Maneri, Sindhudurg 416512 |Promoter: Saikrupa Builders And Developers

10 Apr 2019Registered with MahaRERA
30 Sep 2019Promised completion
29 Mar 2021Revised completionPushed back 1 year and 6 months
1Building
245Units registered0 booked (0%)
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Commercial
Status on MahaRERA
Certificate Signed
Buildings
1
Unit types
2BHK 001, 2BHK 002, 2BHK 101, 2BHK 102, 2BHK 103, 2BHK 104, 2BHK 201, 2BHK 202, 2BHK 203, 2BHK 204, 2BHK 301, 2BHK 302, 2BHK 303, 2BHK 304, Shop s1, Shop s2, Shop s3, Shop s4, Shop s5, Shop s6, Shop s7245 units in all
Address
123b, Sawantwadi Road, ManeriPIN 416512
Designated bank account
180
Developed in phases
No

Registered transactions

No registered transactions matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to this project by evidence.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 1 year and 6 months

The latest completion date on record passed 5 years and 7 months ago.

Registered
10 Apr 2019
Promised
30 Sep 2019
Revised
29 Mar 2021

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5290002044010 Apr 201930 Sep 201929 Mar 2021Saikrupa Builders And DevelopersProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Nandanvan4245

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

0 of 245 units booked (0%), as the promoter reported to MahaRERA

2BHK 001 · 14 units2BHK 002 · 14 units2BHK 101 · 14 units2BHK 102 · 14 units2BHK 103 · 14 units2BHK 104 · 14 units2BHK 201 · 14 units2BHK 202 · 14 units2BHK 203 · 14 units2BHK 204 · 14 units2BHK 301 · 14 units2BHK 302 · 14 units2BHK 303 · 14 units2BHK 304 · 14 unitsShop s1 · 7 unitsShop s2 · 7 unitsShop s3 · 7 unitsShop s4 · 7 unitsShop s5 · 7 unitsShop s6 · 7 unitsShop s7 · 7 units
TypeCarpet areaUnitsBooked
2BHK 00156.91 sq m · 613 sq ft140
2BHK 00256.89 sq m · 612 sq ft140
2BHK 10156.87 sq m · 612 sq ft140
2BHK 10256.91 sq m · 613 sq ft140
2BHK 10356.89 sq m · 612 sq ft140
2BHK 10456.91 sq m · 613 sq ft140
2BHK 20156.87 sq m · 612 sq ft140
2BHK 20256.91 sq m · 613 sq ft140
Show all 21 unit rowsShow fewer unit rows
TypeCarpet areaUnitsBooked
2BHK 20356.89 sq m · 612 sq ft140
2BHK 20456.91 sq m · 613 sq ft140
2BHK 30156.87 sq m · 612 sq ft140
2BHK 30256.91 sq m · 613 sq ft140
2BHK 30356.89 sq m · 612 sq ft140
2BHK 30456.91 sq m · 613 sq ft140
Shop s118.88 sq m · 203 sq ft70
Shop s216.12 sq m · 174 sq ft70
Shop s317.15 sq m · 185 sq ft70
Shop s423.61 sq m · 254 sq ft70
Shop s523.61 sq m · 254 sq ft70
Shop s629.92 sq m · 322 sq ft70
Shop s718.6 sq m · 200 sq ft70

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Documents

2 documents held by Deedo, 56 filings listed on MahaRERA's project page

Registration certificate

Extension certificate

Finance

  • PAN Cardpancard.pdf · uploaded 27 Sep 2018Source

Legal

  • OtherCarpet area.pdf · uploaded 3 Oct 2018Source
  • Legal Title reportPARMEKAR SATHEKHAT.pdf · uploaded 3 Oct 2018Source
  • Legal Title reportpermission for construction.pdf · uploaded 3 Oct 2018Source
  • Legal Title reportsale deed.pdf · uploaded 3 Oct 2018Source
  • Legal Title reportparmekar 7-12.pdf · uploaded 3 Oct 2018Source
Show all 58 documentsShow fewer documents

Legal

  • Legal Title reportparmekar SAMMATIPATRA.pdf · uploaded 3 Oct 2018Source
  • Legal Title reportsupriya rane SAMMATIPATRA.pdf · uploaded 3 Oct 2018Source
  • Legal Title reportPARTNERSHIP.pdf · uploaded 3 Oct 2018Source
  • Declaration Form Bform B.pdf · uploaded 26 Mar 2019Source
  • Otherpercentage of work completion certificate architect 270422.pdf · uploaded 4 May 2022Source
  • Otherpercentage of work completion certificate cunsultant270422.pdf · uploaded 4 May 2022Source
  • OtherCA Certificate281122.pdf · uploaded 4 May 2022Source

Migrated

  • 1 PAN Cardpancard.pdf · uploaded 27 Sep 2018Source
  • 1 Copy of the legal title reportPARMEKAR SATHEKHAT.pdf · uploaded 3 Oct 2018Source
  • 2 Copy of the legal title reportpermission for construction.pdf · uploaded 3 Oct 2018Source
  • 3 Copy of the legal title reportsale deed.pdf · uploaded 3 Oct 2018Source
  • 4 Copy of the legal title reportparmekar 7-12.pdf · uploaded 3 Oct 2018Source
  • 5 Copy of the legal title reportparmekar SAMMATIPATRA.pdf · uploaded 3 Oct 2018Source
  • 6 Copy of the legal title reportsupriya rane SAMMATIPATRA.pdf · uploaded 3 Oct 2018Source
  • 7 Copy of the legal title reportPARTNERSHIP.pdf · uploaded 3 Oct 2018Source
  • 1 Copy of Layout Approval (in case of layout)approved plan.pdf · uploaded 3 Oct 2018Source
  • 1 Building Plan Approval (IOD)approved plan.pdf · uploaded 3 Oct 2018Source
  • 1 OtherCarpet area.pdf · uploaded 3 Oct 2018Source
  • 1 Commencement Certificates / NA Order for plotted developmentpermission for construction.pdf · uploaded 13 Nov 2018Source
  • 1 Certificates of CA (Form 3)Form 3.pdf · uploaded 3 Jan 2019Source
  • 1 Certificates of CA (Form 5)Form 5.pdf · uploaded 3 Jan 2019Source
  • 1 Declaration in FORM Bform B.pdf · uploaded 26 Mar 2019Source
  • 1 Proforma of Allotment letterSALE STATUS.pdf · uploaded 30 Mar 2019Source
  • 1 Details of encumbrancesdetails of encumbrances.pdf · uploaded 2 Apr 2019Source
  • 1 Details of Restarting of Construction work post lockdownSTARTING OF CONSTRUCTION WORK.pdf · uploaded 29 Aug 2020Source
  • 2 Otherpercentage of work completion certificate architect 270422.pdf · uploaded 4 May 2022Source
  • 3 Otherpercentage of work completion certificate cunsultant270422.pdf · uploaded 4 May 2022Source
  • 4 OtherCA Certificate281122.pdf · uploaded 4 May 2022Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate 19-20.pdf · uploaded 1 Dec 2023Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate 20-21.pdf · uploaded 1 Dec 2023Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate 22-23.pdf · uploaded 1 Dec 2023Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate 19-20.pdf · uploaded 1 Dec 2023Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate 20-21.pdf · uploaded 1 Dec 2023Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate 22-23.pdf · uploaded 1 Dec 2023Source
  • 2 Certificates of CA (Form 3)Ca certificate 19-20.pdf · uploaded 1 Dec 2023Source
  • 3 Certificates of CA (Form 3)Ca certificate 2020-21.pdf · uploaded 1 Dec 2023Source
  • 4 Certificates of CA (Form 3)Ca certificate 20-21.pdf · uploaded 1 Dec 2023Source
  • 5 Certificates of CA (Form 3)ca certificate 20-21 (1).pdf · uploaded 1 Dec 2023Source
  • 6 Certificates of CA (Form 3)Ca cer 20-21.pdf · uploaded 1 Dec 2023Source
  • 7 Certificates of CA (Form 3)Ca certificate 22-23.pdf · uploaded 1 Dec 2023Source
  • 8 Certificates of CA (Form 3)ca cer 22-23.pdf · uploaded 1 Dec 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)RERA Certificate 1(Scan).pdf · uploaded 1 Dec 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)RERA Certificate 2 (Scan).pdf · uploaded 1 Dec 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)RERA Certificate 3 (Scan).pdf · uploaded 1 Dec 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Annual Report On Account 21-22.pdf · uploaded 12 Dec 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Annual Report On Account 22-23.pdf · uploaded 12 Dec 2023Source

Technical

  • Documentapproved plan.pdf · uploaded 3 Oct 2018Source
  • Documentapproved plan.pdf · uploaded 3 Oct 2018Source

Technical (Architect)

  • DocumentArchitect Certificate 22-23.pdf · uploaded 1 Dec 2023Source

Technical (Engineer)

  • DocumentEngineer Certificate 22-23.pdf · uploaded 1 Dec 2023Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Maneri, Dodamarg taluka

Survey, CTS, gat or plot numbers

123B

Boundaries

North
Internal Ploting Road
South
123b14
East
Banda Dodamarg State Highway
West
123b13

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectSiddharth D Naik—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology