Lahagaon, Pune

6 in 10 MahaRERA registrations here have pushed their completion date back.

RERA projects23
Registrations25some projects hold several
Completion still due1213 past their date
Median extension4 months64% of registrations extended
Regulatory cases0none on MahaRERA's lists
Lahagaon market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Projects in Lahagaon

23 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
108 ElevateM K InfraPM126000250270611 Mar 202631 Dec 203030 Apr 2031Extended 4 mo0
Ritzz CityRitzz DevelopersPR12600025004674 Aug 202530 Jun 202930 Oct 2029Extended 4 mo0
Namay ResidencyMangal PropertiesP5210007950310 Mar 202531 Dec 202730 Apr 2028Extended 4 mo0
Belmont SkydaleBelmont RealtyP521000794134 Mar 202531 Aug 202831 Dec 2028Extended 4 mo0
SkyscapeSkyrise Buildcon LLPP5210007918514 Feb 202530 Jun 202830 Oct 2028Extended 4 mo0
Aayush ExoticaAayush PropertiesPR126000240001225 Sep 202430 Sep 202630 Jan 2027Extended 4 mo0
Belmont SkyverseBelmont RealtyP5210005574316 Apr 202431 Aug 202831 Dec 2028Extended 4 mo0
Edificio ResidencyM/s Edificio Developers LLPP5210005483315 Feb 202431 Dec 202730 Apr 2028Extended 4 mo0
Panora 276M/s Shri BuildconP5210005318217 Oct 202331 Dec 202830 Apr 2029Extended 4 mo0
Vanity ViewRB DevelopersP5210005221331 Jul 202331 Dec 202630 Apr 2027Extended 4 mo0
Skyways HarmonyM/S Pranam BuildconP5210003480628 Apr 202231 Dec 202431 Dec 2024Promised date passed0
Skyways HorizonM/S Hans AssociatesP5210003490428 Apr 202231 Dec 202630 Apr 2027Extended 4 mo0
Nirvana Life CountyKhandve Nirvana RealtyP5210003155831 Oct 202131 Mar 202531 Mar 2025Promised date passed0
Kumar MangalamS S Construction & DevelopersP5210003127215 Oct 202131 Oct 202231 Oct 2022Promised date passed0
Aastha ResidencyAastha DevelopersP5210002172822 Jul 201930 Sep 202330 Sep 2023Promised date passed0
Jd Green Paradise B WingShreeJagadguru DevelopersP521000197515 Mar 201930 Dec 202015 Sep 2023Extended 33 mo0
Yogin Belva Project AYogin AssociatesP5210001697226 Jun 201830 Dec 202230 Dec 2022Promised date passed0
RadhekrishnaRajesh Ramchandra MehtaP521000166705 Jun 201830 Mar 202230 Mar 2022Promised date passed0
Shubh NilayaShubh RealtorsP5210001544626 Feb 201830 Dec 202130 Dec 2021Promised date passed0
Sanskruti HomesPavan BuilderP521000129357 Sep 201731 Dec 201930 Dec 2021Extended 24 mo0
Oxy BonitaShreyas BuildconP52100006070, P5210001471114 Aug 201731 Dec 201930 Dec 2022Extended 36 mo0
Pankaj AasmaanPankaj DevelopersP52100005649, P5210000966511 Aug 201731 Dec 202730 Apr 2028Extended 4 mo0
OptimusSiddhesh propertiesP5210000080323 Jul 201731 Dec 201831 Dec 2019Extended 12 mo0

Most active promoters

  1. Belmont Realty2 projects
  2. Aastha Developers1 project
  3. Aayush Properties1 project
  4. Khandve Nirvana Realty1 project
  5. Mangal Properties1 project
  6. M K Infra1 project
  7. M/s Edificio Developers LLP1 project
  8. M/S Hans Associates1 project
  9. M/S Pranam Buildcon1 project
  10. M/s Shri Buildcon1 project
Data through11 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Methodology