Vengurla, Sindhudurg
4 in 10 MahaRERA registrations here have pushed their completion date back.
RERA projects29
Registrations29
Completion still due721 past their date
Median extension10 months36% of registrations extended
Regulatory cases0none on MahaRERA's lists
9 in 10 registrations run late here
29 MahaRERA registrations in Vengurla and the places within it
2 not yet due5 extended, not yet due21 past even the latest date1 no date on record
Extended registrations moved their completion date by a median of 10 months.
Projects in Vengurla
29 projects registered with MahaRERA in this taluka and the places within it.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| LotusBenjamin Manwel Dsouza | Due Sep 2029 | — | — |
| Golf De OceanSSL Nirvana Grand Golf Developers Pvt Ltd | Due Apr 2029, extended 4 mo | — | — |
| KrushnaiChirayu Builders Vengurla | Due Sep 2028, extended 4 mo | — | — |
| Hawa ResidencyAslam Anwar Khan | Due Apr 2030, extended 4 mo | — | — |
| Dreamz Goa Phase IILevel Up Constructions | Due Apr 2029, extended 4 mo | — | 9% |
| Nilaya ZionSgm Estates & Resorts Private Limited | 2 yrs 10 mo late | — | — |
| Aradhana SamarpanAarwana Developers | Due Jul 2030, extended 4 mo | — | 44% |
| Shree Kepadevi PlazaKepadevi Constructions | 1 yr 5 mo late | — | 67% |
| Bhumaiyya ParkDattaraj Constructions | 2 yrs 10 mo late | — | 32% |
| Seawood Phase IIShreeram Builders & Developers | 3 yrs 10 mo late | — | 73% |
| Shree Varadvinayak ResidencySunil Raghunath Vidhate | 3 yrs 5 mo late | — | 0% |
| Dreamz GoaLevel Up Constructions | 3 yrs 2 mo late | — | 64% |
| Cosmos Building CBenjamin Manwel Dsouza | 7 yrs 8 mo late | — | 89% |
| Meena Park Plot 2-4Benjamin Manwel Dsouza | 4 yrs 1 mo late | — | 79% |
| Meena Park - 5Benjamin Manwel Dsouza | 8 yrs 7 mo late | — | 95% |
| Vaishali ResidencyAmitkumar Suresh Dublay | 2 yrs 7 mo late | — | 60% |
| Mahalaxmi PlazaMeraj Majesty Builders and Developers | 5 yrs 4 mo late | — | 0% |
| Lotus PlazaChoice Realty Private Limited | 7 yrs 5 mo late | — | 23% |
| 54 Anandwan SankulRajesh Raghuvir Mantri | 8 yrs 4 mo late | — | 30% |
| Devi Darshan Phase IShreeram Builders & Developers | 7 yrs 11 mo late | — | 32% |
| Heramb SankulM/S Heramb Constructions | 6 yrs 10 mo late | — | 34% |
| SEAWOOD Phase IShreeram Builders & Developers | 7 yrs 9 mo late | — | 57% |
| Nakshatra EnclavePancharatna Associates | 3 yrs 10 mo late | — | 35% |
| Patil ChembersBabasaheb Pandurang Patil | 2 yrs 10 mo late | — | 27% |
| Anandi Arpan Phase IIAnandi Constructions | 6 yrs 10 mo late | — | 86% |
Nearby: other talukas in Sindhudurg
Most active promoters
- Benjamin Manwel Dsouza4 projects
- Shreeram Builders & Developers3 projects
- Babasaheb Pandurang Patil2 projects
- Level Up Constructions2 projects
- Aarwana Developers1 project
- Amitkumar Suresh Dublay1 project
- Anandi Constructions1 project
- Aslam Anwar Khan1 project
- Chirayu Builders Vengurla1 project
- Choice Realty Private Limited1 project
Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Methodology