Lahagaon, Pune
6 in 10 MahaRERA registrations here have pushed their completion date back.
RERA projects23
Registrations25some projects hold several
Completion still due1213 past their date
Median extension4 months64% of registrations extended
Regulatory cases0none on MahaRERA's lists
Projects in Lahagaon
23 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| 108 ElevateM K Infra | PM1260002502706 | 11 Mar 2026 | 31 Dec 2030 | 30 Apr 2031 | Extended 4 mo | 0 |
| Ritzz CityRitzz Developers | PR1260002500467 | 4 Aug 2025 | 30 Jun 2029 | 30 Oct 2029 | Extended 4 mo | 0 |
| Namay ResidencyMangal Properties | P52100079503 | 10 Mar 2025 | 31 Dec 2027 | 30 Apr 2028 | Extended 4 mo | 0 |
| Belmont SkydaleBelmont Realty | P52100079413 | 4 Mar 2025 | 31 Aug 2028 | 31 Dec 2028 | Extended 4 mo | 0 |
| SkyscapeSkyrise Buildcon LLP | P52100079185 | 14 Feb 2025 | 30 Jun 2028 | 30 Oct 2028 | Extended 4 mo | 0 |
| Aayush ExoticaAayush Properties | PR1260002400012 | 25 Sep 2024 | 30 Sep 2026 | 30 Jan 2027 | Extended 4 mo | 0 |
| Belmont SkyverseBelmont Realty | P52100055743 | 16 Apr 2024 | 31 Aug 2028 | 31 Dec 2028 | Extended 4 mo | 0 |
| Edificio ResidencyM/s Edificio Developers LLP | P52100054833 | 15 Feb 2024 | 31 Dec 2027 | 30 Apr 2028 | Extended 4 mo | 0 |
| Panora 276M/s Shri Buildcon | P52100053182 | 17 Oct 2023 | 31 Dec 2028 | 30 Apr 2029 | Extended 4 mo | 0 |
| Vanity ViewRB Developers | P52100052213 | 31 Jul 2023 | 31 Dec 2026 | 30 Apr 2027 | Extended 4 mo | 0 |
| Skyways HarmonyM/S Pranam Buildcon | P52100034806 | 28 Apr 2022 | 31 Dec 2024 | 31 Dec 2024 | Promised date passed | 0 |
| Skyways HorizonM/S Hans Associates | P52100034904 | 28 Apr 2022 | 31 Dec 2026 | 30 Apr 2027 | Extended 4 mo | 0 |
| Nirvana Life CountyKhandve Nirvana Realty | P52100031558 | 31 Oct 2021 | 31 Mar 2025 | 31 Mar 2025 | Promised date passed | 0 |
| Kumar MangalamS S Construction & Developers | P52100031272 | 15 Oct 2021 | 31 Oct 2022 | 31 Oct 2022 | Promised date passed | 0 |
| Aastha ResidencyAastha Developers | P52100021728 | 22 Jul 2019 | 30 Sep 2023 | 30 Sep 2023 | Promised date passed | 0 |
| Jd Green Paradise B WingShreeJagadguru Developers | P52100019751 | 5 Mar 2019 | 30 Dec 2020 | 15 Sep 2023 | Extended 33 mo | 0 |
| Yogin Belva Project AYogin Associates | P52100016972 | 26 Jun 2018 | 30 Dec 2022 | 30 Dec 2022 | Promised date passed | 0 |
| RadhekrishnaRajesh Ramchandra Mehta | P52100016670 | 5 Jun 2018 | 30 Mar 2022 | 30 Mar 2022 | Promised date passed | 0 |
| Shubh NilayaShubh Realtors | P52100015446 | 26 Feb 2018 | 30 Dec 2021 | 30 Dec 2021 | Promised date passed | 0 |
| Sanskruti HomesPavan Builder | P52100012935 | 7 Sep 2017 | 31 Dec 2019 | 30 Dec 2021 | Extended 24 mo | 0 |
| Oxy BonitaShreyas Buildcon | P52100006070, P52100014711 | 14 Aug 2017 | 31 Dec 2019 | 30 Dec 2022 | Extended 36 mo | 0 |
| Pankaj AasmaanPankaj Developers | P52100005649, P52100009665 | 11 Aug 2017 | 31 Dec 2027 | 30 Apr 2028 | Extended 4 mo | 0 |
| OptimusSiddhesh properties | P52100000803 | 23 Jul 2017 | 31 Dec 2018 | 31 Dec 2019 | Extended 12 mo | 0 |
Nearby: other localities in Haveli
Most active promoters
- Belmont Realty2 projects
- Aastha Developers1 project
- Aayush Properties1 project
- Khandve Nirvana Realty1 project
- Mangal Properties1 project
- M K Infra1 project
- M/s Edificio Developers LLP1 project
- M/S Hans Associates1 project
- M/S Pranam Buildcon1 project
- M/s Shri Buildcon1 project
Data through11 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Methodology