Ajgaon, Sindhudurg

No MahaRERA registration here has an extended completion date on record.

RERA projects1
Registrations1
Completion still due01 past their date
Median extensionNot on record0% of registrations extended
Regulatory cases0none on MahaRERA's lists
Ajgaon market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

10 in 10 registrations run late here

1 MahaRERA registration in Ajgaon

1 past even the latest date

Projects in Ajgaon

1 project registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Siddhivinayak ComplexPrasad Pramod KhotP5290001109231 Aug 201731 Jul 202231 Jul 2022Promised date passed0

Most active promoters

  1. Prasad Pramod Khot1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Methodology