Kolgaon, Sindhudurg
Deedo IDDL-SIN-KOLGAON10 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects6
Registrations6
Completion still due24 past their date
Median extension77 months33% of registrations extended
Regulatory cases0none on MahaRERA's lists
10 in 10 registrations run late here
6 MahaRERA registrations in Kolgaon
2 extended, not yet due4 past even the latest date
Extended registrations moved their completion date by a median of 77 months.
Projects in Kolgaon
6 projects registered with MahaRERA.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Aaradhya ResidencyAarambha Infotech Pvt Ltd | Due Dec 2027, extended 4 yrs 9 mo | — | 54% |
| Shri PlazaR G Developers | Completed | — | 50% |
| Datta-Anagha ParkDattaraj Constructions | Completed | — | 19% |
| Shri Sidheshwar ComplexRadhey Enterprises | Completed, extended 8 yrs 1 mo | — | 9% |
| Vanashree ApartmentGoldCoast Infra | Completed | — | 17% |
Nearby: other villages in Sawantwadi
Most active promoters
- Aarambha Infotech Pvt Ltd1 project
- Dattaraj Constructions1 project
- Goldcoast Infra1 project
- Radhey Enterprises1 project
- R G Developers1 project
- Vijaydurga Developers1 project
Kolgaon, in questions
How many projects in Kolgaon run late?
10 in 10 MahaRERA registrations (6 of 6): their completion date was extended or has passed, data through 7 Oct 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Kolgaon by Deedo. Medians on fewer than 3 deeds are not shown.
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology