Charathe, Sindhudurg
4 in 10 MahaRERA registrations here have pushed their completion date back.
RERA projects7
Registrations7
Completion still due34 past their date
Median extension39 months43% of registrations extended
Regulatory cases0none on MahaRERA's lists
7 in 10 registrations run late here
7 MahaRERA registrations in Charathe
2 not yet due1 extended, not yet due4 past even the latest date
Extended registrations moved their completion date by a median of 39 months.
Projects in Charathe
7 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| YashrajSanjay Sakharam Sawant | PR1310002602340 | 16 Oct 2026 | 31 Dec 2030 | — | Not yet due | 0 |
| Shiv TejAjinkya Construction | P52900053094 | 16 Oct 2023 | 30 Jun 2031 | 30 Oct 2031 | Extended 4 mo | 0 |
| Green Valley - 2Ajinkya Construction | P52900030736 | 13 Sep 2021 | 31 Aug 2025 | 31 Aug 2025 | Promised date passed | 0 |
| Green ValleyAjinkya Construction | P52900025833 | 19 Jul 2020 | 1 Jan 2024 | 1 Jan 2024 | Promised date passed | 0 |
| Rahmat ArcadeUnited Construction Co | P52900015496 | 1 Mar 2018 | 31 Dec 2019 | 31 Oct 2023 | Extended 46 mo | 0 |
| DwarkanagariSwastik Enterprises | P52900010891 | 31 Aug 2017 | 28 Apr 2031 | 28 Apr 2031 | Not yet due | 0 |
| Skyline PrideSkyline Developers | P52900009098 | 19 Aug 2017 | 31 Mar 2019 | 30 Jun 2022 | Extended 39 mo | 0 |
Nearby: other localities in Sawantwadi
Most active promoters
- Ajinkya Construction3 projects
- Sanjay Sakharam Sawant1 project
- Skyline Developers1 project
- Swastik Enterprises1 project
- United Construction Co1 project
Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Methodology