RERA projects in Ambegaon Bk

2,575 projects under 163 MahaRERA registrations, registered 2017–2026. 44% have a completion date extended beyond the one promised.

Locality
2,575RERA projects
163Registrationssome projects hold several
57Completion still due106 past their completion date
4 monthsMedian extension beyond promised date44% of registrations extended
2Regulatory caseson 2 projects
3,993Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
201752
20189
201918
20209
202110
202215
202319
20249
202512
202610

Projects in Ambegaon Bk

2,575 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Dhiraj RiseonicM/s Dhiraj ConstructionP5210005575816 Apr 202431 Mar 202931 Jul 2029Extended 4 mo0
Venkatesh AnandmayiShree Venkatesh EnterprisesP5210005504626 Feb 202430 Sep 202730 Jan 2028Extended 4 mo0
Airavat B WingAshtavinayak DevelopersP5210005437818 Jan 202417 Nov 202617 Mar 2027Extended 4 mo0
S P PrideS P BuildersP5210005342331 Oct 202330 Sep 202730 Sep 2027Not yet due0
Chandrangan RajgadChandrangan BuildconP521000528945 Oct 202331 Dec 202631 Dec 2026Not yet due0
Durvankur Residency C WingDurvankur DevelopersP521000528225 Oct 202325 May 202625 May 2026Promised date passed0
Chandrangan Revanta C WingChandrangan BuildconP5210005273622 Sep 202331 Dec 202630 Apr 2027Extended 4 mo0
Rajyog C WingSantosh Shankar TatheP5210005215324 Jul 202315 Dec 202615 Dec 2026Not yet due0
Vastudeep AvenueVastudeep ConstructionP5210005202619 Jul 202331 Aug 202631 Dec 2026Extended 4 mo0
CapellaD K RealtiesP521000518777 Jul 202330 Aug 202630 Aug 2026Promised date passed0
Leela SkiesChandrangan Developers & CompanyP5210005154527 Jun 202331 Mar 202531 Mar 2025Promised date passed0
PrimeroseGurukrupa DevelopersP5210005155127 Jun 202331 Mar 202731 Jul 2027Extended 4 mo0
Sai Paradise ResidencySai DevelopersP521000513668 Jun 202330 Jun 202630 Oct 2026Extended 4 mo0
WisteriaJnd ConstructionP5210005110329 May 202331 Dec 202730 Apr 2028Extended 4 mo0
Imperial GoldR K ImperialP5210005061521 Apr 202331 Dec 202531 Dec 2025Promised date passed0
Srp CrystalShreeram DevelopersP5210005054721 Apr 202330 Jun 202630 Oct 2026Extended 4 mo0
Shivay ConstructionShivay ConstructionP521000499996 Mar 202331 Dec 202531 Dec 2025Promised date passed0
Sadguru HeightsAnsh ConstructionP5210004969022 Feb 20231 Jan 20261 Jan 2026Promised date passed0
Nandanvan ColinaSai Sankalp DevelopersP521000493507 Feb 202330 Jun 202630 Jun 2026Promised date passed0
Mbm OrbitSai Sankalp DevelopersP5210004895624 Jan 202319 Sep 202619 Jan 2027Extended 4 mo0
Aishwarya HeightsShree Sadguru ConstructionP521000483903 Jan 202331 Mar 202531 Jul 2026Extended 16 mo0
Guru MantraShree Gurukrupa DevelopersP5210004826522 Dec 202231 Dec 202531 Dec 2025Promised date passed0
Matoshree ResidencyKrushnai DevelopersP5210004825622 Dec 202230 Oct 202431 Dec 2025Extended 14 mo0
Vrundavan KunalNarayan ConstructionP5210004819415 Dec 202231 Dec 202730 Apr 2028Extended 4 mo0
Chandrangan RevantaChandrangan Buildcon LLPP521000475022 Nov 202231 Dec 202830 Apr 2029Extended 4 mo0

Other localities in Haveli

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Chirag Developers7 projects
  2. Amit Enterprises Housing Limited3 projects
  3. Chandrangan Buildcon3 projects
  4. Shree Sadguru Developers3 projects
  5. Adhar Land Developers Pvt. Ltd2 projects
  6. Ganesh Developers & Company2 projects
  7. Gsv Constructions2 projects
  8. Gurukrupa Developers2 projects
  9. Jidnyasa Pramoters & Developers2 projects
  10. Mittal Projects2 projects
Data through20 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology