RERA projects in Malwan (M Cl)
21 projects under 21 MahaRERA registrations, registered 2017–2026. 62% have a completion date extended beyond the one promised.
Locality
21RERA projects
21Registrations
9Completion still due12 past their completion date
4 monthsMedian extension beyond promised date62% of registrations extended
0Regulatory casesnone on MahaRERA's lists
26Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 8 |
| 2018 | 0 |
| 2019 | 0 |
| 2020 | 1 |
| 2021 | 0 |
| 2022 | 2 |
| 2023 | 4 |
| 2024 | 2 |
| 2025 | 1 |
| 2026 | 3 |
Projects in Malwan (M Cl)
21 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Athang GangaMorvekar Realtors | PM1310002600287 | 28 Apr 2026 | 31 Dec 2030 | 30 Apr 2031 | Extended 4 mo | 0 |
| Athang LaxmiMorvekar Realtors | PM1310002502629 | 6 Mar 2026 | 31 Dec 2029 | 30 Apr 2030 | Extended 4 mo | 0 |
| Sea MeridianSky Infrastructure | PM1310002502500 | 26 Feb 2026 | 28 Oct 2033 | 28 Feb 2034 | Extended 4 mo | 0 |
| Mhalsa HeightsNilesh Aravind Manjarekar | P52900078948 | 22 Jan 2025 | 31 Dec 2029 | 30 Apr 2030 | Extended 4 mo | 0 |
| Ruturaj AatmshreeChaitanya Suresh Kambli | P52900055057 | 26 Feb 2024 | 10 Feb 2030 | 10 Jun 2030 | Extended 4 mo | 0 |
| Sea PearlHiraya Constructions LLP | P52900054529 | 25 Jan 2024 | 9 Apr 2029 | 9 Apr 2029 | Not yet due | 0 |
| Venkatesh ApartmentSupreme Builders and Developers | P52900053532 | 10 Nov 2023 | 31 Dec 2025 | 31 Dec 2025 | Promised date passed | 0 |
| Ayaans AmbarySuman Developers | P52900053470 | 6 Nov 2023 | 30 Jun 2027 | 30 Oct 2027 | Extended 4 mo | 0 |
| Samarth AishwaryaSamarth Builders & Developers | P52900053368 | 27 Oct 2023 | 31 May 2028 | 30 Sep 2028 | Extended 4 mo | 0 |
| Shree Tuljabhavani ComplexShree Tuljabhavani Developers | P52900051571 | 27 Jun 2023 | 31 Dec 2030 | 30 Apr 2031 | Extended 4 mo | 0 |
| Ruturaj ShashwatChaitanya Suresh Kambli | P52900046554 | 12 Aug 2022 | 30 Apr 2024 | 30 Apr 2024 | Promised date passed | 0 |
| Vaastu TathastuNilesh Arvind Manjarekar | P52900034388 | 5 Apr 2022 | 29 Nov 2024 | 29 Nov 2024 | Promised date passed | 0 |
| Samarth VaibhavSamarth Builders & Developers | P52900027540 | 14 Dec 2020 | 30 Jun 2025 | 30 Jun 2025 | Promised date passed | 0 |
| Samarth AnganSamarth Krupa Developers | P52900010854 | 31 Aug 2017 | 30 Jun 2019 | 30 Jun 2019 | Promised date passed | 0 |
| Shree Krishnaleela ApartmentIshwardas Sakharam Kubal | P52900011582 | 31 Aug 2017 | 31 Dec 2018 | 12 May 2022 | Extended 41 mo | 0 |
| Pride SignaturePrideland Property | P52900009932 | 22 Aug 2017 | 30 Dec 2022 | 30 Dec 2022 | Promised date passed | 0 |
| Ruturaj EmpireChaitanya Suresh Kambli | P52900006409 | 14 Aug 2017 | 31 May 2019 | 30 Nov 2020 | Extended 18 mo | 0 |
| Shree Samarth ResidencySamarth Developers | P52900006080 | 14 Aug 2017 | 31 Dec 2017 | 30 Oct 2020 | Extended 34 mo | 0 |
| Pride SquarePrideland Properties | P52900005509 | 11 Aug 2017 | 30 Jun 2018 | 30 Jun 2018 | Promised date passed | 0 |
| Coral Residency BSaanvi Landmarks Pvt.Ltd | P52900003719 | 6 Aug 2017 | 31 Jan 2018 | 31 Oct 2019 | Extended 21 mo | 0 |
| Sanskruti ParkSanskruti Infrastructure | P52900001092 | 26 Jul 2017 | 31 Dec 2019 | 30 Dec 2021 | Extended 24 mo | 0 |
Other localities in Malwan
Most active promoters
By projects registered here, as named on MahaRERA.
- Chaitanya Suresh Kambli3 projects
- Morvekar Realtors2 projects
- Samarth Builders & Developers2 projects
- Hiraya Constructions LLP1 project
- Ishwardas Sakharam Kubal1 project
- Nilesh Aravind Manjarekar1 project
- Nilesh Arvind Manjarekar1 project
- Prideland Properties1 project
- Prideland Property1 project
- Saanvi Landmarks Pvt.Ltd1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology