RERA projects in Gadhinglaj
27 projects under 27 MahaRERA registrations, registered 2017–2026. 7% have a completion date extended beyond the one promised.
Locality
27RERA projects
27Registrations
6Completion still due21 past their completion date
51 monthsMedian extension beyond promised date7% of registrations extended
0Regulatory casesnone on MahaRERA's lists
1Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 5 |
| 2018 | 1 |
| 2019 | 3 |
| 2020 | 3 |
| 2021 | 2 |
| 2022 | 5 |
| 2023 | 4 |
| 2024 | 1 |
| 2025 | 2 |
| 2026 | 1 |
Projects in Gadhinglaj
27 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Dream Key 3Bhaskar Ramgonda Patil | PR1150002601051 | 6 Jul 2026 | 31 Dec 2029 | — | Not yet due | 0 |
| Guru Vedas ResidencyGM Infrastructure | PR1150002501087 | 1 Oct 2025 | 31 Dec 2029 | — | Not yet due | 0 |
| Shubh ApartmentReema Premkant Jha | P53000080724 | 27 Jun 2025 | 31 Dec 2027 | — | Not yet due | 0 |
| Om Sai ParadiseShree Balaji Builders And Developers | P53000055702 | 15 Apr 2024 | 1 May 2027 | — | Not yet due | 0 |
| Shri Ganesh ResidencyTanaji Vithoba Kokitkar | P53000051785 | 3 Jul 2023 | 30 Apr 2026 | — | Promised date passed | 0 |
| SkylineSymbiotic Developers LLP | P53000051290 | 8 Jun 2023 | 31 Dec 2027 | — | Not yet due | 0 |
| Shrivenkatesh ResidencyShrivenkatesh Lifespaces LLP | P53000050598 | 21 Apr 2023 | 31 Dec 2025 | — | Promised date passed | 0 |
| Shree Arihant ResidencyShree Arihant Residence | P53000050335 | 5 Apr 2023 | 15 Jan 2025 | — | Promised date passed | 0 |
| Sai Basav SankulShrikant Pandurang Vadgaonkar | P53000045993 | 15 Jun 2022 | 31 Dec 2025 | — | Promised date passed | 0 |
| Shri Heramb Residency.Tanaji Vithoba Kokitkar | P53000045382 | 18 May 2022 | 31 Dec 2028 | — | Not yet due | 0 |
| Shree Bhakti ApartmentShree Bhakti Enterprises | P53000035152 | 10 May 2022 | 31 Dec 2023 | — | Promised date passed | 0 |
| Sant ResidencyShri Mahalaxmi Builders | P53000033725 | 8 Mar 2022 | 31 Mar 2023 | — | Promised date passed | 0 |
| Om Paradise Phase -2Patade Properties | P53000033167 | 9 Feb 2022 | 31 May 2023 | 31 May 2025 | Extended 24 mo | 0 |
| MuktanganAnup Vikas Patil | P53000028732 | 25 Mar 2021 | 30 Jun 2023 | — | Promised date passed | 0 |
| Kalbhairav ResidencyTanaji Vithoba Kokitkar | P53000028444 | 2 Mar 2021 | 29 Aug 2024 | — | Promised date passed | 0 |
| Rajesh Mahadev BorgaveRajesh Mahadev Borgave | P53000026072 | 15 Aug 2020 | 15 Aug 2020 | — | Promised date passed | 0 |
| Mulla BrothersRafik Hasan Mulla | P53000025057 | 18 Mar 2020 | 30 Dec 2023 | — | Promised date passed | 0 |
| Shrinandan ApartmentShree Builders And Developers | P53000023676 | 2 Jan 2020 | 1 Nov 2022 | — | Promised date passed | 0 |
| Guruchandra ResidencyHeramb Developers | P53000022047 | 25 Aug 2019 | 30 Dec 2022 | — | Promised date passed | 0 |
| Ayodhya Park Phase IAshok Ramchandra Yamgekar | P53000019325 | 23 Jan 2019 | 30 May 2022 | — | Promised date passed | 0 |
| Mahalaxmi SankulSandip Ganpati Chechar | P53000019206 | 9 Jan 2019 | 30 Jan 2023 | — | Promised date passed | 0 |
| Shobha HeightsAnup Vikas Patil | P53000015035 | 22 Jan 2018 | 30 Dec 2021 | — | Promised date passed | 0 |
| Om ParadisePatade Properties | P53000008750 | 13 Nov 2017 | 31 Dec 2017 | 30 Jun 2024 | Extended 78 mo | 0 |
| Mayur Vihar ApartmentHeramb Builders And Developers | P53000013377 | 26 Sep 2017 | 31 Mar 2018 | — | Promised date passed | 0 |
| Shri Ram PlazaOmkar Construction | P53000002629 | 2 Aug 2017 | 13 Oct 2020 | — | Promised date passed | 0 |
Other localities in Gadhinglaj
Most active promoters
By projects registered here, as named on MahaRERA.
- Tanaji Vithoba Kokitkar3 projects
- Anup Vikas Patil2 projects
- Bhaskar Ramgonda Patil2 projects
- Patade Properties2 projects
- Ashish Anil Korgaonkar1 project
- Ashok Ramchandra Yamgekar1 project
- GM Infrastructure1 project
- Heramb Builders And Developers1 project
- Heramb Developers1 project
- Omkar Construction1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology