Its promised completion date, Dec 2022, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 0% of its units are booked.

Karvir, Maharashtra 416001 · by Cme Hitech Construction Limited

Delivery3 yrs 11 mo past duePromised Dec 2022 · no extension on record · not shown completedRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales0% booked0 of 36 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Its promised completion date, Dec 2022, has passed and MahaRERA does not show it completed

  • This projectRegistered 28 Jun 2020, completion promised 1 Dec 2022, and still not shown completed today.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP53000025513
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5300002551328 Jun 20201 Dec 20221 Dec 2022Cme Hitech Construction LimitedProject page
Documents19

1 document held by Deedo, 18 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardPAN CARD-CME.pdf · uploaded 21 Mar 2020Source

Legal

  • Legal Title reportCopy of the legal title report.pdf · uploaded 21 Mar 2020Source
  • Declaration Form BFORM-B-min.pdf · uploaded 21 Mar 2020Source

Migrated

  • 1 PAN CardPAN CARD-CME.pdf · uploaded 21 Mar 2020Source
  • 1 Copy of the legal title reportCopy of the legal title report.pdf · uploaded 21 Mar 2020Source
  • 1 Details of encumbrancesDetails of encumbrances.pdf · uploaded 21 Mar 2020Source
  • 1 Copy of Layout Approval (in case of layout)Sanction Plan 02_.pdf · uploaded 21 Mar 2020Source
Show all 19 documentsShow fewer documents

Migrated

  • 1 Building Plan Approval / NA Order for plotted developmentSactionPlan01.pdf · uploaded 21 Mar 2020Source
  • 1 Commencement Certificates / NA Order for plotted developmentSanciton Plan Revised 16-10-16.pdf · uploaded 21 Mar 2020Source
  • 1 Declaration in FORM BFORM-B-min.pdf · uploaded 21 Mar 2020Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate-FORM 1-min.pdf · uploaded 21 Mar 2020Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA FORM 3-min (1).pdf · uploaded 21 Mar 2020Source
  • 1 Proforma of Allotment letterCME ATS draft 1.pdf · uploaded 21 Mar 2020Source
  • 2 Proforma of Allotment letterCME ATS draft 1.pdf · uploaded 21 Mar 2020Source
  • 3 Proforma of Allotment letterCME ATS draft 1.pdf · uploaded 21 Mar 2020Source

Technical

  • DocumentSactionPlan01.pdf · uploaded 21 Mar 2020Source
  • DocumentSanction Plan 02_.pdf · uploaded 21 Mar 2020Source

Technical (Architect)

  • DocumentArchitect Certificate-FORM 1-min.pdf · uploaded 21 Mar 2020Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvals

As registered with MahaRERA and published on its project page

Project type
Commercial
Status on MahaRERA
Certificate Signed
Unit types
2BHK, Office space, Shop36 units in all
Address
326/A, E Ward, New Shahupuri Kolhapur, Near Dabholkar CornerPIN 416001
Land area for this project
1,202 sq m (12,936 sq ft)
Permissible built-up area
1,678 sq m (18,066 sq ft)
Sanctioned built-up area
1,678 sq m (18,066 sq ft)
Designated bank account
119
Developed in phases
No

Land as published on MahaRERA's project page

326/A, E Ward

Boundaries

North
Government Road
South
Petrol Pump
East
Remaining Part of Area 326B
West
Government Road

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking36 units

0 of 36 units booked (0%), as the promoter reported to MahaRERA

2BHK · 4 unitsOffice space · 18 unitsShop · 14 units
TypeCarpet areaUnitsBooked
2BHK257.16 sq m · 2,768 sq ft40
Office space1,449.54 sq m · 15,603 sq ft180
Shop275.01 sq m · 2,960 sq ft140

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals3

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectAvinash Naik—
Chartered accountantS S Kulkarni—
EngineerAbhijit Bhosale—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology