Delayed projects in Kolhapur
131 MahaRERA projects in Kolhapur are past their promised completion date, and MahaRERA shows no completion for them.
Most overdue first
Late: the latest completion date MahaRERA records (promised, or revised by an extension) has passed. Months late count from the first promised date. Page 1 of 3.
| Project | Locality | Promised | Revised | Delivery |
|---|---|---|---|---|
| Aditya EnclaveJirge Developers and Builders | Kolhapur (M Corp.) | Dec 2017 | Dec 2017 | 8 yrs 10 mo late |
| StatusParadise Developers | Kolhapur (M Corp.) | May 2018 | May 2018 | 8 yrs 5 mo late |
| DattatirthGajraj Builders | Nrusinhawadi | Jul 2018 | Aug 2024 | 8 yrs 3 mo late |
| Urban Life Phase II Building CAtharv Estates India Private Limited | Kabnur (Ct) | Jul 2018 | Jul 2023 | 8 yrs 3 mo late |
| Guruprasad Heights 1Guruprasad Builders and Developers | Kolhapur (M Corp.) | Dec 2018 | Dec 2019 | 7 yrs 10 mo late |
| Inest RealtorsInest Realtors | Hatkanangle | Dec 2018 | Dec 2018 | 7 yrs 10 mo late |
| Scarlet HeightsSanjay Shivajirao Shinde | Kolhapur (M Corp.) | Dec 2018 | Sep 2022 | 7 yrs 10 mo late |
| Ujjwal ParkUjvil Associates | Kolhapur (M Corp.) | Jan 2019 | Jan 2019 | 7 yrs 9 mo late |
| Sanjay Balgounda PatilSanjay Balgounda Patil | Ichalkaranji (M Cl) | Mar 2019 | Mar 2022 | 7 yrs 7 mo late |
| Guruprasdad Heights 2Guruprasad Builders And Developers | Kolhapur (M Corp.) | Jun 2019 | Nov 2020 | 7 yrs 4 mo late |
| Pitru Chhaya ApartmentAarati Yogesh Joshi | Kolhapur (M Corp.) | Jul 2019 | Jan 2021 | 7 yrs 3 mo late |
| Pinnac ShivanjanaSuresh Rajaram Dharmadhikari | Kolhapur (M Corp.) | Dec 2019 | Dec 2019 | 6 yrs 10 mo late |
| Bindu PrideSnap Realty | Kolhapur (M Corp.) | Jan 2020 | Jan 2022 | 6 yrs 9 mo late |
| Shree ApartmentRohit Ravindra Parmale | Kolhapur (M Corp.) | Dec 2020 | Dec 2020 | 5 yrs 10 mo late |
| Parshwa EnclaveParshawa Properties | Jaysingpur (M Cl) | Dec 2020 | Feb 2024 | 5 yrs 10 mo late |
| Bellmount TowerRashid Shamshuddin Bargir | Sarnobatwadi | Dec 2021 | Dec 2021 | 4 yrs 10 mo late |
| Bhagyarekha ResidencyJadhav Misal | Kolhapur (M Corp.) | Dec 2021 | Dec 2021 | 4 yrs 10 mo late |
| Bougain VillasSmt.Shashikala Vitthal Mardane and Shri.Ravindra Vitthal Mardane | Kolhapur (M Corp.) | Dec 2021 | Dec 2021 | 4 yrs 10 mo late |
| Mahadik ChambersMaruti Siddhu Mahadik And Mahesh Maruti Mahadik | Jaysingpur (M Cl) | Dec 2021 | Dec 2021 | 4 yrs 10 mo late |
| Rajlaxmi HeightsUdaysinh Hariram shinde | Kolhapur (M Corp.) | Dec 2021 | Dec 2021 | 4 yrs 10 mo late |
| Rajani VinayakRajani Builders & Developers | Karvir | Dec 2021 | Jan 2024 | 4 yrs 10 mo late |
| ShaniwarwadaKaran Bhagwantrao Mane | Kolhapur (M Corp.) | Dec 2021 | Dec 2021 | 4 yrs 10 mo late |
| Sukruti Heights Phase-2Chintamani Developers | Kolhapur (M Corp.) | Mar 2022 | Mar 2022 | 4 yrs 7 mo late |
| Salgar HeightsSunil Dinkar Salgar | Kolhapur (M Corp.) | Mar 2022 | Mar 2022 | 4 yrs 7 mo late |
| Vishwatara EleganceShree Padmamba Developers | Kolhapur (M Corp.) | Mar 2022 | Mar 2022 | 4 yrs 7 mo late |
| S.b. HeightsSidra Developers | Ichalkaranji (M Cl) | May 2022 | Dec 2025 | 4 yrs 5 mo late |
| Ayodhya Park Phase IAshok Ramchandra Yamgekar | Gadhinglaj | May 2022 | May 2022 | 4 yrs 5 mo late |
| Korgaonkar ParkIndumati Constructions | Gadhinglaj (M Cl) | Jun 2022 | Jun 2024 | 4 yrs 4 mo late |
| Kulshri RejancySahadev Nagoji Patil | Kolhapur (M Corp.) | Jun 2022 | Jun 2022 | 4 yrs 4 mo late |
| Choundeshwari PlanetVijay Virupaksha Galgale | Ichalkaranji (M Cl) | Oct 2022 | Oct 2022 | 4 yrs late |
| Meerabhakti Residency Wing BSHP Properties Private Limited | Kolhapur (M Corp.) | Oct 2022 | Oct 2023 | 4 yrs late |
| Shrinandan ApartmentShree Builders And Developers | Gadhinglaj | Nov 2022 | Nov 2022 | 3 yrs 11 mo late |
| Mahadev HeightsSachin Dattatraya Ghorpade | Kolhapur (M Corp.) | Nov 2022 | Jul 2023 | 3 yrs 11 mo late |
| Takshshila CBSCme Hitech Construction Limited | Karvir | Dec 2022 | Dec 2022 | 3 yrs 10 mo late |
| Gayatri-Bhawani ApartmentVijaykumar Vasudev Patki | Kolhapur (M Corp.) | Dec 2022 | Jun 2026 | 3 yrs 10 mo late |
| Kedar Infra HousingKedar infra | Kolhapur (M Corp.) | Dec 2022 | Dec 2022 | 3 yrs 10 mo late |
| The CubeMillennium Group Engineers And Developers | Kolhapur (M Corp.) | Dec 2022 | Dec 2025 | 3 yrs 10 mo late |
| Subhadramaruti EnclaveShree Padmamba Builders And Developers | Kolhapur (M Corp.) | Mar 2023 | Mar 2023 | 3 yrs 7 mo late |
| Sant ResidencyShri Mahalaxmi Builders | Gadhinglaj | Mar 2023 | Mar 2023 | 3 yrs 7 mo late |
| Trade CenterVasant Ramchandra Yamagekar | Gadhinglaj (M Cl) | Apr 2023 | Apr 2023 | 3 yrs 6 mo late |
| Ayodhya ParkShree Construction & Developers | Vadgaon Kasba (M Cl) | Jun 2023 | Jun 2023 | 3 yrs 4 mo late |
| Gajalaxmi ParkAmit Yashwant Singh and Others | Hatkanangale | Jun 2023 | Jun 2023 | 3 yrs 4 mo late |
| MuktanganAnup Vikas Patil | Gadhinglaj | Jun 2023 | Jun 2023 | 3 yrs 4 mo late |
| The 8th AvenueShree Mahalaxmi Constructions | Kolhapur (M Corp.) | Jun 2023 | Jun 2023 | 3 yrs 4 mo late |
| Dipti Villa - KolhapurDipti Home Makers Pvt Ltd | Karvir | Jul 2023 | Jul 2023 | 3 yrs 3 mo late |
| Punya Srushti Co-Op. Housing Society LtdPunyasrushti Sahakari Gruhnirman Sanstha Maryadit | Kolhapur (M Corp.) | Jul 2023 | Jul 2023 | 3 yrs 3 mo late |
| Dharti apartmentPrithviraj Kakade Constructions PVT LTD | Ujalaiwadi (Ct) | Sep 2023 | Sep 2023 | 3 yrs 1 mo late |
| Tapashri PlazaShri Construction | Kolhapur (M Corp.) | Oct 2023 | Dec 2025 | 3 yrs late |
| Royal OrchidSushant Vijay Bhalbar | Kagal (M Cl) | Nov 2023 | Nov 2023 | 2 yrs 11 mo late |
| AmoraBlue Jupiter Realty | Karvir | Dec 2023 | Dec 2025 | 2 yrs 10 mo late |
Delayed projects by district
All MaharashtraPune · 2,208Thane · 1,157Raigarh · 1,044Mumbai Suburban · 988Nashik · 482Palghar · 364Nagpur · 320Mumbai City · 247Aurangabad · 243Satara · 227Ratnagiri · 194Sangli · 176Solapur · 155Kolhapur · 131Sindhudurg · 72Amravati · 71Ahmednagar · 69Chandrapur · 39Jalgaon · 39Latur · 27Akola · 23Beed · 21Nanded · 18Dhule · 17Wardha · 16Buldana · 14Jalna · 11Parbhani · 9Bhandara · 8Yavatmal · 6
SourcesMahaRERA registrations, extension certificates, project pages and document listsA project counts as completed when MahaRERA shows it so: its status, or a completion or occupancy certificate in its documents. Dates are MahaRERA's; Deedo does not know the day a project was handed over.Report a problemMethodology