Bhom, Sindhudurg
Deedo IDDL-SIN-BHOM7 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects3
Registrations3
Completion still due12 past their date
Median extension20 months67% of registrations extended
Regulatory cases0none on MahaRERA's lists
7 in 10 registrations run late here
3 MahaRERA registrations in Bhom
1 not yet due2 past even the latest date
Extended registrations moved their completion date by a median of 20 months.
Projects in Bhom
3 projects registered with MahaRERA.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| MeghmalharShantanu Parshuram Gotoskar Parab | 4 yrs 11 mo late | — | — |
| Aranya I & IIGs Buildcon | Due Dec 2028 | — | — |
| Pushp ResidencySukhakarta Reaalty And Developer | Completed, extended 2 yrs 4 mo | — | 40% |
Nearby: other villages in Sawantwadi
Most active promoters
- Gs Buildcon1 project
- Shantanu Parshuram Gotoskar Parab1 project
- Sukhakarta Reaalty And Developer1 project
Bhom, in questions
How many projects in Bhom run late?
7 in 10 MahaRERA registrations (2 of 3): their completion date was extended or has passed, data through 7 Oct 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Bhom by Deedo. Medians on fewer than 3 deeds are not shown.
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology