Completion was pushed back 4 months, to Oct 2031; no MahaRERA orders on record; 0% of its units are booked.

Charathe, Sindhudurg 416510 · by Ajinkya Construction · 100% of its projects kept the RERA date

DeliveryExtended 4 moPromised Jun 2031 · now due Oct 2031RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales0% booked0 of 53 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 months, to Oct 2031

  • This projectRegistered 16 Oct 2023, completion promised 30 Jun 2031, revised to 30 Oct 2031.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

5 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52900053094
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5290005309416 Oct 202330 Jun 203130 Oct 2031Ajinkya ConstructionProject page
Documents73

2 documents held by Deedo, 71 filings listed on MahaRERA's project page

Registration certificate

Other

  • OtherDate not statedView

Finance

  • PAN CardPAN.pdf · uploaded 5 Aug 2023Source
  • PAN CardDECLARATION OF TYPO ERROR.pdf · uploaded 24 Aug 2023Source

Legal

  • Declaration Form BFORM B _1_1.pdf · uploaded 6 Aug 2023Source
  • Legal Title reportTITLE SEARCH REPORT.pdf · uploaded 1 Sep 2023Source

Migrated

  • 1 PAN CardPAN.pdf · uploaded 5 Aug 2023Source
  • 1 a Details of encumbrances concerned to FinanceNIL ENCUMBRANCE CERTIFICATE CONCERNED TO FINANCE.pdf · uploaded 6 Aug 2023Source
Show all 73 documentsShow fewer documents

Migrated

  • 1 b Details of encumbrances concerned to LegalNIL ENCUMBRANCE CERTIFICATE CONCERNED TO FINANCE.pdf · uploaded 6 Aug 2023Source
  • 1 Copy of Layout Approval (in case of layout)Layout Plan.pdf · uploaded 6 Aug 2023Source
  • 1 Building Plan Approval / NA Order for plotted developmentRow House Plan 1 TO 12.pdf · uploaded 6 Aug 2023Source
  • 2 Building Plan Approval / NA Order for plotted developmentBuilding Plan 1.pdf · uploaded 6 Aug 2023Source
  • 3 Building Plan Approval / NA Order for plotted developmentBuilding Plan 2.pdf · uploaded 6 Aug 2023Source
  • 1 Commencement Certificates / NA Order for plotted developmentCertificate of Commencement.pdf · uploaded 6 Aug 2023Source
  • 1 Declaration in FORM BFORM B _1_1.pdf · uploaded 6 Aug 2023Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1.pdf · uploaded 6 Aug 2023Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2.pdf · uploaded 6 Aug 2023Source
  • 1 Disclosure of sold/ booked inventoryDISCLOSURE REGARDING SOLD AND BOOKED INVENTORIES.pdf · uploaded 6 Aug 2023View
  • 1 Disclosure of Interest in Other Real Estate OrganizationsDISCLOSURE OF INTEREST IN OTHER REAL ESTATE ORGANIZATIONS.pdf · uploaded 6 Aug 2023Source
  • 2 Disclosure of Interest in Other Real Estate OrganizationsDISCLOSURE OF INTEREST IN OTHER REAL ESTATE ORGANIZATIONS_2.pdf · uploaded 6 Aug 2023Source
  • 1 Deviation Report with respect to Allotment letterNO DEVIATION WITH RESPECT TO ALLOTTMENT LETTER.pdf · uploaded 6 Aug 2023Source
  • 1 Deviation Report with respect to model copy of AgreementNO DEVIATION WITH RESPECT TO AGREEMENT FOR SALE.pdf · uploaded 6 Aug 2023Source
  • 1 Proforma of Agreement for saleProforma of Agreement for sale.pdf · uploaded 12 Aug 2023Source
  • 1 Proforma of Allotment letterProforma of Allotment letter.pdf · uploaded 12 Aug 2023Source
  • 2 PAN CardDECLARATION OF TYPO ERROR.pdf · uploaded 24 Aug 2023Source
  • 1 Declaration about Commencement Certificatedeclaration reg CC.pdf · uploaded 24 Aug 2023Source
  • 1 CERSAI detailsDECLARATION OF NO CERSAI REPORT.pdf · uploaded 24 Aug 2023Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3.pdf · uploaded 24 Aug 2023Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFORMAT A.pdf · uploaded 24 Aug 2023Source
  • 2 a Details of encumbrances concerned to FinanceNIL ENCUMBRANCE CERTIFICATE CONCERNED TO LEGAL.pdf · uploaded 29 Aug 2023Source
  • 2 b Details of encumbrances concerned to LegalNIL ENCUMBRANCE CERTIFICATE CONCERNED TO LEGAL.pdf · uploaded 29 Aug 2023Source
  • 1 Copy of the legal title reportTITLE SEARCH REPORT.pdf · uploaded 1 Sep 2023Source
  • 4 Building Plan Approval / NA Order for plotted developmentNA Order.pdf · uploaded 1 Sep 2023Source
  • 2 Declaration about Commencement CertificateMAHARERA E MAIL.pdf · uploaded 2 Sep 2023Source
  • 2 CERSAI detailsNEW CERSAI_Search_Report_200279226432_For_Asset_Based_Search_02_09_2023_12_41_56_866.pdf · uploaded 2 Sep 2023Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM - 1.pdf · uploaded 10 Jun 2024Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM - 1.pdf · uploaded 10 Jun 2024Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM - 1.pdf · uploaded 10 Jun 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM - 2.pdf · uploaded 10 Jun 2024Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM - 2.pdf · uploaded 10 Jun 2024Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM - 2.pdf · uploaded 10 Jun 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM - 3.pdf · uploaded 10 Jun 2024Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM - 3.pdf · uploaded 10 Jun 2024Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM - 3.pdf · uploaded 10 Jun 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 JULY 24.pdf · uploaded 8 Oct 2024Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 JULY 24.pdf · uploaded 8 Oct 2024Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3- 1 apr 24 to 30 jun 24.pdf · uploaded 8 Oct 2024Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 JULY 24.pdf · uploaded 8 Oct 2024Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3- 1 apr 24 to 30 jun 24.pdf · uploaded 8 Oct 2024Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 JULY 24.pdf · uploaded 8 Oct 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 ARCHITECT CERTIFICATE.pdf · uploaded 11 Feb 2025Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 ARCHITECTS CERTIFICATE.pdf · uploaded 11 Feb 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM -3 C A CERTIFICATE.pdf · uploaded 11 Feb 2025Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM -3 C A CERTIFICATE.pdf · uploaded 11 Feb 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 ENGINEERS CERTIFICATE.pdf · uploaded 11 Feb 2025Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 ENGINEERS CERTIFICATE.pdf · uploaded 11 Feb 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)ENGG FORM 2A 2023-2024.pdf · uploaded 26 Feb 2025Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)CA FORM 5 2023-24.pdf · uploaded 26 Feb 2025Source

Technical

  • DocumentLayout Plan.pdf · uploaded 6 Aug 2023Source
  • DocumentRow House Plan 1 TO 12.pdf · uploaded 6 Aug 2023Source
  • DocumentBuilding Plan 1.pdf · uploaded 6 Aug 2023Source
  • DocumentBuilding Plan 2.pdf · uploaded 6 Aug 2023Source
  • DocumentNA Order.pdf · uploaded 1 Sep 2023Source

Technical (Architect)

  • DocumentFORM - 1.pdf · uploaded 10 Jun 2024Source
  • DocumentFORM 1 JULY 24.pdf · uploaded 8 Oct 2024Source
  • DocumentFORM 1 JULY 24.pdf · uploaded 8 Oct 2024Source
  • DocumentFORM 1 ARCHITECT CERTIFICATE.pdf · uploaded 11 Feb 2025Source
  • DocumentFORM 1 ARCHITECTS CERTIFICATE.pdf · uploaded 11 Feb 2025Source

Technical (Engineer)

  • DocumentFORM - 2.pdf · uploaded 10 Jun 2024Source
  • DocumentFORM 2 JULY 24.pdf · uploaded 8 Oct 2024Source
  • DocumentFORM 2 JULY 24.pdf · uploaded 8 Oct 2024Source
  • DocumentFORM 2 ENGINEERS CERTIFICATE.pdf · uploaded 11 Feb 2025Source
  • DocumentFORM 2 ENGINEERS CERTIFICATE.pdf · uploaded 11 Feb 2025Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 20/A/1/A/3, 20/A/3/A

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
1BHK, 2BHK, Bungalow, Office building53 units in all
Address
S No 148 Old Hissa Nos 20/8 20/10 20/12 20/14 And New Hissa Nos 20/A/1/A/5, 20/A/1/A/3, 20/A/3/A, 20/A/3 At Charatha Tal Sawantwadi Sindhudurg, Internal Road, CharathePIN 416510
Village
Charathe, Sawantwadi taluka
Land area for this project
3,175 sq m (34,175 sq ft)
Permissible built-up area
3,076 sq m (33,105 sq ft)
Sanctioned built-up area
3,076 sq m (33,105 sq ft)
Recreational open space
270 sq m (2,906 sq ft)
Designated bank account
190
Developed in phases
Yes

Survey, CTS, gat or plot numbers

20/A/1/A/320/A/3/A20/A/3 AT CHARATHANEW HISSA NOS 20/A/1/A/5S NO 148 OLD HISSA NOS 20/8 20/10 20/12 20/14

Land as published on MahaRERA's project page

S NO 148 OLD HISSA NOS 20/8 20/10 20/12 20/14 AND NEW HISSA NOS 20/A/1/A/5 , 20/A/1/A/3, 20/A/3/A, 20/A/3 AT CHARATHA TAL SAWANTWADI SINDHUDURG

Boundaries

North
S No174 And H No 23
South
H No 13 16 18
East
S No174 And H No 22
West
S No 147

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking53 units

0 of 53 units booked (0%), as the promoter reported to MahaRERA

1BHK · 36 units2BHK · 4 unitsBungalow · 12 unitsOffice building · 1 unit
BuildingTypeCarpet areaUnitsBooked
Apartment Building No 11BHK37.46 sq m · 403 sq ft180
Apartment Building No 21BHK374.47 sq m · 4,031 sq ft180
Apartment Building No 22BHK56.16 sq m · 605 sq ft40
Rb Building 1Bungalow58.13 sq m · 626 sq ft40
Rb Building 2Bungalow58.13 sq m · 626 sq ft20
Rb Building 3Bungalow58,013 sq m · 6,24,446 sq ft60
Rb Building 3Office building47.57 sq m · 512 sq ft10

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals3

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectYeshwant Atmaram Naik—
Chartered accountantSudhir Naik And Associates—
EngineerYeshwant Atmaram Naik—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology