Kagal (M Cl), Kolhapur
6 in 10 MahaRERA registrations here have pushed their completion date back.
RERA projects16
Registrations18some projects hold several
Completion still due108 past their date
Median extension4 months61% of registrations extended
Regulatory cases1on 1 project
Projects in Kagal (M Cl)
16 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Sadguru PlazaMadhuri Shrikant Shirale | PM1150002502200 | 29 Jan 2026 | 31 Dec 2028 | 30 Apr 2029 | Extended 4 mo | 0 |
| Daffodils ResidencyM S Jadhav Huf | P53000077871 | 7 Nov 2024 | 28 Feb 2027 | 28 Jun 2027 | Extended 4 mo | 0 |
| The LandmarkSwarajya Associates | P53000055024 | 26 Feb 2024 | 31 Dec 2026 | 30 Apr 2027 | Extended 4 mo | 0 |
| Kagal Residency Phase IIIMahesh Namdev Magar | P53000046796 | 10 Sep 2022 | 31 Dec 2026 | 31 Dec 2026 | Not yet due | 0 |
| Pearl ResidencyAnnasaheb Adinath Athane | P53000031852 | 22 Nov 2021 | 31 Dec 2023 | 31 Dec 2023 | Promised date passed | 0 |
| Construction of 160 EWS 84 LIG and 28 MIG T/s at Gat no 425/2 Part Kagal Dist Kolhapur under PMAYPune Housing and Area Development Board Pune | P53000029273 | 10 May 2021 | 31 Dec 2028 | 30 Apr 2029 | Extended 4 mo | 1 |
| Construction of 176 EWS and 56 LIG t/s at Gat no 425/2 part Kagal, Dist. kolhapur under PMAY schemePune Housing and Area Development Board Pune | P53000029274 | 10 May 2021 | 31 Dec 2028 | 30 Apr 2029 | Extended 4 mo | 0 |
| Construction of 96 EWS and 84 LIG T/s at Gat no 425/2 part area 1.2 ha Kagal Dist KolhapurPune Housing and Area Development Board Pune | P53000028659 | 25 Mar 2021 | 30 Jun 2029 | 30 Oct 2029 | Extended 4 mo | 0 |
| Powar ComplexPrakash Tatoba Powar | P53000028421 | 2 Mar 2021 | 30 Jun 2026 | 30 Oct 2026 | Extended 4 mo | 0 |
| Pawanraj ResidencyShree Samarth Infrastructure | P53000028164 | 10 Feb 2021 | 30 Jun 2026 | 30 Oct 2026 | Extended 4 mo | 0 |
| Tej ResidencyVishal Namdev Patil | P53000023122 | 2 Dec 2019 | 1 Nov 2024 | 1 Nov 2024 | Promised date passed | 0 |
| Royal OrchidSushant Vijay Bhalbar | P53000017548 | 24 Aug 2018 | 1 Nov 2023 | 1 Nov 2023 | Promised date passed | 0 |
| Royal AnnexSushant Vijay Bhalbar | P53000017431 | 13 Aug 2018 | 1 Nov 2023 | 31 Dec 2025 | Extended 25 mo | 0 |
| Balaji Infra ProjectsBalaji Infra Projects | P53000015463 | 27 Feb 2018 | 28 Feb 2021 | 6 Apr 2022 | Extended 14 mo | 0 |
| Omkar ComplexBalaram Piraji Shingte | P53000004415, P53000051770 | 9 Aug 2017 | 31 Mar 2024 | 31 Mar 2024 | Promised date passed | 0 |
| Viraj CityBhuyekar Patil Construction Company | P53000004289, P53000034792 | 9 Aug 2017 | 31 Dec 2026 | 30 Apr 2027 | Extended 4 mo | 0 |
Most active promoters
- Pune Housing and Area Development Board Pune3 projects
- Sushant Vijay Bhalbar2 projects
- Annasaheb Adinath Athane1 project
- Balaji Infra Projects1 project
- Balaram Piraji Shingte1 project
- Bhuyekar Patil Construction Company1 project
- Madhuri Shrikant Shirale1 project
- Mahesh Namdev Magar1 project
- M S Jadhav Huf1 project
- Prakash Tatoba Powar1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Methodology