Sarnobatwadi, Kolhapur
No MahaRERA registration here has an extended completion date on record.
RERA projects2
Registrations2
Completion still due02 past their date
Median extensionNot on record0% of registrations extended
Regulatory cases0none on MahaRERA's lists
10 in 10 registrations run late here
2 MahaRERA registrations in Sarnobatwadi
2 past even the latest date
Projects in Sarnobatwadi
2 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Kene TowerAkshay Shankarrao Powar | P53000016544 | 23 May 2018 | 5 May 2022 | 5 May 2022 | Promised date passed | 0 |
| Bellmount TowerRashid Shamshuddin Bargir | P53000006208 | 14 Aug 2017 | 30 Dec 2021 | 30 Dec 2021 | Promised date passed | 0 |
Nearby: other localities in Karvir
Most active promoters
- Akshay Shankarrao Powar1 project
- Rashid Shamshuddin Bargir1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Methodology