RERA projects in Vaibhavvadi
10 projects under 11 MahaRERA registrations, registered 2017–2022. 11% have a completion date extended beyond the one promised.
10RERA projects
11Registrationssome projects hold several
2Completion still due7 past their completion date
12 monthsMedian extension beyond promised date11% of registrations extended
1Regulatory caseson 1 project
0Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 2 |
| 2018 | 0 |
| 2019 | 1 |
| 2020 | 1 |
| 2021 | 2 |
| 2022 | 3 |
Projects in Vaibhavvadi
10 projects registered with MahaRERA in this taluka and the places within it.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Inamdar PlazaVijay Shridhar Tawde | P52900048009 | 7 Dec 2022 | 30 Jun 2026 | — | Promised date passed | 0 |
| Manorama TownshipBhawani Heights Development Private Limited | P52900046950 | 26 Sep 2022 | 31 May 2025 | — | Promised date passed | 0 |
| Sadguru ComplexBhagwan Bhikaji Belekar | P52900033439 | 22 Feb 2022 | 31 Dec 2025 | — | Promised date passed | 1 |
| Silver StoneSajjan Vinayak Raorane | P52900029809 | 4 Jul 2021 | 31 May 2024 | — | Promised date passed | 0 |
| Shridhar ApartmentVijay Shridhar Tawde | P52900026841 | 28 Oct 2020 | 30 Jun 2024 | — | Promised date passed | 0 |
| Siddhi Ganesh ParkManoj Vasant Mahadik | P52900021035 | 31 May 2019 | 30 May 2027 | — | Not yet due | 0 |
| Adityasagar ComplexSiddhesh Mahadeo Kanade | P52900012910, P52900029896 | 7 Sep 2017 | 30 Dec 2026 | 31 Dec 2019 | Not yet due | 0 |
| Samartha HillSitaram Krishna Adivarekar | P52900009411 | 22 Aug 2017 | 1 Aug 2019 | — | Promised date passed | 0 |
| Mahakali Complex | P52900018111 | — | — | — | — | 0 |
| Nirmal Sai Apartments | P52900014985 | — | — | — | — | 0 |
Other talukas in Sindhudurg
Most active promoters
By projects registered here, as named on MahaRERA.
- Vijay Shridhar Tawde2 projects
- Bhagwan Bhikaji Belekar1 project
- Bhawani Heights Development Private Limited1 project
- Manoj Vasant Mahadik1 project
- Sajjan Vinayak Raorane1 project
- Siddhesh Mahadeo Kanade1 project
- Sitaram Krishna Adivarekar1 project
Data through8 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology