RERA projects in Kudal

116 projects under 123 MahaRERA registrations, registered 2017–2026. 49% have a completion date extended beyond the one promised.

Taluka
116RERA projects
123Registrationssome projects hold several
45Completion still due63 past their completion date
4 monthsMedian extension beyond promised date49% of registrations extended
1Regulatory caseson 1 project
199Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
201732
201810
20196
20209
20217
202210
20239
20248
202513
20264

Projects in Kudal

116 projects registered with MahaRERA in this taluka and the places within it.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Signature SquareSwami Srushti DevelopersPM13100026020761 Oct 202631 Dec 202831 Dec 2028Not yet due0
Shivaangan HeightsS. G. DevelopersPM131101260023421 Apr 202631 Dec 202830 Apr 2029Extended 4 mo0
Crestview CourtStallum Buildcon Private LimitedPM13100025026659 Mar 202630 Sep 202930 Jan 2030Extended 4 mo0
GraamaEbrix Infratech Real Estate LLPPP13100025026215 Mar 202631 Dec 202830 Apr 2029Extended 4 mo0
Sulabha PlazaLaxmi DevelopersPM131000250196131 Dec 202531 Dec 202830 Apr 2029Extended 4 mo0
AaradhanaBalaji Builders And DevelopersPM131000250150818 Nov 202531 Dec 202930 Apr 2030Extended 4 mo0
Kudaleshwar Krupa Phase IIVijay Mohan NaikPR131101250133728 Oct 202531 Mar 202831 Jul 2028Extended 4 mo0
Sadanand Residency Phase IIIBhavani BuildersP5290008099229 Sep 202531 Mar 203031 Jul 2030Extended 4 mo0
Origin KudalAxon Origin Kudal LLPP5290008094125 Aug 202531 Dec 202930 Apr 2030Extended 4 mo0
Dwarka NiwasJayshree BuildersPM131000250041829 Jul 202530 Jun 202930 Oct 2029Extended 4 mo0
Kudaleshwar Krupa Phase IWeaver ConstroP5290008086524 Jul 202531 Mar 202831 Jul 2028Extended 4 mo0
Nishigandha ApartmentsBrahma ConstructionsP5290008058316 Jun 20251 Apr 20301 Aug 2030Extended 4 mo0
Avdhoot ManthanShashikant Shamrao JadhavP5290007980526 Mar 202531 Dec 202730 Apr 2028Extended 4 mo0
Nirmitee S S Royal PlazaNirmitee Builders & DevelopersP5290007976426 Mar 202530 May 203030 Sep 2030Extended 4 mo0
AlaukikAbhay Sharad WalawalkarP529000790823 Feb 202531 May 202930 Sep 2029Extended 4 mo0
Vrindavan VasShrikant Pandurang VadgaonkarP5290007898828 Jan 202531 Dec 202830 Apr 2029Extended 4 mo0
Aakar AnantAakar Builders And DevelopersP529000787348 Jan 202531 Mar 202831 Jul 2028Extended 4 mo0
GurukripaVastu DevelopersP5290007794914 Nov 202431 Dec 202830 Apr 2029Extended 4 mo0
AtrinandanShree Datt EnterprisesP529000773789 Aug 202431 May 203130 Sep 2031Extended 4 mo0
Narayan PlazaRachana Builders And Developers KudalP5290007708423 Jul 202431 Mar 202931 Jul 2029Extended 4 mo0
Tarangan B WingConsortexe Properties Pvt LtdP5290007669120 Jun 202431 Dec 202630 Apr 2027Extended 4 mo0
Krishiv TowerSanjiv Sahadev ParabP5290005636031 May 202431 Mar 202831 Jul 2028Extended 4 mo0
Vighnaraj ApartmentDhananjay Manohar KalsekarP5290005625722 May 202431 Dec 203030 Apr 2031Extended 4 mo0
Dwarkamai ArcadeDinesh Anant RaneP5290005577716 Apr 202431 Dec 202830 Apr 2029Extended 4 mo0
Prime VistaUmesh Sudhakar SukhiP5290005448725 Jan 202431 Dec 202731 Dec 2027Not yet due0

Other talukas in Sindhudurg

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Nirmitee Builders & Developers5 projects
  2. Consortexe Properties Pvt Ltd4 projects
  3. Abhay Sharad Walawalkar3 projects
  4. Mohan Vasudeo Hundare3 projects
  5. Prakash Rajaram Jaitapkar3 projects
  6. Bhavani Builders2 projects
  7. Rachana Builders And Developers Kudal2 projects
  8. Shantnu Developers2 projects
  9. Shashikant Shamrao Jadhav2 projects
  10. Shreyash Builders & Developers2 projects
Data through15 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology