Skip to content

Nandanvan Colina

Certificate Signed

Ambegaon Bk, Pune 411046 |Promoter: Sai Sankalp Developers

Residential / Group HousingRERAP52100049350
7 Feb 2023Registered with MahaRERA
30 Jun 2026Promised completion
1Building
79Units registered12 booked (15%)
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Buildings
1
Unit types
1BHK, 2BHK, Office space, Showroom79 units in all
Address
S.No. 34 Hissa No. 12/1/1+12/1/2+12/1/3+12/1/4+13B/2A1A/1/2/1/1/1/1/1/1/B+10+11A+11B+12/1/4+41/6 PART, Dehu Road, Ambegaon BudrukPIN 411046
Designated bank account
43
Developed in phases
No

Registered transactions

No registered transactions matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to this project by evidence.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 30 Jun 2026

The latest completion date on record passed 4 months ago.

Registered
7 Feb 2023
Promised
30 Jun 2026

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P521000493507 Feb 202330 Jun 202630 Jun 2026Sai Sankalp DevelopersProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
B1379

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

12 of 79 units booked (15%), as the promoter reported to MahaRERA

1BHK · 12 units2BHK · 60 unitsOffice space · 3 unitsShowroom · 4 units
TypeCarpet areaUnitsBooked
1BHK48.37 sq m · 521 sq ft122
2BHK56.34 sq m · 606 sq ft20
2BHK69.89 sq m · 752 sq ft123
2BHK70.4 sq m · 758 sq ft124
2BHK74.38 sq m · 801 sq ft120
2BHK75.7 sq m · 815 sq ft101
2BHK85.59 sq m · 921 sq ft81
2BHK85.91 sq m · 925 sq ft40
Show all 15 unit rowsShow fewer unit rows
TypeCarpet areaUnitsBooked
Office space58.12 sq m · 626 sq ft10
Office space99.71 sq m · 1,073 sq ft10
Office space105.33 sq m · 1,134 sq ft10
Showroom60.42 sq m · 650 sq ft10
Showroom72.99 sq m · 786 sq ft10
Showroom89.38 sq m · 962 sq ft11
Showroom153.98 sq m · 1,657 sq ft10

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Documents

1 document held by Deedo, 205 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardSai Sankalp PAN Card Original 001.pdf · uploaded 26 Jul 2022Source

Legal

  • Legal Title reportFhale PA 4 AND HALF R.pdf · uploaded 26 Aug 2022Source
  • Legal Title reportShevade 20 R Sales Agreement.pdf · uploaded 26 Aug 2022Source
  • Legal Title reportBagul Kharedi khat 3 and Half R.pdf · uploaded 30 Aug 2022Source
  • Declaration Form BForm- B_.pdf · uploaded 10 Jan 2023Source
  • Legal Title reportFlow Of the title s r no 34_compressed.pdf · uploaded 20 Jan 2023Source
  • Legal Title reportFormat A Legal Title Combined_020323.pdf · uploaded 20 Jan 2023Source
Show all 206 documentsShow fewer documents

Legal

  • Legal Title reportComp Flow of Title Sr No 41.pdf · uploaded 20 Jan 2023Source
  • Declaration Form BAnanta More.pdf · uploaded 20 Jan 2023Source
  • Declaration Form BDeepak Mane.pdf · uploaded 20 Jan 2023Source
  • Declaration Form BNandkumar Beldare.pdf · uploaded 20 Jan 2023Source
  • Declaration Form BPurva More.pdf · uploaded 20 Jan 2023Source
  • Declaration Form BSantosh Mane.pdf · uploaded 20 Jan 2023Source
  • Declaration Form BYuvraj Beldare.pdf · uploaded 20 Jan 2023Source
  • Legal Title reportLegal Title Report(1).pdf · uploaded 3 Nov 2023Source
  • Legal Title report8 Copy of the legal title report_compressed.pdf · uploaded 14 Dec 2023Source
  • Legal Title report9Copy of the legal title report.pdf · uploaded 14 Dec 2023Source

Migrated

  • 1 PAN CardSai Sankalp PAN Card Original 001.pdf · uploaded 26 Jul 2022Source
  • 1 a Details of encumbrances concerned to FinanceNon Encumbrance Certificate.pdf · uploaded 26 Jul 2022Source
  • 1 b Details of encumbrances concerned to LegalAdvocate Title Report.pdf · uploaded 26 Jul 2022Source
  • 1 Copy of Layout Approval (in case of layout)Building Layout.PDF · uploaded 26 Jul 2022Source
  • 1 Building Plan Approval / NA Order for plotted developmentBuilding Layout.PDF · uploaded 26 Jul 2022Source
  • 1 Commencement Certificates / NA Order for plotted developmentCommencement Certificate (1).pdf · uploaded 26 Jul 2022Source
  • 1 Declaration about Commencement CertificateFORMAT D -DECLARATION ABOUT COMMENCEMNT CERTIFICATE.pdf · uploaded 26 Jul 2022Source
  • 1 CERSAI detailsCERSAI DECLARATION.pdf · uploaded 26 Jul 2022Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameBank Details.pdf · uploaded 26 Jul 2022Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate.pdf · uploaded 25 Aug 2022Source
  • 1 Copy of the legal title reportFhale PA 4 AND HALF R.pdf · uploaded 26 Aug 2022Source
  • 2 Copy of the legal title reportShevade 20 R Sales Agreement.pdf · uploaded 26 Aug 2022Source
  • 3 Copy of the legal title reportBagul Kharedi khat 3 and Half R.pdf · uploaded 30 Aug 2022Source
  • 2 Copy of Layout Approval (in case of layout)Temp00018.PDF · uploaded 30 Aug 2022Source
  • 3 Copy of Layout Approval (in case of layout)Temp00022.PDF · uploaded 30 Aug 2022Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineers Certificate Form 2.pdf · uploaded 30 Aug 2022Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - Sai Sankalp.pdf · uploaded 30 Aug 2022Source
  • 2 a Details of encumbrances concerned to FinanceNon Encumbrance Certificate.pdf · uploaded 21 Sep 2022Source
  • 2 Declaration about Commencement CertificateDeclaration for Commencement.pdf · uploaded 21 Sep 2022Source
  • 2 CERSAI detailsCERSAI_Search_Report_Nandnavan Colina.pdf · uploaded 21 Sep 2022Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 with Promoters Confirmations.pdf · uploaded 21 Sep 2022Source
  • 2 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameDeclaration for Seperate Bank Account-Format A.pdf · uploaded 21 Sep 2022Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)form 3 rera_1_11zon.pdf · uploaded 4 Oct 2022Source
  • 3 a Details of encumbrances concerned to FinanceEncumbrances Letter.pdf · uploaded 5 Nov 2022Source
  • 2 b Details of encumbrances concerned to LegalEncumbrances Letter.pdf · uploaded 5 Nov 2022Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 5 Nov 2022Source
  • 1 Proforma of Agreement for saleBooking Agreement - COLINA - B - Wing.pdf · uploaded 5 Nov 2022Source
  • 1 Proforma of Allotment letterMODEL FORM OF ALLOTMENT LETTER.pdf · uploaded 24 Nov 2022Source
  • 1 Deviation Report with respect to Allotment letterDaviation Sheet_Allotment Letter.pdf · uploaded 24 Nov 2022Source
  • 1 Deviation Report with respect to model copy of AgreementDaviation Sheet_Agreement.pdf · uploaded 24 Nov 2022Source
  • 2 Proforma of Agreement for saleBooking Agreement COLINA B Wing.pdf · uploaded 29 Nov 2022Source
  • 1 Disclosure of Interest in Other Real Estate Organizationscombinepdfcompress.pdf · uploaded 6 Jan 2023Source
  • 1 Declaration in FORM BForm- B_.pdf · uploaded 10 Jan 2023Source
  • 4 Copy of the legal title reportFlow Of the title s r no 34_compressed.pdf · uploaded 20 Jan 2023Source
  • 5 Copy of the legal title reportFormat A Legal Title Combined_020323.pdf · uploaded 20 Jan 2023Source
  • 6 Copy of the legal title reportComp Flow of Title Sr No 41.pdf · uploaded 20 Jan 2023Source
  • 2 Declaration in FORM BAnanta More.pdf · uploaded 20 Jan 2023Source
  • 3 Declaration in FORM BDeepak Mane.pdf · uploaded 20 Jan 2023Source
  • 4 Declaration in FORM BNandkumar Beldare.pdf · uploaded 20 Jan 2023Source
  • 5 Declaration in FORM BPurva More.pdf · uploaded 20 Jan 2023Source
  • 6 Declaration in FORM BSantosh Mane.pdf · uploaded 20 Jan 2023Source
  • 7 Declaration in FORM BYuvraj Beldare.pdf · uploaded 20 Jan 2023Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architects B- Nandanvan.pdf · uploaded 21 Aug 2023Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer B- Nandanvan.pdf · uploaded 21 Aug 2023Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Nandan Colina FY 22-23 Q4.pdf · uploaded 21 Aug 2023Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architecs Certificate Nandanvan.pdf · uploaded 29 Aug 2023Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineers certificates Nandanvan.pdf · uploaded 29 Aug 2023Source
  • 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)Nandan Colina Form 3 Q1 2324_compressed.pdf · uploaded 29 Aug 2023Source
  • 7 Copy of the legal title reportLegal Title Report(1).pdf · uploaded 3 Nov 2023Source
  • 2 Building Plan Approval / NA Order for plotted developmentTemp00002.PDF · uploaded 3 Nov 2023Source
  • 3 Building Plan Approval / NA Order for plotted developmentTemp00003.PDF · uploaded 3 Nov 2023Source
  • 4 Building Plan Approval / NA Order for plotted developmentTemp00004.PDF · uploaded 3 Nov 2023Source
  • 5 Building Plan Approval / NA Order for plotted developmentTemp00005.PDF · uploaded 3 Nov 2023Source
  • 6 Building Plan Approval / NA Order for plotted developmentTemp00006.PDF · uploaded 3 Nov 2023Source
  • 2 Commencement Certificates / NA Order for plotted developmentRevised CC_11zon.pdf · uploaded 3 Nov 2023Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architects - B WING.pdf · uploaded 3 Nov 2023Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineers Certificate - Nandanvan Colina.pdf · uploaded 4 Nov 2023Source
  • 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)Nandanvan Colina - FORM 3_11zon.pdf · uploaded 4 Nov 2023Source
  • 7 Building Plan Approval / NA Order for plotted developmentTemp00002_compressed.pdf · uploaded 21 Nov 2023Source
  • 8 Copy of the legal title report8 Copy of the legal title report_compressed.pdf · uploaded 14 Dec 2023Source
  • 9 Copy of the legal title report9Copy of the legal title report.pdf · uploaded 14 Dec 2023Source
  • 3 Proforma of Agreement for saleAgreement-COLINA-B-Wing.pdf · uploaded 14 Dec 2023Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate.pdf · uploaded 2 Mar 2024Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineers Certificates.pdf · uploaded 2 Mar 2024Source
  • 8 CA Certificate on Project Cost & Fund withdrawal (Form 3)Nandanvan Form 3 Q 3.pdf · uploaded 2 Mar 2024Source
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)Nandanvan Architets Certificate.pdf · uploaded 30 May 2024Source
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)Eng Nandanvan Q4.pdf · uploaded 30 May 2024Source
  • 9 CA Certificate on Project Cost & Fund withdrawal (Form 3)Nandanvan B CA 2.pdf · uploaded 30 May 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Nandanvan - Architects Certif.pdf · uploaded 8 Nov 2024Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Nandanvan Form 3 Q 1_Scanned_11zon (1).pdf · uploaded 8 Nov 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Nandanvan_Q2_form3_11zon.pdf · uploaded 8 Nov 2024Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Nananvan_Eng_Certificate_Q1 (1).pdf · uploaded 8 Nov 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Nandanvan_Eng_Q2.pdf · uploaded 8 Nov 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Nandanvan Architects.pdf · uploaded 11 Nov 2024Source
  • 2 Copy of Layout Approval (in case of layout)B wing Master Plan_11zon.pdf · uploaded 7 Mar 2025Source
  • 1 Copy of Layout Approval (in case of layout)B wing Master Plan_11zon.pdf · uploaded 7 Mar 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect certificate.pdf · uploaded 8 Mar 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 NC Q 3_11zon.pdf · uploaded 8 Mar 2025Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)NC Form 3 Q3_compressed.pdf · uploaded 8 Mar 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate.pdf · uploaded 8 Mar 2025Source
  • 4 Building Plan Approval / NA Order for plotted developmentscan_20250131113920_11zon.pdf · uploaded 8 Mar 2025Source
  • 11 Building Plan Approval / NA Order for plotted developmentscan_20250131114452_11zon.pdf · uploaded 8 Mar 2025Source
  • 10 Building Plan Approval / NA Order for plotted developmentscan_20250131114357_11zon.pdf · uploaded 8 Mar 2025Source
  • 9 Building Plan Approval / NA Order for plotted developmentscan_20250131114324_11zon.pdf · uploaded 8 Mar 2025Source
  • 8 Building Plan Approval / NA Order for plotted developmentscan_20250131114222_11zon.pdf · uploaded 8 Mar 2025Source
  • 7 Building Plan Approval / NA Order for plotted developmentscan_20250131114048_11zon.pdf · uploaded 8 Mar 2025Source
  • 6 Building Plan Approval / NA Order for plotted developmentscan_20250131114019_11zon.pdf · uploaded 8 Mar 2025Source
  • 5 Building Plan Approval / NA Order for plotted developmentscan_20250131113950_11zon.pdf · uploaded 8 Mar 2025Source
  • 3 Building Plan Approval / NA Order for plotted developmentB wing MHADA Plan_11zon.pdf · uploaded 8 Mar 2025Source
  • 2 Building Plan Approval / NA Order for plotted developmentB wing Mezzanine Floor Plan_11zon.pdf · uploaded 8 Mar 2025Source
  • 1 Building Plan Approval / NA Order for plotted developmentB wing Master Plan_11zon.pdf · uploaded 8 Mar 2025Source
  • 1 Disclosure of sold/ booked inventoryDISCLOSER OF SOLD BOOKED INVENTORY Page 1 001.pdf · uploaded 9 Mar 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Arch- Nand.pdf · uploaded 25 Jun 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)fORM-3_11zon.pdf · uploaded 25 Jun 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engg - Nand.pdf · uploaded 25 Jun 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Arch- Nand.pdf · uploaded 25 Jun 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)fORM-3_11zon.pdf · uploaded 25 Jun 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engg - Nand.pdf · uploaded 25 Jun 2025Source
  • Form 1Arc Certificate_Nandanvan.pdf · uploaded 26 Jul 2025Source
  • Form 2Eng Certificate_Nandanvan.pdf · uploaded 26 Jul 2025Source
  • Form 3Form_3.pdf · uploaded 26 Jul 2025Source
  • Disclosure of Sold and Booked InventorySold unsold_NANDANVAN COLINA.pdf · uploaded 26 Jul 2025Source
  • Form 12 Architect’s Certificate of Percentage of Completion of Work (Form 1).pdf · uploaded 18 Aug 2025Source
  • Form 13 Architect’s Certificate of Percentage of Completion of Work (Form 1).pdf · uploaded 18 Aug 2025Source
  • Form 14 Architect’s Certificate of Percentage of Completion of Work (Form 1).pdf · uploaded 18 Aug 2025Source
  • Form 15 Architect’s Certificate of Percentage of Completion of Work (Form 1).pdf · uploaded 18 Aug 2025Source
  • Form 15 Architect’s Certificate of Percentage of Completion of Work (Form 1).pdf · uploaded 18 Aug 2025Source
  • Form 17 Architect’s Certificate of Percentage of Completion of Work (Form 1).pdf · uploaded 18 Aug 2025Source
  • Form 18 Architect’s Certificate of Percentage of Completion of Work (Form 1).pdf · uploaded 18 Aug 2025Source
  • Form 19 Architect’s Certificate of Percentage of Completion of Work (Form 1).pdf · uploaded 18 Aug 2025Source
  • Form 110 Architect’s Certificate of Percentage of Completion of Work (Form 1).pdf · uploaded 18 Aug 2025Source
  • Form 22 Engineer’s Certificate on Cost Incurred on Project (Form 2).pdf · uploaded 18 Aug 2025Source
  • Form 23 Engineer’s Certificate on Cost Incurred on Project (Form 2).pdf · uploaded 18 Aug 2025Source
  • Form 24 Engineer’s Certificate on Cost Incurred on Project (Form 2).pdf · uploaded 18 Aug 2025Source
  • Form 25 Engineer’s Certificate on Cost Incurred on Project (Form 2).pdf · uploaded 18 Aug 2025Source
  • Form 25 Engineer’s Certificate on Cost Incurred on Project (Form 2).pdf · uploaded 18 Aug 2025Source
  • Form 27 Engineer’s Certificate on Cost Incurred on Project (Form 2).pdf · uploaded 18 Aug 2025Source
  • Form 28 Engineer’s Certificate on Cost Incurred on Project (Form 2).pdf · uploaded 18 Aug 2025Source
  • Form 29 Engineer’s Certificate on Cost Incurred on Project (Form 2).pdf · uploaded 18 Aug 2025Source
  • Form 210 Engineer’s Certificate on Cost Incurred on Project (Form 2).pdf · uploaded 18 Aug 2025Source
  • Form 35 CA Certificate on Project Cost & Fund withdrawal (Form 3).pdf · uploaded 18 Aug 2025Source
  • Form 35 CA Certificate on Project Cost & Fund withdrawal (Form 3).pdf · uploaded 18 Aug 2025Source
  • Form 37 CA Certificate on Project Cost & Fund withdrawal (Form 3).pdf · uploaded 18 Aug 2025Source
  • Form 38 CA Certificate on Project Cost & Fund withdrawal (Form 3).pdf · uploaded 18 Aug 2025Source
  • Form 38 CA Certificate on Project Cost & Fund withdrawal (Form 3).pdf · uploaded 18 Aug 2025Source
  • Form 310 CA Certificate on Project Cost & Fund withdrawal (Form 3).pdf · uploaded 18 Aug 2025Source
  • Form 311 CA Certificate on Project Cost & Fund withdrawal (Form 3).pdf · uploaded 18 Aug 2025Source
  • Form 312 CA Certificate on Project Cost & Fund withdrawal (Form 3).pdf · uploaded 18 Aug 2025Source
  • Form 3fORM-3_11zon.pdf · uploaded 18 Aug 2025Source
  • Disclosure of Sold and Booked InventorySold Unsold Inventory.pdf · uploaded 18 Aug 2025Source
  • Disclosure of Sold and Booked InventorySold Unsold Statement.pdf · uploaded 18 Aug 2025Source
  • Disclosure of Sold and Booked InventorySold Unsold Statement.pdf · uploaded 18 Aug 2025Source
  • Disclosure of Sold and Booked InventorySold Unsold Statement.pdf · uploaded 18 Aug 2025Source
  • Disclosure of Sold and Booked InventorySold Unsold Statement.pdf · uploaded 18 Aug 2025Source
  • Disclosure of Sold and Booked InventorySold Unsold Statement.pdf · uploaded 18 Aug 2025Source
  • Disclosure of Sold and Booked InventorySold Unsold Statement.pdf · uploaded 18 Aug 2025Source
  • Disclosure of Sold and Booked InventorySold Unsold Statement.pdf · uploaded 18 Aug 2025Source
  • Disclosure of Sold and Booked InventorySold Unsold Statement.pdf · uploaded 18 Aug 2025Source
  • Withdrawal Update Form 1arc.pdf · uploaded 11 Mar 2026Source
  • Withdrawal Update Form 2Eng Nandanvan Q4.pdf · uploaded 11 Mar 2026Source
  • Withdrawal Update Form 3Nandanvan B CA 2.pdf · uploaded 11 Mar 2026Source
  • Withdrawal Update Form 1arc.pdf · uploaded 12 Mar 2026Source
  • Withdrawal Update Form 1arc.pdf · uploaded 12 Mar 2026Source
  • Withdrawal Update Form 1arc.pdf · uploaded 12 Mar 2026Source
  • Withdrawal Update Form 2form 2 (1) (1)_page-0001.pdf · uploaded 12 Mar 2026Source
  • Withdrawal Update Form 2form 2 (1) (1)_page-0001.pdf · uploaded 12 Mar 2026Source
  • Withdrawal Update Form 2form 2 (1) (1)_page-0001.pdf · uploaded 12 Mar 2026Source
  • Withdrawal Update Form 3form 3_compressed.pdf · uploaded 12 Mar 2026Source
  • Withdrawal Update Form 3form 3_compressed.pdf · uploaded 12 Mar 2026Source
  • Withdrawal Update Form 3form 3_compressed.pdf · uploaded 12 Mar 2026Source
  • Withdrawal Update Form 1arc.pdf · uploaded 30 Apr 2026Source
  • Withdrawal Update Form 2form 2 (1) (1)_page-0001.pdf · uploaded 30 Apr 2026Source
  • Withdrawal Update Form 3form 3_compressed.pdf · uploaded 30 Apr 2026Source

Technical

  • DocumentBuilding Layout.PDF · uploaded 26 Jul 2022Source
  • DocumentBuilding Layout.PDF · uploaded 26 Jul 2022Source
  • DocumentTemp00018.PDF · uploaded 30 Aug 2022Source
  • DocumentTemp00022.PDF · uploaded 30 Aug 2022Source
  • DocumentTemp00002.PDF · uploaded 3 Nov 2023Source
  • DocumentTemp00003.PDF · uploaded 3 Nov 2023Source
  • DocumentTemp00004.PDF · uploaded 3 Nov 2023Source
  • DocumentTemp00005.PDF · uploaded 3 Nov 2023Source
  • DocumentTemp00006.PDF · uploaded 3 Nov 2023Source
  • DocumentTemp00002_compressed.pdf · uploaded 21 Nov 2023Source
  • DocumentB wing Master Plan_11zon.pdf · uploaded 7 Mar 2025Source
  • DocumentB wing Master Plan_11zon.pdf · uploaded 7 Mar 2025Source
  • DocumentB wing Master Plan_11zon.pdf · uploaded 8 Mar 2025Source
  • DocumentB wing Mezzanine Floor Plan_11zon.pdf · uploaded 8 Mar 2025Source
  • DocumentB wing MHADA Plan_11zon.pdf · uploaded 8 Mar 2025Source
  • Documentscan_20250131113920_11zon.pdf · uploaded 8 Mar 2025Source
  • Documentscan_20250131113950_11zon.pdf · uploaded 8 Mar 2025Source
  • Documentscan_20250131114019_11zon.pdf · uploaded 8 Mar 2025Source
  • Documentscan_20250131114048_11zon.pdf · uploaded 8 Mar 2025Source
  • Documentscan_20250131114222_11zon.pdf · uploaded 8 Mar 2025Source
  • Documentscan_20250131114324_11zon.pdf · uploaded 8 Mar 2025Source
  • Documentscan_20250131114357_11zon.pdf · uploaded 8 Mar 2025Source
  • Documentscan_20250131114452_11zon.pdf · uploaded 8 Mar 2025Source

Technical (Architect)

  • DocumentNandanvan - Architects Certif.pdf · uploaded 8 Nov 2024Source
  • DocumentNandanvan Architects.pdf · uploaded 11 Nov 2024Source
  • DocumentArchitect certificate.pdf · uploaded 8 Mar 2025Source
  • DocumentArch- Nand.pdf · uploaded 25 Jun 2025Source
  • DocumentArch- Nand.pdf · uploaded 25 Jun 2025Source
  • Documentarc.pdf · uploaded 12 Mar 2026Source

Technical (Engineer)

  • DocumentNananvan_Eng_Certificate_Q1 (1).pdf · uploaded 8 Nov 2024Source
  • DocumentNandanvan_Eng_Q2.pdf · uploaded 8 Nov 2024Source
  • DocumentEngineer Certificate.pdf · uploaded 8 Mar 2025Source
  • DocumentEngg - Nand.pdf · uploaded 25 Jun 2025Source
  • DocumentEngg - Nand.pdf · uploaded 25 Jun 2025Source
  • Documentform 2 (1) (1)_page-0001.pdf · uploaded 12 Mar 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In AMBEGAON Bk, Haveli taluka

Survey, CTS, gat or plot numbers

S.No. 34 Hissa No. 12/1/1+12/1/2+12/1/3+12/1/4+13B/2A1A/1/2/1/1/1/1/1/1/B+10+11A+11B+12/1/4+41/6 PART

Boundaries

North
Remaining land of 34 and 41-6
South
Remaining land of 34 and 41-6
East
Remaining land of 34 and 41-6
West
Remaining land of 34 and 41-6

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectVilas Tarwadi—
Chartered accountantAnant Vasudevan Iyer—
Chartered accountantSachin Khajindar—
EngineerMahadev Bhaskar Gaikwad—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology