Trimurti One
Deedo IDDP-THN-90GECompletion was pushed back 4 months, to Apr 2029; no MahaRERA orders on record; 20% of its units are booked.
Katemanevali, Thane 421306 · by Trimurti Construction
Buying a flat here?
See every deed registered on it.
Completion was pushed back 4 months, to Apr 2029
- This projectRegistered 31 Jan 2024, completion promised 31 Dec 2028, revised to 30 Apr 2029.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales first, then rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP51700054547
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51700054547 | 31 Jan 2024 | 31 Dec 2028 | 30 Apr 2029 | Trimurti Construction | Project page |
Documents72
1 document held by Deedo, 71 filings listed on MahaRERA's project page
Finance
- PAN CardTRIMURTI FIRM pan.PDF · uploaded 31 Jul 2023Source
Legal
- Declaration Form BFORM B TRIMURTI.pdf · uploaded 2 Aug 2023Source
- Legal Title reportTITLE SEARCH REPORT FINAL.pdf · uploaded 10 Oct 2023Source
- Other – LegalPOA.pdf · uploaded 4 Dec 2023Source
- Other – LegalTitle Report.pdf · uploaded 27 Dec 2023Source
- Other – LegalForm B Landowner.pdf · uploaded 8 Jan 2024Source
Migrated
- 1 PAN CardTRIMURTI FIRM pan.PDF · uploaded 31 Jul 2023Source
Show all 72 documentsShow fewer documents
Migrated
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameBANK LETTER.pdf · uploaded 31 Jul 2023Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate.pdf · uploaded 1 Aug 2023Source
- 1 Declaration in FORM BFORM B TRIMURTI.pdf · uploaded 2 Aug 2023Source
- 1 Copy of Layout Approval (in case of layout)scan0028.pdf · uploaded 3 Aug 2023Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENGINEER CERTIFICATE.pdf · uploaded 3 Aug 2023Source
- 1 Disclosure of Interest in Other Real Estate OrganizationsHariram Druvanarayan Chaurasia.pdf · uploaded 3 Aug 2023Source
- 2 Disclosure of Interest in Other Real Estate OrganizationsKamesh Ramesh Jadhav.pdf · uploaded 3 Aug 2023Source
- 3 Disclosure of Interest in Other Real Estate OrganizationsMeena jaichand kesharwani.pdf · uploaded 3 Aug 2023Source
- 4 Disclosure of Interest in Other Real Estate OrganizationsRamesh sudam Jadhav.pdf · uploaded 3 Aug 2023Source
- 5 Disclosure of Interest in Other Real Estate OrganizationsRavi jaichand Kesharwani.pdf · uploaded 3 Aug 2023Source
- 6 Disclosure of Interest in Other Real Estate OrganizationsVaibhav Chaurasia.pdf · uploaded 3 Aug 2023Source
- 1 Proforma of Allotment letterfinal allotment.pdf · uploaded 3 Aug 2023Source
- 1 a Details of encumbrances concerned to FinanceFinance_legal_merged.pdf · uploaded 5 Aug 2023Source
- 1 b Details of encumbrances concerned to LegalFinance_legal_merged.pdf · uploaded 5 Aug 2023Source
- 1 Commencement Certificates / NA Order for plotted developmentCC.pdf · uploaded 5 Aug 2023Source
- 1 CERSAI detailsCERSAI NEW.pdf · uploaded 5 Aug 2023Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)organized.pdf · uploaded 5 Aug 2023Source
- 1 Deviation Report with respect to Allotment letterDeviation 2.pdf · uploaded 5 Aug 2023Source
- 1 Deviation Report with respect to model copy of AgreementDeviation 1.pdf · uploaded 5 Aug 2023Source
- 1 Copy of the legal title reportTITLE SEARCH REPORT FINAL.pdf · uploaded 10 Oct 2023Source
- 1 Building Plan Approval / NA Order for plotted development35-4 Plan Trimurti one.pdf · uploaded 17 Oct 2023Source
- 2 Building Plan Approval / NA Order for plotted development35-4 pla Trimurti one.pdf · uploaded 17 Oct 2023Source
- 2 CERSAI detailsCersai.pdf · uploaded 17 Oct 2023Source
- 1 Proforma of Agreement for saleAGREEMENT FOR SALE_11zon (1).pdf · uploaded 17 Oct 2023Source
- 1 Declaration about Commencement Certificatecommencement Declaration.pdf · uploaded 4 Dec 2023Source
- 1 Other – LegalPOA.pdf · uploaded 4 Dec 2023Source
- 1 Other – TechnicalNew Ca Certificate.pdf · uploaded 4 Dec 2023Source
- 2 Other – LegalTitle Report.pdf · uploaded 27 Dec 2023Source
- 3 Other – LegalForm B Landowner.pdf · uploaded 8 Jan 2024Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Trimurti Construction (ONE) Engineer certificate.pdf · uploaded 7 May 2024Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Trimurti One Form 3.pdf · uploaded 7 May 2024Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 20 Jul 2024Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 20 Jul 2024Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 30-9.pdf · uploaded 20 Oct 2024Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 30-9.pdf · uploaded 20 Oct 2024Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECT (3).pdf · uploaded 22 Oct 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Trimurti One.pdf · uploaded 31 Oct 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 trimurti.pdf · uploaded 29 Jan 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Trimurti.pdf · uploaded 29 Jan 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Trimurti One.pdf · uploaded 30 Jan 2025Source
- Form 5 (FY 2024-2025)Trimurti_compressed.pdf · uploaded 30 Sep 2025Source
- Withdrawal Update Form 1Form 1 Dec 25.pdf · uploaded 14 Apr 2026Source
- Withdrawal Update Form 1Form 1 Dec 25.pdf · uploaded 14 Apr 2026Source
- Withdrawal Update Form 2form 2.pdf · uploaded 14 Apr 2026Source
- Withdrawal Update Form 2Form 2 Dec 25.pdf · uploaded 14 Apr 2026Source
- Withdrawal Update Form 3ca certificate.pdf · uploaded 14 Apr 2026Source
- Withdrawal Update Form 3Q3 ca certificate.pdf · uploaded 14 Apr 2026Source
- Withdrawal Update Form 1Trimurti Architect.pdf · uploaded 11 May 2026Source
- Withdrawal Update Form 2Trimurti one Engineer certificate gaurav (1).pdf · uploaded 11 May 2026Source
- Withdrawal Update Form 3Form 3 signed.pdf · uploaded 11 May 2026Source
- Withdrawal Update Form 1Architect.pdf · uploaded 5 Aug 2026Source
- Withdrawal Update Form 2Engineer.pdf · uploaded 5 Aug 2026Source
- Withdrawal Update Form 3Ca certificate.pdf · uploaded 5 Aug 2026Source
- Form 5 (FY 2025-2026)TRIMURTI FORM 5.pdf · uploaded 26 Sep 2026Source
Technical
Technical (Architect)
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel Survey No 35 H .No 4
As registered with MahaRERA and published on its project page
- Project type
- Others
- Status on MahaRERA
- Certificate Signed
- Unit types
- 1BHK, 2BHK, 3BHK, Office space, Shop118 units in all
- Address
- Survey No 35 H .No 4, MOUJE, KalyanPIN 421306
- Village
- Katemanevali, Kalyan taluka
- Land area for this project
- 1,950 sq m (20,990 sq ft)
- Permissible built-up area
- 6,658 sq m (71,671 sq ft)
- Sanctioned built-up area
- 6,658 sq m (71,671 sq ft)
- Designated bank account
- 28
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
Survey No 35 H .No 4
Boundaries
- North
- 0
- South
- 0
- East
- 0
- West
- 0
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking118 units
24 of 118 units booked (20%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 36.11 sq m · 389 sq ft | 13 | 2 |
| 1BHK | 37.09 sq m · 399 sq ft | 12 | 0 |
| 1BHK | 39.38 sq m · 424 sq ft | 13 | 2 |
| 1BHK | 39.46 sq m · 425 sq ft | 13 | 7 |
| 2BHK | 47.78 sq m · 514 sq ft | 10 | 7 |
| 2BHK | 47.87 sq m · 515 sq ft | 12 | 4 |
| 2BHK | 48.51 sq m · 522 sq ft | 22 | 1 |
| 3BHK | 65.28 sq m · 703 sq ft | 2 | 1 |
Show all 17 unit rowsShow fewer unit rows
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| Office space | 11.68 sq m · 126 sq ft | 1 | 0 |
| Office space | 14.19 sq m · 153 sq ft | 1 | 0 |
| Office space | 14.75 sq m · 159 sq ft | 1 | 0 |
| Office space | 15.42 sq m · 166 sq ft | 2 | 0 |
| Office space | 15.83 sq m · 170 sq ft | 4 | 0 |
| Office space | 16.11 sq m · 173 sq ft | 2 | 0 |
| Shop | 22.46 sq m · 242 sq ft | 2 | 0 |
| Shop | 28.33 sq m · 305 sq ft | 2 | 0 |
| Shop | 30.59 sq m · 329 sq ft | 6 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals5
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Shirish G Nachane | — |
| Chartered accountant | Girish Tarwani | — |
| Chartered accountant | Vinesh Ahuja | — |
| Engineer | Gaurav Chaurasia | — |
| Other | Jaysukh Lalji Patel | — |
Source: MahaRERA project page. Contact details are not shown.
Other projects in Katemanevali
- Royal HillsRERA PM1330002602131
- Sai Dream World Building No 04 Sai Dream VertexRERA PM1330002602039
- Sai Dream World Building No 01 (Sai Dream Signature)RERA PM1330002602012
- Samarth AlturaRERA PR1330002601411
- Ananntshree PearlRERA PM1330002600358
- Madhu Nirmal HeightsRERA PR1330002502556
- Matrix By MadhavRERA PC1330002502042
- Ramayan Co-Operative Housing Society LimitedRERA PR1330002501858
All 59 projects in Katemanevali · Compare Trimurti One with another project