73 projects under 80 MahaRERA registrations, registered 2017–2026. 19% have a completion date extended beyond the one promised.

Locality
73RERA projects
80Registrationssome projects hold several
28Completion still due52 past their completion date
24 monthsMedian extension beyond promised date19% of registrations extended
0Regulatory casesnone on MahaRERA's lists
8Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
201725
20184
20195
20203
20217
20227
202310
202410
20257
20262

Projects in Katraj

73 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
The VantageGiriraj Promoters Private LimitedPC126000250268410 Mar 202631 Dec 2028—Not yet due0
Infinity StudioSBSP PrropertiesPM126000250180716 Dec 202531 Dec 2027—Not yet due0
Habitat SpringHabitat Builders and DevelopersP5210008105227 Nov 20251 May 2028—Not yet due0
Krishna ResidencyM/S Kiran ConstructionsP521000809951 Oct 202530 Jun 2027—Not yet due0
VrindavanM/S Jain Bafna AssociatesPR126000250079215 Sep 202530 Jun 2032—Not yet due0
Vastu ShilpVastu ConstructionPM12600025004865 Aug 202531 Mar 2028—Not yet due0
Saideep DwarkaM/s. Saideep Construction and Land DevelopersP5210008025315 May 202531 Dec 2026—Not yet due0
Karthikeya ResidencyLaxman Kala ConstructionsP521000801715 May 202531 May 2029—Not yet due0
GulmoharArun Pandurang MoreP5210007811825 Nov 202431 Dec 2026—Not yet due0
Siddhi AvenueSiddhivinayak DevelopersP5210007812925 Nov 202431 Dec 2027—Not yet due0
Vastushree Phase-1Vastu ConstructionP5210007748116 Aug 202415 Aug 2026—Promised date passed0
PadmarangSbs PrropertiesP5210007723531 Jul 202431 Mar 2027—Not yet due0
Ivory VistaPhate Kamthe AssociatesP521000554822 Apr 202430 Jun 2027—Not yet due0
Chintamani HeightsAvadhoot DevelopersP521000551224 Mar 202431 Dec 2026—Not yet due0
Golden LakeNarsinh AssociatesP5210005510029 Feb 202431 Dec 2027—Not yet due0
Tcg GardeniaThe Construction & Development Co, The Construction & Development Co.P52100054541, P5210006651731 Jan 202431 Dec 2027—Not yet due0
Green Hill Phase 2D.S. Dhone BuildersP5210005408427 Dec 202331 Dec 2026—Not yet due0
Shree Sadguru KshitijShri Sadguru DevelopersP521000538718 Dec 202331 Dec 2026—Not yet due0
Navkaar HeightsNavkaar Nx Developers LLPP5210005356010 Nov 202331 Dec 2024—Promised date passed0
LAKE TOWN D-6, WING - A and BVenkatesh AssociatesP5210005324823 Oct 202331 Mar 2026—Promised date passed0
Sai NagariSaikedareshwar Developers LLPP52100052977, P52100052996, P52100078517 +110 Oct 202331 Dec 2030—Not yet due0
Mhada-Tcg GardeniaThe Construction & Development CoP521000522869 Aug 202331 Dec 2027—Not yet due0
Chintamani ResidencyG P K DevelopersP521000511651 Jun 202331 Dec 2026—Not yet due0
G. M. KalashG M DevelopersP5210004948215 Feb 202331 Dec 2024—Promised date passed0
Padmashree Phase - INilesh Shashikant OstwalP5210004905430 Jan 202331 Dec 2027—Not yet due0
7th HeavenSwapnpurti AssociatesP521000479291 Dec 202215 Aug 2025—Promised date passed0
Nakshatra ResidencyShree Sairaj DevelopersP5210004615420 Jun 202230 Jun 202530 Jun 2026Extended 12 mo0
Amit SankulGhansham Jagannath DahiwalP5210003517410 May 202225 Mar 2025—Promised date passed0
Akshara GathaParasnath DevelopersP5210003393714 Mar 202230 Jun 2024—Promised date passed0
Dnyaneshwar ApartmentDnyaneshwar Sonba DharpaleP521000336222 Mar 202231 Dec 2024—Promised date passed0
Aakanksha ResidencySharvin Builders LLPP5210003330715 Feb 202231 Dec 202330 Sep 2024Extended 9 mo0
Sky PavilionKiran DevelopersP5210003268824 Jan 202231 Dec 2025—Promised date passed0
Chinmay PrideChinmay PrideP5210003133115 Oct 202123 May 2024—Promised date passed0
Dhanmai AavaasMs Rathi Construction Through Its Proprietor Mr Rajesh Dhanraj RathiP5210002895815 Apr 202131 Mar 2022—Promised date passed0
"Laxminath" Project by "Swastika Landmarks"Sagar Ratan TamhaneP5210002882830 Mar 202130 Sep 2022—Promised date passed0
Akshara GardenNahar RealityP521000284522 Mar 202130 Jun 202231 Mar 2024Extended 21 mo0
Shreepad VallabhM/S Shreepad DevelopersP521000284682 Mar 202130 Jun 2024—Promised date passed0
Chinmay Heritage Phase 2Chinmay HeritageP521000281134 Feb 202123 Nov 2024—Promised date passed0
Panchratna Hills Phase 2Panchratna ConstructionP5210002797621 Jan 202130 Jun 2026—Promised date passed0
Akshara HillsK N K BuildersP5210002720224 Nov 202030 Sep 2022—Promised date passed0
Tcg Gardenia Phase - I Building A BThe Construction & Development CoP5210002662310 Oct 202030 Jun 2025—Promised date passed0
Matoshri Enclavevishal gajanan kenjaleP5210002400114 Jan 202031 Dec 2026—Not yet due0
Samrat SarthakBora Realty LLPP5210002309529 Nov 201928 Feb 2025—Promised date passed0
Sai HomesAnita Kishorkumar JainP5210002208525 Aug 201930 Oct 2023—Promised date passed0
Yashashree IIAashish Promoters & BuildersP5210002098427 May 201930 Dec 2023—Promised date passed0
Agam Darshan Phase IIAkashdeep Constructions Private LimitedP521000204329 Apr 201930 Mar 2024—Promised date passed0
Savali HeritageSavali HeritageP521000151947 Feb 201820 Dec 201930 Dec 2020Extended 12 mo0
Chitamani NivasKrishna Haribhau LohokareP5210001496715 Jan 201830 Dec 2021—Promised date passed0
Pooja NiwasGangotree GreenbuildP521000147752 Jan 201830 Dec 202231 Dec 2024Extended 24 mo0
saijeevanTricon Construction CompanyP5210001454412 Dec 201730 Sep 2018—Promised date passed0
GokuldhamR K AssociatesP521000140587 Nov 201731 Dec 2028—Not yet due0
K.d. HillsKulshree AssociatesP521000134467 Oct 201730 Dec 2023—Promised date passed0
GloriaDrushti DevelopersP521000128087 Sep 201730 Dec 202030 Dec 2020Promised date passed0
Shyam ViharKrishna DevelopersP521000129117 Sep 201731 Mar 2018—Promised date passed0
Praga SerenePratik ConstrP5210001125731 Aug 201730 Jun 202129 Dec 2022Extended 18 mo0
Vaishnavi ComplexVaishnavi ConstructionsP5210001135531 Aug 201731 Jul 201930 Jun 2025Extended 71 mo0
Wehome LakesideWehome lakesideP5210001190531 Aug 201731 Oct 2018—Promised date passed0
Gokul ResidencyVastu And Chopra DevelopersP5210001044327 Aug 201731 Dec 201930 Dec 2021Extended 24 mo0
Lush GreenPragati ConstructionsP5210001019624 Aug 201731 Dec 201930 Jun 2022Extended 30 mo0
Rituparna ResidenceMitaali GroopP5210001023624 Aug 201730 Nov 2019—Promised date passed0
Lake TierraAnand ConstructionsP5210000960422 Aug 201730 Dec 2026—Not yet due0
Pietra EnclavePietra InfrastructureP5210000982922 Aug 201730 Jun 2018—Promised date passed0
Blossom GardenM S AssociatesP5210000874519 Aug 201731 May 202631 May 2026Promised date passed0
Hamy ParkHamy Construction Pvt LtdP5210000814518 Aug 201730 Mar 2022—Promised date passed0
Shree Sadguru KrupaMaa Pranaam VentureP5210000789918 Aug 201731 Dec 201930 Dec 2021Extended 24 mo0
PanacheTrimurti Sai Nath Infras LLPP52100005287, P52100006198, P52100016181 +111 Aug 201730 Dec 2021—Promised date passed0
VastushreeKalash Realities And DevelopersP5210000536811 Aug 201730 Jun 202131 Jul 2022Extended 13 mo0
Siddhi SamruddhiSanghvi DevelopersP521000032555 Aug 201731 Mar 201923 Nov 2021Extended 32 mo0
Ved - Ashritha Phase IYogvinda Promoters & Developers Pvt. Ltd.P5210000217531 Jul 201714 Feb 202131 Oct 2023Extended 32 mo0
Gagan Unnatii Phase 2Gagan Unnati VenturesP5210000181829 Jul 201731 Mar 201930 Sep 2020Extended 18 mo0
ShriyogA & A AssociatesP5210000169129 Jul 201731 Mar 2019—Promised date passed0
Ashritha Phase IYogvinda Promoters & Developers Pvt. Ltd.P5210000148528 Jul 201728 Dec 201829 Jan 2021Extended 25 mo0
Silver Oak Ph -IIM/S Ashtekar ConstructionsP5210000021910 Jul 20171 Jul 2018—Promised date passed0

Other localities in Haveli

Most active promoters

By projects registered here, as named on MahaRERA.

  1. The Construction & Development Co3 projects
  2. Vastu Construction2 projects
  3. Yogvinda Promoters & Developers Pvt. Ltd.2 projects
  4. A & A Associates1 project
  5. Aashish Promoters & Builders1 project
  6. Akashdeep Constructions Private Limited1 project
  7. Anand Constructions1 project
  8. Anita Kishorkumar Jain1 project
  9. Arun Pandurang More1 project
  10. Avadhoot Developers1 project
Data through11 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology