5 Oct 2023Registered with MahaRERA
25 May 2026Promised completion
1Building
34Units registered
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Certificate Signed
Buildings
1
Unit types
—34 units in all
Address
28/17, S.no 28/17 Amgegaon Bk, Ambegaon BkPIN 411046
Designated bank account
43
Developed in phases
No

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 18.52043, 73.85674
Durvankur Residency C Wing is at latitude 18.52043, longitude 73.85674.

Registered transactions

No registered transactions matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to this project by evidence.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 25 May 2026

The latest completion date on record passed 5 months ago.

Registered
5 Oct 2023
Promised
25 May 2026

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P521000528225 Oct 202325 May 202625 May 2026Durvankur DevelopersProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Durvankur Residency C Wing734

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

34 units registered

— · 34 units
TypeCarpet areaUnits
——34

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Documents

1 document held by Deedo, 94 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardPAN CARD.pdf · uploaded 26 May 2023Source

Legal

  • Declaration Form BFORM B_BALASAHEB MOHOL.pdf · uploaded 26 May 2023Source
  • Declaration Form BFORM B_BALASAHEB WALSEPATIL.pdf · uploaded 26 May 2023Source
  • Declaration Form BFORM B_RAJESH MOHOL.pdf · uploaded 26 May 2023Source
  • Declaration Form BFORM B_SARJERAO SHILIMKAR.pdf · uploaded 26 May 2023Source
  • Legal Title reportTitle final.pdf · uploaded 27 Jun 2023Source

Migrated

  • 1 PAN CardPAN CARD.pdf · uploaded 26 May 2023Source
Show all 95 documentsShow fewer documents

Migrated

  • 1 Copy of Layout Approval (in case of layout)BUILDING PLAN_Temp00001.PDF · uploaded 26 May 2023Source
  • 1 Building Plan Approval / NA Order for plotted developmentBUILDING PLAN_Temp00001.PDF · uploaded 26 May 2023Source
  • 2 Building Plan Approval / NA Order for plotted developmentBUILDING PLAN_Temp00002.PDF · uploaded 26 May 2023Source
  • 3 Building Plan Approval / NA Order for plotted developmentBUILDING PLAN_Temp00003.PDF · uploaded 26 May 2023Source
  • 1 Commencement Certificates / NA Order for plotted developmentCommencement Certificate Scan_compressed.pdf · uploaded 26 May 2023Source
  • 1 Declaration in FORM BFORM B_BALASAHEB MOHOL.pdf · uploaded 26 May 2023Source
  • 2 Declaration in FORM BFORM B_BALASAHEB WALSEPATIL.pdf · uploaded 26 May 2023Source
  • 3 Declaration in FORM BFORM B_RAJESH MOHOL.pdf · uploaded 26 May 2023Source
  • 4 Declaration in FORM BFORM B_SARJERAO SHILIMKAR.pdf · uploaded 26 May 2023Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Letter_compressed.pdf · uploaded 26 May 2023Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 26 May 2023Source
  • 1 Proforma of Agreement for saleRera standered format Durwankur Developers.pdf · uploaded 26 May 2023Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)RERA CERTIFICATE FORM 2_compressed.pdf · uploaded 30 May 2023Source
  • 1 Declaration about Commencement CertificateFormat D.pdf · uploaded 31 May 2023Source
  • 1 CERSAI detailsSelf Declaration CERSAI Reports Scan.pdf · uploaded 31 May 2023Source
  • 1 Proforma of Allotment letterModel Allotment Letter Scan.pdf · uploaded 31 May 2023Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameDeclaration abour Separate Bank Acc Scan.pdf · uploaded 31 May 2023Source
  • 1 Deviation Report with respect to Allotment letterDeclaration for No Deviation in Model Allotment Letter Scan.pdf · uploaded 31 May 2023Source
  • 1 Deviation Report with respect to model copy of AgreementDeviation wrt agreement to sale.pdf · uploaded 31 May 2023Source
  • 1 Copy of the legal title reportTitle final.pdf · uploaded 27 Jun 2023Source
  • 1 a Details of encumbrances concerned to FinanceDeclaration for Legal Encumbrances_Scan.pdf · uploaded 27 Jun 2023Source
  • 2 a Details of encumbrances concerned to FinanceDeclaration for Financial Encumbrances Scan.pdf · uploaded 27 Jun 2023Source
  • 1 b Details of encumbrances concerned to LegalDeclaration for Legal Encumbrances_Scan.pdf · uploaded 27 Jun 2023Source
  • 2 b Details of encumbrances concerned to LegalDeclaration for Financial Encumbrances Scan.pdf · uploaded 27 Jun 2023Source
  • 2 Commencement Certificates / NA Order for plotted developmentPLINTH Checking Certificate.pdf · uploaded 27 Jun 2023Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsDiscl of Inttt of Oth Real Estate Org.pdf · uploaded 27 Jun 2023Source
  • 2 Disclosure of Interest in Other Real Estate OrganizationsBW_Discl of Intt of Oth Real Estate Org.pdf · uploaded 27 Jun 2023Source
  • 3 Disclosure of Interest in Other Real Estate OrganizationsSS_Discl of Intt of Oth Real Estate Org.pdf · uploaded 27 Jun 2023Source
  • 4 Disclosure of Interest in Other Real Estate OrganizationsRM_Discl of Intt of Oth Real Estate Org.pdf · uploaded 27 Jun 2023Source
  • 3 Commencement Certificates / NA Order for plotted developmentmail.pdf · uploaded 26 Sep 2023Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECT LETTER DURVANKUR DEVELOPERS.pdf · uploaded 26 Jan 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENGEENER LETTER DURVANKUR DEVELOPERS.pdf · uploaded 26 Jan 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)ca certificate_merged.pdf · uploaded 26 Jan 2024Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA CERTIFICATE Q4_compressed.pdf · uploaded 19 Nov 2024Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)engineer certificates 23-24 Q4_page-0001.pdf · uploaded 19 Nov 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)architect certificates durvankur developer_page-0001.pdf · uploaded 19 Nov 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)architect certificates durvankur developer_page-0001.pdf · uploaded 19 Nov 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA CERTIFICATE Q4_compressed.pdf · uploaded 19 Nov 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)engineer certificates 23-24 Q4_page-0001.pdf · uploaded 19 Nov 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCH 24-25 Q1.pdf · uploaded 20 Nov 2024Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA CERTIFICATE 24-25 Q1.pdf · uploaded 20 Nov 2024Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCH 24-25 Q1.pdf · uploaded 20 Nov 2024Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA CERTIFICATE 24-25 Q1.pdf · uploaded 20 Nov 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Archect Certificate.pdf · uploaded 14 Jan 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA CERTIFICATE-1-5_merged_compressed.pdf · uploaded 14 Jan 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate.pdf · uploaded 14 Jan 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form no 1.pdf · uploaded 26 Feb 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form no 3_compressed (1).pdf · uploaded 26 Feb 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form no2.pdf · uploaded 26 Feb 2025Source
  • Form 1Form no 1.pdf · uploaded 17 Jun 2025Source
  • Form 2Form no 2.pdf · uploaded 17 Jun 2025Source
  • Form 3Form no 3.pdf · uploaded 17 Jun 2025Source
  • Disclosure of Sold and Booked InventorySold Unsold Inventory.pdf · uploaded 17 Jun 2025Source
  • Withdrawal Update Form 1ARCHITECT LETTER DURVANKUR DEVELOPERS.pdf · uploaded 11 Sep 2025Source
  • Withdrawal Update Form 1ARCHITECT LETTER FORM 1_page-0001.pdf · uploaded 11 Sep 2025Source
  • Withdrawal Update Form 2ENGEENER LETTER DURVANKUR DEVELOPERS.pdf · uploaded 11 Sep 2025Source
  • Withdrawal Update Form 2ENGEENER LETTER DURVANKUR DEVELOPERS.pdf · uploaded 11 Sep 2025Source
  • Withdrawal Update Form 3ca certificate_merged.pdf · uploaded 11 Sep 2025Source
  • Withdrawal Update Form 3Durvankur developers Form no 3.pdf · uploaded 11 Sep 2025Source
  • Withdrawal Update Form 1FORM 1 AR Certifiacte Q2 SEP-2025.pdf · uploaded 28 Mar 2026Source
  • Withdrawal Update Form 1FORM 1 AR Certifiacte Q2 SEP-2025.pdf · uploaded 28 Mar 2026Source
  • Withdrawal Update Form 2FORM 2 EGG Certificate Q2 SEP-2025.pdf · uploaded 28 Mar 2026Source
  • Withdrawal Update Form 2FORM 2 EGG Certificate Q2 SEP-2025.pdf · uploaded 28 Mar 2026Source
  • Withdrawal Update Form 3FORM 3 CA Certificate Q2 SEP-2025.pdf · uploaded 28 Mar 2026Source
  • Withdrawal Update Form 3FORM 3 CA Certificate Q2 SEP-2025.pdf · uploaded 28 Mar 2026Source
  • Withdrawal Update Form 1FORM 1 AR Certifiacte Q2 SEP-2025.pdf · uploaded 30 Mar 2026Source
  • Withdrawal Update Form 1FORM 1 AR Certifiacte Q3 DEC-2025.pdf · uploaded 30 Mar 2026Source
  • Withdrawal Update Form 2FORM 2 EGG Certificate Q2 SEP-2025.pdf · uploaded 30 Mar 2026Source
  • Withdrawal Update Form 2FORM 2 EGG Certificate Q3 DEC-2025.pdf · uploaded 30 Mar 2026Source
  • Withdrawal Update Form 3FORM 3 CA Certificate Q2 SEP-2025.pdf · uploaded 30 Mar 2026Source
  • Withdrawal Update Form 3FORM 3 CA Certificate Q3 DEC-2025_.pdf · uploaded 30 Mar 2026Source

Technical

  • DocumentBUILDING PLAN_Temp00001.PDF · uploaded 26 May 2023Source
  • DocumentBUILDING PLAN_Temp00002.PDF · uploaded 26 May 2023Source
  • DocumentBUILDING PLAN_Temp00003.PDF · uploaded 26 May 2023Source
  • DocumentBUILDING PLAN_Temp00001.PDF · uploaded 26 May 2023Source

Technical (Architect)

  • Documentarchitect certificates durvankur developer_page-0001.pdf · uploaded 19 Nov 2024Source
  • Documentarchitect certificates durvankur developer_page-0001.pdf · uploaded 19 Nov 2024Source
  • DocumentARCH 24-25 Q1.pdf · uploaded 20 Nov 2024Source
  • DocumentARCH 24-25 Q1.pdf · uploaded 20 Nov 2024Source
  • DocumentArchect Certificate.pdf · uploaded 14 Jan 2025Source
  • DocumentForm no 1.pdf · uploaded 26 Feb 2025Source
  • DocumentFORM 1 AR Certifiacte Q3 DEC-2025.pdf · uploaded 30 Mar 2026Source

Technical (Engineer)

  • Documentengineer certificates 23-24 Q4_page-0001.pdf · uploaded 19 Nov 2024Source
  • Documentengineer certificates 23-24 Q4_page-0001.pdf · uploaded 19 Nov 2024Source
  • DocumentEngineer Certificate.pdf · uploaded 14 Jan 2025Source
  • DocumentForm no2.pdf · uploaded 26 Feb 2025Source
  • DocumentFORM 2 EGG Certificate Q3 DEC-2025.pdf · uploaded 30 Mar 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In AMBEGAON Bk, Haveli taluka

Survey, CTS, gat or plot numbers

28/17

Boundaries

North
D P Road
South
Property of Pasambal and Others
East
Amenity Space of PMC
West
Road

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectMr.Rushikesh Gorakh Zagade GORAKH ZAGADE—
Chartered accountantCa B B Awari B Awari—
Chartered accountantNeha Katariya—
EngineerSubhash Mangori & Associates—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology