RERA projects in Sawantwadi (M Cl)
51 projects under 51 MahaRERA registrations, registered 2017–2026. 39% have a completion date extended beyond the one promised.
Locality
51RERA projects
51Registrations
21Completion still due30 past their completion date
4 monthsMedian extension beyond promised date39% of registrations extended
2Regulatory caseson 2 projects
63Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 21 |
| 2018 | 3 |
| 2019 | 1 |
| 2020 | 2 |
| 2021 | 2 |
| 2022 | 6 |
| 2023 | 5 |
| 2024 | 6 |
| 2025 | 3 |
| 2026 | 2 |
Projects in Sawantwadi (M Cl)
51 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Unnati HeightsS S Construction | PR1310002601854 | 10 Sep 2026 | 31 Dec 2030 | 31 Dec 2030 | Not yet due | 0 |
| Gobind SrushtiSukhmani Landmark | PM1310002601048 | 6 Jul 2026 | 31 Dec 2032 | 30 Apr 2033 | Extended 4 mo | 0 |
| Anand Sagar ApartmentPravin Babli Parab | P52900081036 | 3 Nov 2025 | 31 Mar 2028 | 31 Jul 2028 | Extended 4 mo | 0 |
| Krishnamoreshwar ResidencyAjinkya Construction | P52900080924 | 18 Aug 2025 | 30 Nov 2029 | 30 Mar 2030 | Extended 4 mo | 0 |
| Sknt LakeviewSKNT Enterprises Private Limited | P52900080222 | 9 May 2025 | 31 Dec 2027 | 30 Apr 2028 | Extended 4 mo | 0 |
| Datta SrishtiNeeraj Mohan Desai | P52900077107 | 23 Jul 2024 | 23 May 2029 | 23 Sep 2029 | Extended 4 mo | 0 |
| Anaadih Shri DattaPrabhakar Krishnaji Parab | P52900056485 | 5 Jun 2024 | 31 Dec 2026 | 30 Apr 2027 | Extended 4 mo | 0 |
| Vaibhavlakshmi ApartmentRajendra Shashikant Morye | P52900056235 | 22 May 2024 | 31 Mar 2029 | 31 Jul 2029 | Extended 4 mo | 0 |
| Shrikrushna City CentreLaxminarayan Construction | P52900055542 | 2 Apr 2024 | 30 Sep 2028 | 30 Jan 2029 | Extended 4 mo | 0 |
| Gobind DarshanSukhmani Constructions | P52900055093 | 29 Feb 2024 | 31 Dec 2030 | 30 Apr 2031 | Extended 4 mo | 0 |
| M J TowersMahesh Someshwar Joshi | P52900054999 | 26 Feb 2024 | 31 Mar 2026 | 31 Jul 2026 | Extended 4 mo | 0 |
| Dipali ResidencyDattatray Construction | P52900053530 | 10 Nov 2023 | 24 Dec 2026 | 24 Dec 2026 | Not yet due | 0 |
| Amruta HeightsAnish Ajay Swar | P52900053262 | 23 Oct 2023 | 31 May 2028 | 30 Sep 2028 | Extended 4 mo | 0 |
| Apna GharVyankatesh Vasant Deshpande | P52900053000 | 10 Oct 2023 | 31 May 2028 | 30 Sep 2028 | Extended 4 mo | 0 |
| Ujwal ResidencyAjinkya Construction | P52900050943 | 15 May 2023 | 31 Jul 2027 | 31 Jul 2027 | Not yet due | 0 |
| Samarth PlazaTejas Harishchandra Samant | P52900049719 | 22 Feb 2023 | 20 Nov 2029 | 20 Mar 2030 | Extended 4 mo | 0 |
| Panchami HeightsGovind Janardan Khorjuvekar | P52900048001 | 7 Dec 2022 | 1 Oct 2027 | 1 Oct 2027 | Not yet due | 0 |
| Srishti ImperiaNeeraj Mohan Desai | P52900047188 | 11 Oct 2022 | 5 Jul 2027 | 5 Jul 2027 | Not yet due | 0 |
| Parvati PlazaPrakash Radhakrishna Mishal | P52900046695 | 30 Aug 2022 | 31 Dec 2025 | 31 Dec 2025 | Promised date passed | 0 |
| Gobind DhamSukhmani Constructions | P52900046685 | 29 Aug 2022 | 31 Dec 2027 | 31 Dec 2027 | Not yet due | 1 |
| Sahyog - R ComplexSahyog Construction | P52900034945 | 28 Apr 2022 | 31 Dec 2026 | 31 Dec 2026 | Not yet due | 0 |
| Devgiri HeightsDarpan Construction | P52900034016 | 17 Mar 2022 | 1 Mar 2027 | 1 Jul 2027 | Extended 4 mo | 0 |
| Rocky ResidencyAjinkya Construction | P52900030417 | 25 Aug 2021 | 31 Jul 2025 | 31 Jul 2025 | Promised date passed | 0 |
| Srishti Aangan Phase 2Neeraj Mohan Desai Huf | P52900028662 | 25 Mar 2021 | 15 Sep 2026 | 15 Sep 2026 | Promised date passed | 0 |
| SiddhiSankalp Siddhi Developers | P52900025649 | 1 Jul 2020 | 30 Nov 2021 | 30 Nov 2021 | Promised date passed | 0 |
Other localities in Sawantwadi
Most active promoters
By projects registered here, as named on MahaRERA.
- Ajinkya Construction5 projects
- Sukhmani Constructions5 projects
- Darpan Construction2 projects
- Neeraj Mohan Desai2 projects
- Neeraj Mohan Desai Huf2 projects
- Ajay Vasant Gondavale1 project
- Anil Bajarang Channe1 project
- Anish Ajay Swar1 project
- Aryak Associates1 project
- Babasaheb Pandurang Patil1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology