RERA projects in Shirol
40 projects under 41 MahaRERA registrations, registered 2017–2026. 38% have a completion date extended beyond the one promised.
Taluka
40RERA projects
41Registrationssome projects hold several
12Completion still due28 past their completion date
4 monthsMedian extension beyond promised date38% of registrations extended
0Regulatory casesnone on MahaRERA's lists
49Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 7 |
| 2018 | 1 |
| 2019 | 3 |
| 2020 | 6 |
| 2021 | 1 |
| 2022 | 8 |
| 2023 | 6 |
| 2024 | 2 |
| 2025 | 4 |
| 2026 | 2 |
Projects in Shirol
40 projects registered with MahaRERA in this taluka and the places within it.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| OrchidBalaji Developers | PR1150002602261 | 12 Oct 2026 | 1 Aug 2029 | 1 Aug 2029 | Not yet due | 0 |
| Arnika Business BayParikh Sygmia Ventures | PC1150002600840 | 18 Jun 2026 | 31 Oct 2028 | 28 Feb 2029 | Extended 4 mo | 0 |
| Mahapadma AvenueM S Infrastructure | PM1150002501829 | 19 Dec 2025 | 1 Nov 2029 | 1 Mar 2030 | Extended 4 mo | 0 |
| Parshawa Sujit EmpireParshawa Developers | P53000080571 | 16 Jun 2025 | 31 Dec 2028 | 30 Apr 2029 | Extended 4 mo | 0 |
| Parshawa ParkParshawa Developers And Builders | P53000080128 | 29 Apr 2025 | 31 Dec 2027 | 30 Apr 2028 | Extended 4 mo | 0 |
| KrupasindhuDigvijay Bhagatsing Rajput | P53000077809 | 7 Nov 2024 | 31 Mar 2028 | 31 Jul 2028 | Extended 4 mo | 0 |
| Hira Moti Golden Square PlazaHira Moti Golden Square Developers LLP | P53000054807 | 12 Feb 2024 | 31 Dec 2026 | 30 Apr 2027 | Extended 4 mo | 0 |
| RajyogBalaji Developers | P53000053204 | 23 Oct 2023 | 15 Aug 2026 | 15 Aug 2026 | Promised date passed | 0 |
| Swapnvel IISmarth Constructions | P53000053071 | 12 Oct 2023 | 11 Apr 2028 | 11 Apr 2028 | Not yet due | 0 |
| Porwal TowerPorwal Tower | P53000051554 | 27 Jun 2023 | 31 Mar 2024 | 31 Dec 2025 | Extended 21 mo | 0 |
| Padmini HeightsSudarshan Appaso Chougule | P53000049831 | 6 Mar 2023 | 31 Dec 2027 | 31 Dec 2027 | Not yet due | 0 |
| H M HeritageH M Construction | P53000049322 | 7 Feb 2023 | 31 Dec 2025 | 31 Dec 2025 | Promised date passed | 0 |
| Shubhra HeightsSai Developers | P53000048626 | 10 Jan 2023 | 31 Dec 2024 | 31 Dec 2024 | Promised date passed | 0 |
| S P GalaxyS P Developers And Builders | P53000047228 | 12 Oct 2022 | 30 Dec 2026 | 30 Dec 2026 | Not yet due | 0 |
| KapidhwajMr.Atul Vijay Shinde and Mr.Rahul Vijay Shinde | P53000046924, P53000080266 | 20 Sep 2022 | 31 Dec 2028 | 30 Apr 2029 | Extended 4 mo | 0 |
| Green Heightspraveenkumar meghraj baldawa | P53000045966 | 15 Jun 2022 | 15 Aug 2025 | 15 Aug 2025 | Promised date passed | 0 |
| Ratnatray ResidencyVision Developers | P53000034826 | 28 Apr 2022 | 30 Sep 2024 | 30 Sep 2025 | Extended 12 mo | 0 |
| Parshwa AnnexParshwa Residency | P53000033472 | 22 Feb 2022 | 31 Dec 2024 | 31 Dec 2024 | Promised date passed | 0 |
| Arihant ParkShankar Maruti Kumbhar | P53000033150 | 9 Feb 2022 | 30 Jun 2025 | 30 Jun 2025 | Promised date passed | 0 |
| Kwality Fortune SapphireFortune Developers | P53000033237 | 9 Feb 2022 | 31 Jan 2026 | 31 Jan 2026 | Promised date passed | 0 |
| Shantimohini HeightsAshok Shantilal Runwal | P53000032372 | 4 Jan 2022 | 30 Aug 2022 | 30 Aug 2022 | Promised date passed | 0 |
| Green Vally Phase 1praveenkumar meghraj baldawa | P53000028451 | 2 Mar 2021 | 1 Jul 2023 | 1 Jul 2023 | Promised date passed | 0 |
| Parshwa EnclaveParshawa Properties | P53000025963 | 2 Aug 2020 | 31 Dec 2020 | 15 Feb 2024 | Extended 38 mo | 0 |
| Green Valley Phase 3H M Developers | P53000025545 | 28 Jun 2020 | 30 Jun 2023 | 30 Jun 2023 | Promised date passed | 0 |
| Padmini SquareSudarshan Appaso Chougule | P53000025539 | 28 Jun 2020 | 15 Sep 2023 | 15 Sep 2023 | Promised date passed | 0 |
Other talukas in Kolhapur
Most active promoters
By projects registered here, as named on MahaRERA.
- Balaji Developers2 projects
- Fortune Developers2 projects
- praveenkumar meghraj baldawa2 projects
- Shankar Maruti Kumbhar2 projects
- Smarth Constructions2 projects
- S P Developers And Builders2 projects
- Sudarshan Appaso Chougule2 projects
- Anandkishor Motilal Malu1 project
- Ashok Shantilal Runwal1 project
- Digvijay Bhagatsing Rajput1 project
Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology