9 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects23
Registrations23
Completion still due617 past their date
Median extension4 months26% of registrations extended
Regulatory cases0none on MahaRERA's lists

9 in 10 registrations run late here

23 MahaRERA registrations in Gadhinglaj (M Cl)

2 not yet due4 extended, not yet due17 past even the latest date

Extended registrations moved their completion date by a median of 4 months.

Projects in Gadhinglaj (M Cl)

23 projects registered with MahaRERA.

ProjectDeliveryMedian ₹/sq ftBooked
Sayaji ResidencyVijaya Sayajirao BhonsleDue May 2029, extended 4 mo——
Parth Abhishekh ResidencyOmkar ConstructionDue Apr 2029, extended 4 mo—27%
Dream KeyBhaskar Ramgonda PatilDue Apr 2029, extended 4 mo—37%
Shriram ResidencyMs Om ConstructionCompleted—96%
Abhishek VillasUjawala Bhaskar PatilCompleted—100%
All 23 projects →
Gadhinglaj (M Cl) market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Nearby: other municipal areas in Gadhinglaj

Most active promoters

  1. Bhaskar Ramgonda Patil4 projects
  2. Omkar Construction2 projects
  3. Rajendra Shankar Kokitkar2 projects
  4. Abhishek Builders1 project
  5. Ashwamedh Developers1 project
  6. Balaji Construction1 project
  7. Creative Trunkey Projects Pvt Ltd1 project
  8. Manohar Baburao Gaikwad1 project
  9. Ms Om Construction1 project
  10. Om Construction1 project

Gadhinglaj (M Cl), in questions

How many projects in Gadhinglaj (M Cl) run late?

9 in 10 MahaRERA registrations (21 of 23): their completion date was extended or has passed, data through 21 Oct 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Gadhinglaj (M Cl) by Deedo. Medians on fewer than 3 deeds are not shown.

Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology