RERA projects in Kabnur (Ct)

2 projects under 2 MahaRERA registrations, registered 2017–2025. 100% have a completion date extended beyond the one promised.

Locality
2RERA projects
2Registrations
1Completion still due1 past their completion date
32 monthsMedian extension beyond promised date100% of registrations extended
0Regulatory casesnone on MahaRERA's lists
2Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20171
20180
20190
20200
20210
20220
20230
20240
20251

Projects in Kabnur (Ct)

2 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
KrishnaprabhaM/s Citi DevelopersPR115101250026814 Jul 202531 Dec 202730 Apr 2028Extended 4 mo0
Urban Life Phase II Building CAtharv Estates India Private LimitedP5300000217931 Jul 201731 Jul 201831 Jul 2023Extended 60 mo0

Other localities in Hatkanangle

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Atharv Estates India Private Limited1 project
  2. M/s Citi Developers1 project
Data through11 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology