Dodamarg, Sindhudurg
Deedo IDDL-SIN-DODAMARG4 in 10 MahaRERA registrations here have pushed their completion date back.
RERA projects32
Registrations32
Completion still due916 past their date
Median extension12 months44% of registrations extended
Regulatory cases0none on MahaRERA's lists
7 in 10 registrations run late here
32 MahaRERA registrations in Dodamarg and the places within it
3 not yet due6 extended, not yet due16 past even the latest date7 no date on record
Extended registrations moved their completion date by a median of 12 months.
Projects in Dodamarg
32 projects registered with MahaRERA in this taluka and the places within it.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Sateri TowersM/S Prasad Constructions | Due Dec 2030 | — | — |
| Bliss AquaEwissen Infrastructure | Due Apr 2029, extended 4 mo | — | — |
| ShantimAvira Dream Homes Private Limited | Due Apr 2027, extended 4 mo | — | — |
| Ghd Samaya RetreatGhd Infra Developers Pvt Ltd | Due Apr 2028, extended 4 mo | — | — |
| AlturaM/s. Block Buildtech LLP | Due Dec 2027 | — | — |
| Yog AnandAbome Real Estate Private Limited | Due Apr 2032, extended 4 mo | — | — |
| Yog AnandDomilis Estate LLP | Due Dec 2031 | — | — |
| Suvidha Suryakant ComplexBahar Dasharath Bhosale | 10 mo late | — | 0% |
| Dodamarg HeightsReality and Manufacture Group RMG | 10 mo late | — | 15% |
| Ghd Casa GrandeGulshan Homez And Developers | 2 yrs 3 mo late | — | 28% |
| Shripad PlazaShivanand Dasharath Bhosale | 10 mo late | — | 28% |
| Padmavati PlazaShivanand Dasharath Bhosale | 2 yrs 8 mo late | — | 60% |
| Sudhakar ArcadePrasad Raghunath Pangam | 1 yr 10 mo late | — | — |
| Shri Datta ApartmentBahar Dasharath Bhosale | 2 yrs 4 mo late | — | 0% |
| Axis Lake CityGirirajji Infrastructure Private Limited | 1 yr 6 mo late | — | 0% |
| Ghd Orchid HomesGulshan Homez And Developer's | 2 yrs 4 mo late | — | — |
| Axis BluesEejak Holdings Private Limited | 2 yrs late | — | 81% |
| Veenas Dream HomeVanita Govind Bhosle | Due Feb 2027, extended 4 mo | — | 0% |
| Hadikars Appaji PlazaFondu Apaji Hadikar | 4 mo late | — | 0% |
| Axis Yog VillasArush Infra Promoters Private Limited | Due May 2027, extended 2 yrs 10 mo | — | 6% |
| NandanvanSaikrupa Builders And Developers | 7 yrs 1 mo late | — | 0% |
| Kamakshi ResidencySiddhivianak Builders and Developers | 4 yrs late | — | 0% |
| AanganGulshan Homez And Developers | 4 yrs 2 mo late | — | 36% |
| Maneri ResidencyNatasha Dcosta | 3 yrs 4 mo late | — | 0% |
| Krishna KunjRajendra Dinkar Phatarpekar | 7 yrs 3 mo late | — | 0% |
Nearby: other talukas in Sindhudurg
Most active promoters
- Bahar Dasharath Bhosale2 projects
- Gulshan Homez And Developers2 projects
- Shivanand Dasharath Bhosale2 projects
- Abome Real Estate Private Limited1 project
- Arush Infra Promoters Private Limited1 project
- Avira Dream Homes Private Limited1 project
- Domilis Estate LLP1 project
- Eejak Holdings Private Limited1 project
- Ewissen Infrastructure1 project
- Fondu Apaji Hadikar1 project
Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology