RERA projects in Ichalkaranji (M Cl)
57 projects under 57 MahaRERA registrations, registered 2017–2026. 19% have a completion date extended beyond the one promised.
Locality
57RERA projects
57Registrations
22Completion still due35 past their completion date
21 monthsMedian extension beyond promised date19% of registrations extended
2Regulatory caseson 2 projects
6Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 11 |
| 2018 | 11 |
| 2019 | 3 |
| 2020 | 2 |
| 2021 | 5 |
| 2022 | 8 |
| 2023 | 5 |
| 2024 | 1 |
| 2025 | 5 |
| 2026 | 6 |
Projects in Ichalkaranji (M Cl)
57 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Kamal KunjBiyani & Sons | PR1150002601263 | 20 Jul 2026 | 31 Mar 2028 | — | Not yet due | 0 |
| Mg Market Block AMg Developers | PR1150002600850 | 18 Jun 2026 | 31 Dec 2030 | — | Not yet due | 0 |
| Shri Ram ResidencyShri Mangaraya Developers | PR1151012600720 | 10 Jun 2026 | 31 Dec 2027 | — | Not yet due | 0 |
| Vihanga ResidencyIndo Buildcon Developers | PM1150002600245 | 22 Apr 2026 | 31 Dec 2030 | — | Not yet due | 0 |
| Digvijay HeightsDigvijay Associates Builders Developers & Earthmovers | PR1150002600054 | 9 Apr 2026 | 31 Mar 2031 | — | Not yet due | 0 |
| Maheshwari HeightsSubhash Ramgopal Maheshwari | P53000081087 | 16 Jan 2026 | 31 Dec 2027 | — | Not yet due | 0 |
| Emmanuel CornerstoneSantosh Mohan Arawattigi | P53000081072 | 16 Dec 2025 | 31 Oct 2032 | — | Not yet due | 0 |
| Niranjan HeightsProprietor B S Developers SABIHA FIROJ SHIKALAGAR | PM1150002501276 | 20 Oct 2025 | 31 Dec 2029 | — | Not yet due | 0 |
| Galaxy HeightsAditya Bhimrao Kolawale | PM1150002500795 | 15 Sep 2025 | 31 Mar 2029 | — | Not yet due | 0 |
| Brk Aura ResidencyManibhadra (Brk) Builders And Developers | P53000080755 | 3 Jul 2025 | 31 Dec 2029 | — | Not yet due | 0 |
| Ekdant HeightsPerfect Developers-Ekdant Heights | P53000080745 | 1 Jul 2025 | 31 Dec 2027 | — | Not yet due | 0 |
| Vrindavan ParadiseHbd Developers | P53000054990 | 21 Feb 2024 | 31 Dec 2028 | — | Not yet due | 0 |
| Nirmal TowerVimalkumar Pukhraj Kothari | P53000053616 | 10 Nov 2023 | 31 Dec 2028 | — | Not yet due | 0 |
| Vathare ElitesJahir Chandsab Soudagar | P53000053102 | 16 Oct 2023 | 25 Sep 2027 | — | Not yet due | 0 |
| City CrownSaiyam Santosh Shah | P53000052975 | 10 Oct 2023 | 31 Dec 2027 | — | Not yet due | 0 |
| Jijamata ParkTodkar Builders | P53000052974 | 6 Oct 2023 | 31 Mar 2027 | — | Not yet due | 0 |
| Mahaveer ResidencySunita Sureshkumar Lalwani | P53000050315 | 1 Apr 2023 | 31 Mar 2026 | — | Promised date passed | 0 |
| Fortune Sky CityFortune Developers | P53000048192 | 15 Dec 2022 | 31 Dec 2028 | — | Not yet due | 0 |
| Swapnshilp TowerShaheen Mansoor Bijali | P53000047148 | 10 Oct 2022 | 30 Dec 2022 | 30 Dec 2024 | Extended 24 mo | 0 |
| Laxmi CasaMahesh Sohanlal Jhawar | P53000046625 | 25 Aug 2022 | 30 Apr 2025 | 31 Dec 2026 | Extended 20 mo | 0 |
| Sahyadri ComplexSarika Vasant Korvi | P53000045702 | 6 Jun 2022 | 1 May 2028 | — | Not yet due | 0 |
| NisargayanSidra Developers | P53000045421 | 18 May 2022 | 2 Jun 2029 | — | Not yet due | 0 |
| Jamadade HeightsGafari-Harale | P53000034110 | 24 Mar 2022 | 31 Dec 2024 | — | Promised date passed | 0 |
| Navkar HightsOssiya Developers | P53000033927 | 14 Mar 2022 | 1 Jan 2026 | — | Promised date passed | 0 |
| Swapnshilp PlazaShaheen Mansoor Bijali | P53000033062 | 3 Feb 2022 | 31 Dec 2024 | — | Promised date passed | 1 |
Other localities in Hatkanangle
- Vadgaon Kasba (M Cl)11 projects
- Vadgaon Kasaba3 projects
- Hupari (Ct)2 projects
- Kabnur (Ct)2 projects
- Hatkanangale1 project
- Majale1 project
- Shiroli1 project
- Vathar Tarf Vadgaon1 project
Most active promoters
By projects registered here, as named on MahaRERA.
- Fortune Developers2 projects
- Shaheen Mansoor Bijali2 projects
- Sidra Developers2 projects
- Surabhi Developers2 projects
- Todkar Builders2 projects
- Vijay Virupaksha Galgale2 projects
- Abhijeet Hambirrao Kharade1 project
- Aditya Bhimrao Kolawale1 project
- Bhagwati Builders And Developers1 project
- Biyani & Sons1 project
Data through11 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology