RERA projects in Karvir

582 projects under 591 MahaRERA registrations, registered 2017–2026. 14% have a completion date extended beyond the one promised.

582RERA projects
591Registrationssome projects hold several
225Completion still due336 past their completion date
18 monthsMedian extension beyond promised date14% of registrations extended
7Regulatory caseson 7 projects
68Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
2017149
201830
201931
202034
202138
202273
202366
202452
202542
202646

Projects in Karvir

582 projects registered with MahaRERA in this taluka and the places within it.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Mangalam ImperiaGaikwad Infrastructure Private LimitedPM11500026020811 Oct 202631 Dec 2031—Not yet due0
Time SquareGrey Bricks RealityPM11500026021061 Oct 202631 Dec 2030—Not yet due0
Yashshri - Grand Lake VistaDestiny BuildersPM11500026020491 Oct 202628 Feb 2029—Not yet due0
Shubhashish PrideVp DevelopersPR115000260197721 Sep 202631 Dec 2029—Not yet due0
Dwarka Adreno Building BRandive Builders And DevelopersPR115101260192715 Sep 202631 Dec 2030—Not yet due0
Aero CityPanjwani DevelopersPR115000260187611 Sep 202631 Dec 2031—Not yet due0
Eminent Vision TowerAce DevelopersPC115000260188911 Sep 202631 Dec 2031—Not yet due0
Radha RegencyVj And Space RealtorsPM115000260189211 Sep 202631 Dec 2031—Not yet due0
Geeta BlossomsViva Deva RealtyPM11500026017381 Sep 202631 Dec 2030—Not yet due0
Sharada SquareSquare Angle InfrastructurePM115000260154814 Aug 202631 Dec 2030—Not yet due0
Krystal TowerM/S SD AssociatesPR115000260151011 Aug 202631 Dec 2030—Not yet due0
Kalyani EnclaveMasute and Patil BuildersPR115000260125120 Jul 20261 May 2031—Not yet due0
Acharya Shree VidyasagarMasute Builders And DevelopersPR11500026011028 Jul 202631 Mar 2029—Not yet due0
Lm EmpireRajendra Lalasaheb ChavanPM115000260088822 Jun 202631 Dec 2030—Not yet due0
Vrindavan HeightsMahalaxmi BuildconPR115000260087822 Jun 202631 Dec 2028—Not yet due0
Sharad Pride 41Pratik InfraPR115000260076512 Jun 202630 Apr 2030—Not yet due0
Green CountyMirajkar Nichite Builders And Developers Private LimitedPR11500026006978 Jun 202631 Mar 2029—Not yet due0
Samarth ResidencyS P AssociatesPM11500026006151 Jun 202631 Dec 2030—Not yet due0
The BalsamM/S Jotiraditya BuildersPR115000260057229 May 202631 Dec 2030—Not yet due0
Loknagari Karande MalaVikesh Abhaykumar OswalPR115000260052825 May 202631 Mar 2030—Not yet due0
Nimbalkar HeritageMorbale Infra Project Private LimitedPM115000260049121 May 202629 Dec 2029—Not yet due0
Vasant Villas ResidencyShree Datta DevelopersPR115000260048721 May 202631 Dec 2029—Not yet due0
Anant Pride Phase IIIAnant Estate DevelopersPM115000260038311 May 202631 Dec 2030—Not yet due0
Sequoia RiseDevika ConstructionPR115000260026627 Apr 202631 Dec 2032—Not yet due0
Palace GrandeurMangal RealtyPR115000260022621 Apr 202631 Dec 2029—Not yet due0
Meen Kiran ResidencyBhumi BuildersPM115000260021718 Apr 202631 Dec 2030—Not yet due0
Goldenn ProsperaCskcon Private LimitedPM115000260011115 Apr 202631 Dec 2028—Not yet due0
Veerashri HeightsViraj Sunilkumar SarnaikPR115000250295018 Mar 202631 Dec 2029—Not yet due0
Lords HighlandBalraj Digambar JadhavP5300008110813 Mar 202631 May 2028—Not yet due0
33 West AvenueAtk InfraPM115000250272812 Mar 202631 Dec 2030—Not yet due0
Brahmandnayak SankulLandmark DevelopersPM115000250276312 Mar 202631 Dec 2030—Not yet due0
CellestiaBalaji InfraPM11500025026789 Mar 202631 Aug 2029—Not yet due0
Ideal Aero PlazaIdeal DevelopersPC11500025026759 Mar 202631 Dec 2027—Not yet due0
Varun Flora Township Jasmine BuildingVertex DevelopersPR11500025026399 Mar 202631 Dec 2030—Not yet due0
Joy NestAniket Rajendra KhadePR115000250222630 Jan 202631 Dec 2029—Not yet due0
Gateway ResidenciesSiddhivinayak DevelopersPR115000250220329 Jan 202631 Dec 2031—Not yet due0
Growing GraceAmit Bapu LokhandePR115000250220529 Jan 202631 Dec 2029—Not yet due0
WaterlilyLife Style DevelopersPR115000250220629 Jan 202631 Dec 2030—Not yet due0
SkylineShree ConstructionsPR115000250219227 Jan 202631 Dec 2030—Not yet due0
Redekar CrownHankare Patil LandmarksPM115000250216122 Jan 202631 Dec 2030—Not yet due0
The Indira PalatialShree Mahalaxmi RealtyPM115000250215622 Jan 202631 Dec 2029—Not yet due0
339 Tapasya NiwaraM/s Niwara Builders & DevelopersPR115000250213321 Jan 202631 Dec 2029—Not yet due0
Ideal EliteIdeal PropertiesPR115000250214321 Jan 202631 Dec 2028—Not yet due0
The ClayNarayan Auto WorksPR115000250177715 Dec 202531 Dec 2029—Not yet due0
The Grand PinnacleSairaj Builders And DevelopersPM115000250176715 Dec 202531 Dec 2030—Not yet due0
One EarthDeshpande InfraPR115000250173910 Dec 202531 Dec 2032—Not yet due0
Sky HeightsKirtikumar Balasaheb MasutePR115000250153221 Nov 202531 Dec 2028—Not yet due0
The ApexShiv Siddhi BuildconPM115000250126820 Oct 202531 Dec 2029—Not yet due0
HorizonDeshpande InfraPM115000250126116 Oct 202531 Dec 2028—Not yet due0
Padalkar ResidencyShirke More Builders and DevelopersPM115000250122213 Oct 202531 Dec 2028—Not yet due0
Shakuntala HeightsGaikwad Infrastructure Private LimitedPR11500025011289 Oct 202531 Dec 2028—Not yet due0
Ishwar KrupaChavan Builders and DevelopersPM115000250093424 Sep 202531 Dec 2028—Not yet due0
Nanda Bal ParadiseUnity Pramoters And BuildersPR115000250088222 Sep 202531 Dec 2029—Not yet due0
Amey Hi Life Wing C & DAmey EstatesPR115101250076311 Sep 202531 Dec 2032—Not yet due0
Dinkar ResidencySwamiraj DevelopersPM11500025005197 Aug 202531 Dec 2029—Not yet due0
Mira Co-Op Hou Soc Ltd KopRamsina Redefine Homes LLPPR115101250036525 Jul 202530 Sep 2027—Not yet due0
24 Keywest East And West AvenueKeywest InfraPM115000250026914 Jul 202531 Dec 2031—Not yet due0
Sahyadri HeightsShree Datta DevelopersP5300008083014 Jul 20251 Jun 2028—Not yet due0
Om ElegantSunil Gajanan ShrishrimalP5300008080810 Jul 202531 Dec 2027—Not yet due0
EvaraUrban InfraP530000807583 Jul 202531 Dec 2028—Not yet due0
Sanskruti HeightsShreeyog ConstructionsPR115000250012225 Jun 202531 Dec 2030—Not yet due0
Shaskiya And Z P Health Employees Sahakari Grah Nirman Sanstha Marya - Building No 3Shaskiya And Z P Health Employees Sahakari Grah Nirman Sanstha MaryaP5300008067725 Jun 202531 Dec 2028—Not yet due0
Pallavi Cooperative Housing SocietyVaradlaxmi And Kapade DevelopersP5300008050011 Jun 202531 Dec 2028—Not yet due0
Vardhaman Chintamani Wing CSpm ConstructionsP5300008048010 Jun 202530 Sep 2028—Not yet due0
Executive EmeraldRajendra Sukhraj OswalP5300008032021 May 202531 Dec 2028—Not yet due0
Palace EdgeH S VentureP5300008007122 Apr 202531 Dec 2028—Not yet due0
Dhanashree SvastiBedekar Lifespaces LLPP5300008000517 Apr 202531 Dec 2028—Not yet due0
Soni HeightsShashwat BuildersP530000799427 Apr 202531 Dec 2026—Not yet due0
Krishna ResidencyMahendrasingh Gumansingh DeoraP5300007989128 Mar 202531 Dec 2028—Not yet due0
Arihant PrideChougule Jirge DevelopersP5300007982427 Mar 202531 Dec 2028—Not yet due0
Highstreet CbdHighstreet DevelopersP53000079840, P53000079851, P53000079962 +227 Mar 202531 Dec 2031—Not yet due0
AnuradhaNitin Vishnu ShindeP5300007975326 Mar 202531 Dec 2029—Not yet due0
Krishnae ResidencyHemlata Sunil BhosaleP5300007978326 Mar 202530 Sep 2028—Not yet due0
Rdm Elite - KissanAbi BuildersP5300007967120 Mar 202531 May 2026—Promised date passed0
The SkylinePanjwani DevelopersP5300007957112 Mar 202531 Dec 2028—Not yet due0
Anand ParvaIndrajeet Anand DesaiP530000794727 Mar 202531 Dec 2028—Not yet due0
KP EmpireMahalaxmi InfraP530000794033 Mar 202531 Dec 2027—Not yet due0
Yash ParkShri Sai Shanti ConstructionsP53000079086, PR11510126001473 Feb 202531 Dec 2029—Not yet due0
TridentGrey Bricks Real-Estate & InfrastructureP530000787469 Jan 202531 Dec 2028—Not yet due0
HighfoldGrey Bricks RealityP530000787067 Jan 202531 Dec 2028—Not yet due0
Sbi Employees Omkar Co Op Housing SocietyConstruo DeveloperP530000786771 Jan 202531 Mar 2027—Not yet due0
Shri Mahalaxmi Co Operative Housing Society LtdShri Mahalaxmi Co Op Housing Society LtdP5300007858727 Dec 202431 Dec 2028—Not yet due0
Crystal SkylineBuild Angle Builders and DevelopersP5300007848217 Dec 202431 Dec 2029—Not yet due0
K Seven BreezeAkshay Sanjeev KushteP5300007814625 Nov 202431 Dec 2026—Not yet due0
Vrundavan Co-Op Housing Society Ltd.Swapnaprabha Realtors LLPP5300007778029 Oct 202431 Mar 2030—Not yet due0
Noble PointMasute and Patil BuildersP5300007774125 Oct 202431 Dec 2028—Not yet due0
The ReserveDeshpande InfraP5300007770121 Oct 202431 Dec 2027—Not yet due0
Sk SavitriSk Developers And BuildersP5300007754510 Oct 202431 Dec 2027—Not yet due0
Suyash HeightsSarvam DevelopersPR115000240000420 Sep 202415 Aug 2029—Not yet due0
Tirumala Residency PiwalawadaMahalaxmi InfrastructuresP5300007751520 Aug 202431 Dec 2028—Not yet due0
Sharayu PlazaPratik Sharad PatilP5300007726031 Jul 202431 May 2029—Not yet due0
Joy PalaceAmit Bapu LokhandeP5300007713523 Jul 202431 Dec 2025—Promised date passed0
Studio 233Amit Sunil ShahP5300007711823 Jul 202431 Dec 2026—Not yet due0
Hind Paradise C BuildingParshwa Estate DevelopersP5300007671521 Jun 202431 Dec 2028—Not yet due0
Anand Business CenterGaikwad Infrastructure Private LimitedP5300007663118 Jun 202431 Dec 2027—Not yet due0
Indira HeightsMukund Manohar JoshiP5300007662718 Jun 202431 Dec 2026—Not yet due0
Krystal TowersRaysons ConstructionsP5300005643031 May 202431 Dec 2030—Not yet due0
MahaLaxmi KrushnanganRajshri Satish KulkarniP5300005643831 May 202410 Nov 2026—Not yet due0
Laxmi ResidencyPotdar ConstructionsP5300005620521 May 202423 Mar 2030—Not yet due0
Jewel SquareRatnaraj Builders And DevelopersP5300005614216 May 202431 Dec 2028—Not yet due0

Other talukas in Kolhapur

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Deshpande Infra7 projects
  2. Shendre and Associates5 projects
  3. The Ideal Construction5 projects
  4. Bedekar Lifespaces LLP4 projects
  5. Mahabharat Construction Corporation4 projects
  6. M/S SD Associates4 projects
  7. Patki-Joshi Engineers and Contractors Pvt. Ltd.4 projects
  8. Raysons Constructions4 projects
  9. Tushar Mohanrao Khatavkar4 projects
  10. Varad Developers4 projects
Data through8 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology