RERA projects in Vadgaon Kasaba
3 projects under 3 MahaRERA registrations, registered 2017–2019. None has an extended completion date on record.
3RERA projects
3Registrations
0Completion still due3 past their completion date
—Median extension beyond promised date0% of registrations extended
0Regulatory casesnone on MahaRERA's lists
0Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 1 |
| 2018 | 1 |
| 2019 | 1 |
Projects in Vadgaon Kasaba
3 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Mahalaxmi ComplexMahalaxmi Complex | P53000021837 | 31 Jul 2019 | 20 Jun 2023 | — | Promised date passed | 0 |
| Silver Dream CRejoice Buildocn | P53000018660 | 22 Nov 2018 | 26 Dec 2022 | — | Promised date passed | 0 |
| Riddhi Siddhi ComplexRiddhi Siddhi Complex | P53000013964 | 2 Nov 2017 | 31 Dec 2018 | — | Promised date passed | 0 |
Other localities in Hatkanangle
- Ichalkaranji (M Cl)57 projects
- Vadgaon Kasba (M Cl)11 projects
- Hupari (Ct)2 projects
- Kabnur (Ct)2 projects
- Hatkanangale1 project
- Majale1 project
- Shiroli1 project
- Vathar Tarf Vadgaon1 project
Most active promoters
By projects registered here, as named on MahaRERA.
- Mahalaxmi Complex1 project
- Rejoice Buildocn1 project
- Riddhi Siddhi Complex1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology