Charathe, Sindhudurg

4 in 10 MahaRERA registrations here have pushed their completion date back.

RERA projects7
Registrations7
Completion still due34 past their date
Median extension39 months43% of registrations extended
Regulatory cases0none on MahaRERA's lists
Charathe market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

7 in 10 registrations run late here

7 MahaRERA registrations in Charathe

2 not yet due1 extended, not yet due4 past even the latest date

Extended registrations moved their completion date by a median of 39 months.

Projects in Charathe

7 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
YashrajSanjay Sakharam SawantPR131000260234016 Oct 202631 Dec 2030—Not yet due0
Shiv TejAjinkya ConstructionP5290005309416 Oct 202330 Jun 203130 Oct 2031Extended 4 mo0
Green Valley - 2Ajinkya ConstructionP5290003073613 Sep 202131 Aug 202531 Aug 2025Promised date passed0
Green ValleyAjinkya ConstructionP5290002583319 Jul 20201 Jan 20241 Jan 2024Promised date passed0
Rahmat ArcadeUnited Construction CoP529000154961 Mar 201831 Dec 201931 Oct 2023Extended 46 mo0
DwarkanagariSwastik EnterprisesP5290001089131 Aug 201728 Apr 203128 Apr 2031Not yet due0
Skyline PrideSkyline DevelopersP5290000909819 Aug 201731 Mar 201930 Jun 2022Extended 39 mo0

Most active promoters

  1. Ajinkya Construction3 projects
  2. Sanjay Sakharam Sawant1 project
  3. Skyline Developers1 project
  4. Swastik Enterprises1 project
  5. United Construction Co1 project
Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Methodology