Gadhinglaj, Kolhapur
Deedo IDDL-KOL-GADHINGLAJ3 in 10 MahaRERA registrations here have pushed their completion date back.
RERA projects80
Registrations80
Completion still due1453 past their date
Median extension4 months28% of registrations extended
Regulatory cases0none on MahaRERA's lists
8 in 10 registrations run late here
80 MahaRERA registrations in Gadhinglaj and the places within it
4 not yet due10 extended, not yet due53 past even the latest date13 no date on record
Extended registrations moved their completion date by a median of 4 months.
Projects in Gadhinglaj
80 projects registered with MahaRERA in this taluka and the places within it.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Dream Key 3Bhaskar Ramgonda Patil | Due Apr 2030, extended 4 mo | — | — |
| Galaxy HeightsA Space Developers | Due Apr 2030, extended 4 mo | — | — |
| Guru Vedas ResidencyGM Infrastructure | Due Apr 2030, extended 4 mo | — | — |
| Hira HeightsOm Construction | Due Apr 2029, extended 4 mo | — | — |
| Shubh ApartmentReema Premkant Jha | Due Apr 2028, extended 4 mo | — | 0% |
| Sayaji ResidencyVijaya Sayajirao Bhonsle | Due May 2029, extended 4 mo | — | 0% |
| Om Sai ParadiseShree Balaji Builders And Developers | Due May 2027 | — | — |
| Joshi Sabnis SankulCskcon Private Limited | 10 mo late | — | 4% |
| Parth Abhishekh ResidencyOmkar Construction | Due Apr 2029, extended 4 mo | — | 27% |
| Shri Ganesh ResidencyTanaji Vithoba Kokitkar | 6 mo late | — | — |
| Dream KeyBhaskar Ramgonda Patil | Due Apr 2029, extended 4 mo | — | 37% |
| SkylineSymbiotic Developers LLP | Due Dec 2027 | — | 1% |
| Shriram ResidencyMs Om Construction | 11 mo late | — | 96% |
| Abhishek VillasUjawala Bhaskar Patil | Due Dec 2028 | — | 100% |
| Shrivenkatesh ResidencyShrivenkatesh Lifespaces LLP | 10 mo late | — | 5% |
| Shree Arihant ResidencyShree Arihant Residence | 1 yr 9 mo late | — | — |
| Shiv BasavShri Bhaveshwari Builders And Developers Gadhinglaj Private Ltd | 10 mo late | — | 10% |
| S.K. PlazaSuhas Shivaji Kumbhar | 2 yrs 1 mo late | — | 0% |
| Sai Basav SankulShrikant Pandurang Vadgaonkar | 10 mo late | — | 0% |
| Om ResidencyOm Construction | 2 yrs 1 mo late | — | 93% |
| Shri Heramb Residency.Tanaji Vithoba Kokitkar | Due Apr 2029, extended 4 mo | — | — |
| Shree Bhakti ApartmentShree Bhakti Enterprises | 2 yrs 10 mo late | — | 0% |
| Sant ResidencyShri Mahalaxmi Builders | 3 yrs 7 mo late | — | 0% |
| AmstarRamsun Builders And Developers | 1 yr 9 mo late | — | 0% |
| Om Paradise Phase -2Patade Properties | 3 yrs 5 mo late | — | 21% |
Nearby: other talukas in Kolhapur
Most active promoters
- Bhaskar Ramgonda Patil6 projects
- Omkar Construction3 projects
- Tanaji Vithoba Kokitkar3 projects
- Anup Vikas Patil2 projects
- Hari Mauli Builders And Developers LLP2 projects
- Om Construction2 projects
- Patade Properties2 projects
- Rajendra Shankar Kokitkar2 projects
- Abhishek Builders1 project
- Ashish Anil Korgaonkar1 project
Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology