |
| Lakeview Co Operative Housing LimitedGP Infra | Completed | — | 40% |
| Sai AltezzaSai Shraddha Constructions | Due Apr 2027, extended 4 mo | — | 29% |
| Gmail Luxuiraalka prakash mhatre | 11 mo late | — | 18% |
| Avighna Karan Wing CAvighna Karan | 3 mo late | — | 91% |
| Tisai HeightsTisai Construction | Completed, extended 1 yr | — | 49% |
| BHANUMATI TOWER wing APooja Buildcon | 4 yrs 5 mo late | — | — |
| Kairali ParkRAI RESIDENCY Private Limited | 2 yrs 5 mo late | — | 64% |
| Sai HeightsAaradhana Construction | Completed | — | 100% |
| Tulip ApartmentsSpace Edge Projects Pvt Ltd | 5 mo late | — | 44% |
| Vasant VatikaOm Constructions | 1 yr 1 mo late | — | 91% |
| Shelar HeightsGanesh Developers | Completed | — | — |
| Om Darshan HeightsPragati Constructions | 3 yrs 1 mo late | — | — |
| Sai GalaxySanchi Construction | Completed | — | 38% |
| Vitthu Paradise Building No. 3Aradhna Construction | Due Mar 2027 | — | 59% |
| Shreeram ComplexG K Developers | 8 yrs 5 mo late | — | 100% |
| Ritesh EmpireSapphire Developers | Completed | — | 55% |
| Dasarath PlazaPrabhat Builders & Developers | Completed | — | 15% |
| Jamunabai TowerNageshwar Construction | 11 mo late | — | — |
| Rai ParadiseRAI RESIDENCY Private Limited | Completed | — | 39% |
Nearby: other villages in Kalyan
Most active promoters
- Rai Residency Private Limited4 projects
- Pragati Constructions3 projects
- Avighna Karan2 projects
- Ganesh Developers2 projects
- Pawshe Group Builders And Developers2 projects
- Shree Prabhat Developer2 projects
- Aaradhana Construction1 project
- Alka Prakash Mhatre1 project
- Anil Shilpayatan Private Limited1 project
- Aradhna Construction1 project
Katemanevali, in questions
How many projects in Katemanevali run late?
9 in 10 MahaRERA registrations (51 of 60): their completion date was extended or has passed, data through 26 Nov 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Katemanevali by Deedo. Medians on fewer than 3 deeds are not shown.
Data through26 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology