Shirol, Kolhapur
Deedo IDDL-KOL-SHIROL9 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects40
Registrations41some projects hold several
Completion still due1228 past their date
Median extension4 months38% of registrations extended
Regulatory cases0none on MahaRERA's lists
9 in 10 registrations run late here
41 MahaRERA registrations in Shirol and the places within it
4 not yet due8 extended, not yet due28 past even the latest date1 no date on record
Extended registrations moved their completion date by a median of 4 months.
Projects in Shirol
40 projects registered with MahaRERA in this taluka and the places within it.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Mahadik ChambersMaruti Siddhu Mahadik And Mahesh Maruti Mahadik | 4 yrs 11 mo late | — | — |
| Sai ResidencyRevanji Ramu Chougule | Completed | — | — |
| Yashashree ApartmentAnandkishor Motilal Malu | Completed | — | — |
| Sp EmpireSpk Developers | Completed | — | 100% |
| Swapnavel-ISmarth Constructions | Completed | — | 17% |
| Arihant PlazaShankar Maruti Kumbhar | Completed | — | 88% |
| Pramila HeightsSachin Patil Developers | Completed | — | — |
| Padmini PlazaSudarshan Chougule | Completed | — | 100% |
| Emh - 1Vistacore Lifespace Developers India Pvt Ltd | Completed, extended 3 yrs 6 mo | — | 84% |
| Fortune World OneFortune Developers | Completed | — | 38% |
| DattatirthGajraj Builders | 8 yrs 4 mo late | — | 56% |
| Oriental PlazaMark Construction | Completed, extended 2 yrs 5 mo | — | 23% |
| Sp Aadi ArcadeS P Developers And Builders | Completed | — | 67% |
| Kwality PlazaGhodawat Developers LLP | Completed, extended 2 yrs | — | 3% |
| P53000026703 | No date on record | — | — |
Nearby: other talukas in Kolhapur
Most active promoters
- Fortune Developers2 projects
- Praveenkumar Meghraj Baldawa2 projects
- Shankar Maruti Kumbhar2 projects
- Smarth Constructions2 projects
- S P Developers And Builders2 projects
- Anandkishor Motilal Malu1 project
- Ashok Shantilal Runwal1 project
- Balaji Developers1 project
- Balaji Developers1 project
- Digvijay Bhagatsing Rajput1 project
Shirol, in questions
How many projects in Shirol run late?
9 in 10 MahaRERA registrations (36 of 41): their completion date was extended or has passed, data through 21 Oct 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Shirol by Deedo. Medians on fewer than 3 deeds are not shown.
Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology