Delayed projects in Sindhudurg

72 MahaRERA projects in Sindhudurg are past their promised completion date, and MahaRERA shows no completion for them.

Most overdue first

Late: the latest completion date MahaRERA records (promised, or revised by an extension) has passed. Months late count from the first promised date. Page 1 of 2.

ProjectLocalityPromisedRevisedDelivery
Nirmaan BhavanNirman Builders And DevelopersSawantwadi (M Cl)Oct 2018Oct 20198 yrs late
Laxmi ArcadeAtharva DevelopersKudal (Ct)Dec 2018Oct 20237 yrs 10 mo late
Shree Krishnaleela ApartmentIshwardas Sakharam KubalMalwan (M Cl)Dec 2018May 20227 yrs 10 mo late
Swayambhu TirthShree Samartha ConstructionKankavaliJul 2019Jul 20197 yrs 3 mo late
Bhalchandra ResidencyJBS DevelopersKankavaliAug 2019Aug 20257 yrs 2 mo late
NandanvanSaikrupa Builders And DevelopersManeriSep 2019Mar 20217 yrs 1 mo late
Godgress AGodgressDevgadDec 2019Dec 20246 yrs 10 mo late
Icon GreensIcon RealtyKudal (Ct)Dec 2019Mar 20226 yrs 10 mo late
Morya Business PlazaMorya Infraconstruct Private LimitedSangirdeDec 2019Dec 20216 yrs 10 mo late
Siddhivinayak Appartment 1Shreyash Builders & DevelopersKudal (Ct)Dec 2019Dec 20196 yrs 10 mo late
Kavya ApartmentUday Tukaram SawantSangaveJan 2020Jan 20206 yrs 9 mo late
Swarnankar ApartmentShankar Govind ChindarkarOras Bk.Sep 2020Sep 20206 yrs 1 mo late
V MallVijaykumar Jagannath ValanjuKankavaliNov 2020Jun 20245 yrs 11 mo late
Shree Mahalaxmi ParadisemahalaxmicivilcontractorOras Bk.Mar 2021Apr 20225 yrs 7 mo late
Parvati PrideVedant DevelopersBanda (Ct)May 2021Nov 20245 yrs 5 mo late
SiddhiSankalp Siddhi DevelopersSawantwadi (M Cl)Nov 2021Nov 20214 yrs 11 mo late
TakshashilaInfinity BuildconKumbharmathDec 2021Apr 20254 yrs 10 mo late
MeghmalharShantanu Parshuram Gotoskar ParabBhomDec 2021Dec 20224 yrs 10 mo late
DyaneshwariDyaneshwari EnterprisesKudal (Ct)Sep 2022Sep 20234 yrs 1 mo late
PARADISE HOMES - Phase 1Rise & Rise InfraprojectsJanvaliNov 2022Dec 20253 yrs 11 mo late
Dipali ApartmentSavitri BuildersOras Bk.Dec 2022Dec 20233 yrs 10 mo late
Kanak ParadiseTriveni Builders And DevelopersKankavaliDec 2022Dec 20253 yrs 10 mo late
Rameshwar ApartmentVasudeo Sharad DalviOras Bk.Dec 2022Dec 20223 yrs 10 mo late
asmita residencyUday Vasudev WaingankarKattaDec 2022Dec 20223 yrs 10 mo late
Vrukshavalli B2Vijay Gangaram NaikMalgaonMar 2023Mar 20243 yrs 7 mo late
Malvani Days Inn Phase 1Manmohan Balkrishna RaneKumbharmathMay 2023May 20233 yrs 5 mo late
Shree Varadvinayak ResidencySunil Raghunath VidhateVengurla (M Cl)May 2023Nov 20253 yrs 5 mo late
Aarambh Business CentreConsortexe Properties Pvt LtdPinguliJun 2023Jun 20233 yrs 4 mo late
SeagreensRara RealtyJamsandeJun 2023Dec 20243 yrs 4 mo late
Dreamz GoaLevel Up ConstructionsShirodaAug 2023Jul 20263 yrs 2 mo late
Bhumaiyya ParkDattaraj ConstructionsArawaliDec 2023Dec 20232 yrs 10 mo late
Goa 2Sanskruti LandmarksPalasmbDec 2023Dec 20232 yrs 10 mo late
MoreshwarwadiKeshav Nandkishor BhiseTiravdeDec 2023Dec 20242 yrs 10 mo late
Otra Business ParkOtra Infrastructure Private LimitedOras Bk.Dec 2023Dec 20232 yrs 10 mo late
Paradise GardenUnited DevelopersSawantwadi (M Cl)Dec 2023Dec 20232 yrs 10 mo late
Sanjuchiwadi Phase-2Shantnu DevelopersKudal (Ct)Dec 2023Dec 20232 yrs 10 mo late
Shubham Nagari -Samarth Krupa Apt. Plot No.04Shubham InfrastructureOras Bk.Dec 2023Dec 20232 yrs 10 mo late
Teachers ColonyM S Patel ConstructionSawantwadi (M Cl)Dec 2023Dec 20232 yrs 10 mo late
Diksha Park Phase III BDashrath Babu JadhavJanvaliDec 2023Dec 20232 yrs 10 mo late
Nilaya ZionSgm Estates & Resorts Private LimitedBhogaveDec 2023Dec 20232 yrs 10 mo late
Padmavati PlazaShivanand Dasharath BhosaleDodamargFeb 2024May 20262 yrs 8 mo late
Omkar HomesSantosh Gopal KodeChindarMay 2024May 20242 yrs 5 mo late
Silver StoneSajjan Vinayak RaoraneVabhaveMay 2024May 20242 yrs 5 mo late
Ghd Orchid HomesGulshan Homez And Developer'sGirodeJun 2024Jun 20252 yrs 4 mo late
Shri Datta ApartmentBahar Dasharath BhosaleKasaiJun 2024Jun 20242 yrs 4 mo late
Ghd Casa GrandeGulshan Homez And DevelopersVazareJul 2024Jul 20242 yrs 3 mo late
Sai Sahavas Phase VSai Sampada Lifespaces Private LimitedHalvalJul 2024Jul 20242 yrs 3 mo late
Royal PlazaShailesh Bapu JadhavSawantwadiAug 2024Aug 20242 yrs 2 mo late
Axis BluesEejak Holdings Private LimitedManeriOct 2024Apr 20262 yrs late
Future CityFuture Infra Builders And Developers LLPBanda (Ct)Dec 2024Dec 20241 yr 10 mo late

Delayed projects by district

SourcesMahaRERA registrations, extension certificates, project pages and document listsA project counts as completed when MahaRERA shows it so: its status, or a completion or occupancy certificate in its documents. Dates are MahaRERA's; Deedo does not know the day a project was handed over.Report a problemMethodology