RERA projects in Ambegaon Bk

817 projects under 163 MahaRERA registrations, registered 2017–2026. 44% have a completion date extended beyond the one promised.

Locality
817RERA projects
163Registrationssome projects hold several
57Completion still due106 past their completion date
4 monthsMedian extension beyond promised date44% of registrations extended
2Regulatory caseson 2 projects
1,034Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
201752
20189
201918
20209
202110
202215
202319
20249
202512
202610

Projects in Ambegaon Bk

817 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Elmont TowersShree Bhairavnath DevelopersPR126000260226713 Oct 202631 Dec 2031—Not yet due0
Balwant EmpireKcnest Housing Corporation LLPPR12600026021265 Oct 202631 Dec 202931 Dec 2029Not yet due0
Bkc PearlRani Maruti LandgePR126000260196618 Sep 202631 Dec 202831 Dec 2028Not yet due0
AviraThe Pride RealtyPR126000260117715 Jul 202631 Dec 202930 Apr 2030Extended 4 mo0
Astonia Royale Phase IV M and N BuildingsAmit Enterprises Housing LimitedPR126202260114513 Jul 202631 Mar 203131 Jul 2031Extended 4 mo0
Sai Aspire SquareShree Aspire VenturesPM12600026010346 Jul 202631 Dec 203030 Apr 2031Extended 4 mo0
Indu Aspire EnclaveIndu Aspire PropertiesPR12600026010102 Jul 202630 Apr 203130 Apr 2031Not yet due0
VrundavanTrinity DevelopersPR12600026006564 Jun 202631 Aug 202931 Dec 2029Extended 4 mo0
Sun ApexJindal Mittal Graha Nirman Pvt. Ltd.PR126101250193930 Dec 202531 Dec 203031 Dec 2030Not yet due0
SkyrisePrathamakruti Construction LLPPM126000250159327 Nov 202531 Dec 202930 Apr 2030Extended 4 mo0
Atrinandan HeightsKrushna DevelopersPR126000250153721 Nov 202531 Dec 203130 Apr 2032Extended 4 mo0
Varad DwarkaVarad RealtyPR12600025011269 Oct 202531 Dec 202830 Apr 2029Extended 4 mo0
Grand View Vismay Building A, B, C, D, EGold Natrajan Developers LLPPR126000250095725 Sep 202531 Dec 202931 Dec 2029Not yet due0
Siddhi AspireSiddhivinayak GroupPR12600025007179 Sep 202530 Jun 202930 Oct 2029Extended 4 mo0
Malhar SkiesCTM Lifespaces LLPPR126000250025711 Jul 202531 Dec 202730 Apr 2028Extended 4 mo0
Chaandrai GalaxySachin DevelopersP5210008030519 May 20251 Apr 20291 Aug 2029Extended 4 mo0
Gv7 Insignia Building B And CM/S Chirag DevelopersP5210008026515 May 202531 Dec 202930 Apr 2030Extended 4 mo0
D Hermes AvenueKhushi Neel DevelopersP5210007879113 Jan 202531 Dec 202730 Apr 2028Extended 4 mo0
PunyashriPunyashri Sahakari Gruhrachana Sanstha MaryaditP5210007876113 Jan 202531 Aug 202731 Dec 2027Extended 4 mo0
Optima AspireOptima HighriseP5210007771223 Oct 202431 Dec 202730 Apr 2028Extended 4 mo0
Tsb CapitalT S B DevelopersP5210007771323 Oct 202431 Dec 202630 Apr 2027Extended 4 mo0
4-FlamingosKondhare Wable AssociatesP5210007715223 Jul 202430 Dec 202830 Apr 2029Extended 4 mo0
Optima Aspire PlusOptima InfraP5210007699616 Jul 202431 Dec 202830 Apr 2029Extended 4 mo0
Basil ShivrajShree Sadguru DevelopersP5210005643931 May 202431 Dec 202730 Apr 2028Extended 4 mo0
Basil VrundavanBasil Promoters LLPP52100056440, PR126101250148631 May 202431 Dec 202830 Apr 2029Extended 4 mo0

Other localities in Haveli

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Chirag Developers7 projects
  2. Amit Enterprises Housing Limited3 projects
  3. Chandrangan Buildcon3 projects
  4. Shree Sadguru Developers3 projects
  5. Adhar Land Developers Pvt. Ltd2 projects
  6. Ganesh Developers & Company2 projects
  7. Gsv Constructions2 projects
  8. Gurukrupa Developers2 projects
  9. Jidnyasa Pramoters & Developers2 projects
  10. Mittal Projects2 projects
Data through15 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology