Skip to content
Residential / Group Housing · 2 buildings · 98 unitsRERA P51700013877

Ritesh Empire

Deedo IDDP-THN-DASJ

MahaRERA shows it completed; no MahaRERA orders on record; 55% of its units are booked.

Katemanevali, Thane 421306 · by Sapphire Developers

DeliveryCompletedCompletion / occupancy certificate on MahaRERARegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales55% booked54 of 98 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

MahaRERA shows it completed

  • This projectRegistered 30 Oct 2017, completion promised 30 Dec 2023.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

2 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP51700013877
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5170001387730 Oct 201730 Dec 202330 Dec 2023Sapphire DevelopersProject page
Documents73

1 document held by Deedo, 72 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardSapphire Developers pan.pdf · uploaded 30 Sep 2017Source

Legal

  • Legal Title reportTitle Certificate.pdf · uploaded 30 Sep 2017Source
  • Declaration Form BAffidavit Chandrashekhar.pdf · uploaded 30 Sep 2017Source
  • Declaration Form BFormB.pdf · uploaded 30 Mar 2018Source
  • Declaration Form BAffidavit Randesh.pdf · uploaded 30 Mar 2018Source
  • Declaration Form BAffidavit Chandrashekhar.pdf · uploaded 30 Mar 2018Source
  • Other – LegalShekhar Vakalatnama_0001.pdf · uploaded 14 Jul 2025Source
Show all 73 documentsShow fewer documents

Legal

  • Other – Legal7 Sapphire Vakalatnama.pdf · uploaded 14 Jul 2025Source
  • Other – Legal5 Shekhar Replay to Show Cause Notice.pdf · uploaded 14 Jul 2025Source
  • Other – LegalShekhar Allotment Letter_0001.pdf · uploaded 14 Jul 2025Source
  • Other – Legal4 Shekhar Show Cause Notice_0001.pdf · uploaded 14 Jul 2025Source
  • Other – Legal2 Zaman Ali Notice Replay 220623.pdf · uploaded 14 Jul 2025Source
  • Other – Legal6 Zaman Ali Notice Reply 310723.pdf · uploaded 14 Jul 2025Source
  • Other – Legal1 Zaman Ali Notice 160623_compressed.pdf · uploaded 14 Jul 2025Source
  • Other – LegalShekhar Say_0001_compressed.pdf · uploaded 14 Jul 2025Source
  • Other – Legal8 Sapphire Say_0001_compressed.pdf · uploaded 14 Jul 2025Source
  • Other – Legal3 Zaman Ali Notice Responce Letter 220623_0001_compressed_compressed_Compressed.pdf · uploaded 14 Jul 2025Source

Migrated

  • 1 PAN CardSapphire Developers pan.pdf · uploaded 30 Sep 2017Source
  • 1 Copy of the legal title reportTitle Certificate.pdf · uploaded 30 Sep 2017Source
  • 1 Details of encumbrancesSearch Report.pdf · uploaded 30 Sep 2017Source
  • 2 Details of encumbrancesTitle Certificate.pdf · uploaded 30 Sep 2017Source
  • 1 Copy of Layout Approval (in case of layout)Plan Copy.pdf · uploaded 30 Sep 2017Source
  • 1 Building Plan Approval (IOD)IOD.pdf · uploaded 30 Sep 2017Source
  • 1 Declaration in FORM BAffidavit Chandrashekhar.pdf · uploaded 30 Sep 2017Source
  • 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architech Certificate.pdf · uploaded 30 Sep 2017Source
  • 1 Certificates of CA (Form 3)CA Certificate.pdf · uploaded 30 Sep 2017Source
  • 1 Proforma of Allotment letterDraft Agreement.pdf · uploaded 30 Sep 2017Source
  • 2 Declaration in FORM BFormB.pdf · uploaded 30 Mar 2018Source
  • 3 Declaration in FORM BAffidavit Randesh.pdf · uploaded 30 Mar 2018Source
  • 4 Declaration in FORM BAffidavit Chandrashekhar.pdf · uploaded 30 Mar 2018Source
  • 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)1.pdf · uploaded 30 Mar 2018Source
  • 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)2.pdf · uploaded 30 Mar 2018Source
  • 3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)3.pdf · uploaded 30 Mar 2018Source
  • 2 Certificates of CA (Form 3)CA Certificate.pdf · uploaded 30 Mar 2018Source
  • 3 Certificates of CA (Form 3)CA Certificate.pdf · uploaded 30 Mar 2018Source
  • 1 Commencement Certificates / NA Order for plotted developmentRevised Commencement Certificate.pdf · uploaded 26 Jun 2019Source
  • 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)45 and Architech Rera Certificate( B-Wing).pdf · uploaded 26 Jun 2019Source
  • 4 Certificates of CA (Form 3)fORM 3.pdf · uploaded 26 Jun 2019Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)Form 5 17-18.pdf · uploaded 9 Feb 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)Form 5 18 - 19.pdf · uploaded 9 Feb 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)Form 5 19-20.pdf · uploaded 9 Feb 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Form 5 20-21.pdf · uploaded 9 Feb 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Form 5 21-22.pdf · uploaded 9 Feb 2023Source
  • 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentSapphire Occupancy Certificate.pdf · uploaded 9 Feb 2023Source
  • 1 Commencement Certificates / NA Order for plotted developmentRevision cc (2) - 20 June 2022.pdf · uploaded 30 Nov 2024Source
  • 1 Building Plan Approval (IOD)Sapphire Part Completion Plan 20 Dec 2021_11zon.pdf · uploaded 30 Nov 2024Source
  • 2 Building Plan Approval (IOD)Plans 20 June 2022.pdf · uploaded 30 Nov 2024Source
  • 3 Building Plan Approval (IOD)Plans 07 Dec 2022.pdf · uploaded 30 Nov 2024Source
  • 1 Status of Formation of Legal Entity (Society/Co Op etc.)Society Registration Certificate_0001.pdf · uploaded 30 Nov 2024Source
  • 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentPart OC 1.pdf · uploaded 30 Nov 2024Source
  • 2 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFull OC 2.pdf · uploaded 30 Nov 2024Source
  • 3 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFull OC - Both.pdf · uploaded 30 Nov 2024Source
  • 1 Architect’s Certificate on Completion of Project (Form 4)Form 4_11zon.pdf · uploaded 4 Dec 2024Source
  • 2 Architect’s Certificate on Completion of Project (Form 4)Form 4_compressed.pdf · uploaded 9 Dec 2024Source
  • 1 Other – LegalShekhar Vakalatnama_0001.pdf · uploaded 14 Jul 2025Source
  • 2 Other – Legal7 Sapphire Vakalatnama.pdf · uploaded 14 Jul 2025Source
  • 3 Other – Legal5 Shekhar Replay to Show Cause Notice.pdf · uploaded 14 Jul 2025Source
  • 4 Other – LegalShekhar Allotment Letter_0001.pdf · uploaded 14 Jul 2025Source
  • 5 Other – Legal4 Shekhar Show Cause Notice_0001.pdf · uploaded 14 Jul 2025Source
  • 6 Other – Legal2 Zaman Ali Notice Replay 220623.pdf · uploaded 14 Jul 2025Source
  • 7 Other – Legal6 Zaman Ali Notice Reply 310723.pdf · uploaded 14 Jul 2025Source
  • 8 Other – Legal1 Zaman Ali Notice 160623_compressed.pdf · uploaded 14 Jul 2025Source
  • 9 Other – LegalShekhar Say_0001_compressed.pdf · uploaded 14 Jul 2025Source
  • 10 Other – Legal8 Sapphire Say_0001_compressed.pdf · uploaded 14 Jul 2025Source
  • 11 Other – Legal3 Zaman Ali Notice Responce Letter 220623_0001_compressed_compressed_Compressed.pdf · uploaded 14 Jul 2025Source

Technical

  • DocumentPlan Copy.pdf · uploaded 30 Sep 2017Source
  • DocumentIOD.pdf · uploaded 30 Sep 2017Source
  • DocumentSapphire Part Completion Plan 20 Dec 2021_11zon.pdf · uploaded 30 Nov 2024Source
  • DocumentPlans 20 June 2022.pdf · uploaded 30 Nov 2024Source
  • DocumentPlans 07 Dec 2022.pdf · uploaded 30 Nov 2024Source

Technical (Architect)

  • Document45 and Architech Rera Certificate( B-Wing).pdf · uploaded 26 Jun 2019Source

Technical (Engineer)

  • Document3.pdf · uploaded 30 Mar 2018Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel S NO 39 H NO 1

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
1BHK, 5BHK & more, Office space, Shop98 units in all
Address
S No 39 H No 1, Maharashtra, KatemanevaliPIN 421306
Village
Katemanevali, Kalyan taluka
Land area for this project
3,131 sq m (33,702 sq ft)
Permissible built-up area
2,530 sq m (27,235 sq ft)
Sanctioned built-up area
2,530 sq m (27,235 sq ft)
Designated bank account
196
Developed in phases
Yes

Survey, CTS, gat or plot numbers

S NO 39 H NO 1

Land as published on MahaRERA's project page

S NO 39 H NO 1

Boundaries

North
S No 38
South
18 Mtr Wide D P Road
East
S No 30 And 35
West
S No 39 H No 3

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking98 units

54 of 98 units booked (55%), as the promoter reported to MahaRERA

1BHK · 75 units5BHK & more · 1 unitOffice space · 7 unitsShop · 15 units
BuildingTypeCarpet areaUnitsBooked
Ritesh Empire1BHK30.57 sq m · 329 sq ft53
Ritesh Empire1BHK30.63 sq m · 330 sq ft43
Ritesh Empire1BHK30.79 sq m · 331 sq ft10
Ritesh Empire1BHK32.65 sq m · 351 sq ft20
Ritesh Empire1BHK32.94 sq m · 355 sq ft42
Ritesh Empire1BHK33.16 sq m · 357 sq ft10
Ritesh Empire1BHK33.27 sq m · 358 sq ft10
Ritesh Empire1BHK33.6 sq m · 362 sq ft33
Show all 43 unit rowsShow fewer unit rows
BuildingTypeCarpet areaUnitsBooked
Ritesh Empire1BHK33.67 sq m · 362 sq ft31
Ritesh Empire1BHK33.74 sq m · 363 sq ft76
Ritesh Empire1BHK34.18 sq m · 368 sq ft20
Ritesh Empire1BHK34.67 sq m · 373 sq ft52
Ritesh Empire1BHK34.7 sq m · 374 sq ft53
Ritesh Empire1BHK34.71 sq m · 374 sq ft54
Ritesh Empire1BHK34.73 sq m · 374 sq ft42
Ritesh Empire1BHK34.79 sq m · 374 sq ft53
Ritesh Empire1BHK45.73 sq m · 492 sq ft10
Ritesh Empire1BHK45.96 sq m · 495 sq ft10
Ritesh Empire1BHK46.27 sq m · 498 sq ft44
Ritesh Empire1BHK46.34 sq m · 499 sq ft33
Ritesh Empire1BHK46.4 sq m · 499 sq ft44
Ritesh Empire1BHK46.44 sq m · 500 sq ft33
Ritesh Empire1BHK46.75 sq m · 503 sq ft10
Ritesh Empire1BHK47.79 sq m · 514 sq ft11
Ritesh Empire5BHK & more20.35 sq m · 219 sq ft11
Ritesh EmpireOffice space37.63 sq m · 405 sq ft10
Ritesh EmpireOffice space39.3 sq m · 423 sq ft20
Ritesh EmpireOffice space41.74 sq m · 449 sq ft10
Ritesh EmpireOffice space43.18 sq m · 465 sq ft10
Ritesh EmpireOffice space48.83 sq m · 526 sq ft10
Ritesh EmpireOffice space57.08 sq m · 614 sq ft10
Ritesh EmpireShop14.23 sq m · 153 sq ft10
Ritesh EmpireShop17.4 sq m · 187 sq ft21
Ritesh EmpireShop17.7 sq m · 191 sq ft10
Ritesh EmpireShop17.73 sq m · 191 sq ft10
Ritesh EmpireShop19.56 sq m · 211 sq ft11
Ritesh EmpireShop21.2 sq m · 228 sq ft20
Ritesh EmpireShop23.1 sq m · 249 sq ft32
Ritesh EmpireShop24.11 sq m · 260 sq ft10
Ritesh EmpireShop27.42 sq m · 295 sq ft10
Ritesh EmpireShop27.63 sq m · 297 sq ft11
Ritesh EmpireShop40.55 sq m · 436 sq ft11
Ritesh Empire IIShop—00

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals2

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectAnniruddha S Dastane—
EngineerEntech Consultant—

Source: MahaRERA project page. Contact details are not shown.

Other projects in Katemanevali

All 59 projects in Katemanevali · Compare Ritesh Empire with another project

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology