Skip to content

Maneri, Sindhudurg

Deedo IDDL-SIN-MANERI

9 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects8
Registrations8
Completion still due44 past their date
Median extension15 months75% of registrations extended
Regulatory cases0none on MahaRERA's lists

9 in 10 registrations run late here

8 MahaRERA registrations in Maneri

1 not yet due3 extended, not yet due4 past even the latest date

Extended registrations moved their completion date by a median of 15 months.

Projects in Maneri

8 projects registered with MahaRERA.

ProjectDeliveryMedian ₹/sq ftBooked
ShantimAvira Dream Homes Private LimitedDue Apr 2027, extended 4 mo——
Yog AnandAbome Real Estate Private LimitedDue Apr 2032, extended 4 mo——
Yog AnandDomilis Estate LLPDue Dec 2031——
Axis Lake CityGirirajji Infrastructure Private Limited1 yr 7 mo late——
Axis BluesEejak Holdings Private Limited2 yrs 1 mo late—81%
All 8 projects →
Maneri market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Abome Real Estate Private Limited1 project
  2. Arush Infra Promoters Private Limited1 project
  3. Avira Dream Homes Private Limited1 project
  4. Domilis Estate LLP1 project
  5. Eejak Holdings Private Limited1 project
  6. Girirajji Infrastructure Private Limited1 project
  7. Natasha Dcosta1 project
  8. Saikrupa Builders And Developers1 project

Maneri, in questions

How many projects in Maneri run late?

9 in 10 MahaRERA registrations (7 of 8): their completion date was extended or has passed, data through 14 Nov 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Maneri by Deedo. Medians on fewer than 3 deeds are not shown.

Data through14 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology