Sadguru Plaza
Deedo IDDP-KOL-8E53Completion was pushed back 4 months, to Apr 2029; no MahaRERA orders on record; 0% of its units are booked.
Kagal (M Cl), Kolhapur 416216 · by Madhuri Shrikant Shirale
Buying a flat here?
See every deed registered on it.
Completion was pushed back 4 months, to Apr 2029
- This projectRegistered 29 Jan 2026, completion promised 31 Dec 2028, revised to 30 Apr 2029.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales first, then rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationPM1150002502200
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| PM1150002502200 | 29 Jan 2026 | 31 Dec 2028 | 30 Apr 2029 | Madhuri Shrikant Shirale | Project page |
Documents24
1 document held by Deedo, 23 filings listed on MahaRERA's project page
Finance
Legal
- OthersAnnexure A - Disclosure of Interest in other ORG.pdf · uploaded 24 Nov 2025Source
- OthersEncumbrances Concerned to legal.pdf · uploaded 24 Nov 2025Source
- Declaration Form BLegal Title and Search Report.pdf · uploaded 24 Nov 2025Source
- Declaration Form BForm B Declaration.pdf · uploaded 24 Nov 2025Source
- Declaration Form BSale Deed.pdf · uploaded 24 Nov 2025Source
Show all 24 documentsShow fewer documents
Legal
- Declaration Form BProperty Card 2115.pdf · uploaded 28 Nov 2025Source
Migrated
- Withdrawal Update Form 1Form 1.pdf · uploaded 20 Apr 2026Source
- Withdrawal Update Form 2Engineers Certificate.pdf · uploaded 20 Apr 2026Source
- Withdrawal Update Form 3Form 3.pdf · uploaded 20 Apr 2026Source
- Form 2A (FY 2025-2026)Form 2A.pdf · uploaded 20 Apr 2026Source
- Withdrawal Update Form 1Form 1_compressed (17).pdf · uploaded 17 Jul 2026Source
- Withdrawal Update Form 2Form 2.pdf · uploaded 17 Jul 2026Source
- Withdrawal Update Form 3Form 3_compressed (93).pdf · uploaded 17 Jul 2026Source
Technical
- OthersForm 1.pdf · uploaded 24 Nov 2025Source
- OthersFormat D - Declaration about CC.pdf · uploaded 24 Nov 2025Source
- DocumentSANCTION PLAN.pdf · uploaded 25 Nov 2025Source
- DocumentSANCTION PLAN.pdf · uploaded 25 Nov 2025Source
- DocumentAnnexure A - One Plot One Registration.pdf · uploaded 28 Nov 2025Source
- OthersForm 2.pdf · uploaded 28 Nov 2025Source
Technical (Architect)
- DocumentForm 1_compressed (17).pdf · uploaded 17 Jul 2026Source
Technical (Engineer)
- DocumentForm 2.pdf · uploaded 17 Jul 2026Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel PLOT NO. 295 OUT OF C.S.NO. 2115
As registered with MahaRERA and published on its project page
- Project type
- Mixed
- Status on MahaRERA
- Certificate Signed
- Unit types
- —21 units in all
- Address
- Kagal, Jaysingrao ParkPIN 416216
- Village
- Kagal (M Cl), Kagal taluka
- Location
- 16.58907, 74.31034
- Land area for this project
- 561 sq m (6,042 sq ft)
- Permissible built-up area
- 1,262 sq m (13,579 sq ft)
- Sanctioned built-up area
- 1,262 sq m (13,579 sq ft)
- Recreational open space
- 0 sq m (0 sq ft)
- Designated bank account
- 159
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
PLOT NO. 295 OUT OF C.S.NO. 2115
Boundaries
- North
- 12 Meter Road
- South
- Plot No. 293
- East
- Plot No. 294
- West
- 12 Meter Road
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking21 units
21 units registered
| Type | Carpet area | Units |
|---|---|---|
| — | — | 21 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals3
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Gajendra Gopal Sabale | — |
| Engineer | Amrut Krushna Savant | — |
| Engineer | Pratik Rajendra Barad | — |
Source: MahaRERA project page. Contact details are not shown.
Other projects in Kagal (M Cl)
- Daffodils ResidencyRERA P53000077871
- The LandmarkRERA P53000055024
- Kagal Residency Phase IIIRERA P53000046796
- Pearl ResidencyRERA P53000031852
- Construction of 160 EWS 84 LIG and 28 MIG T/s at Gat no 425/2 Part Kagal Dist Kolhapur under PMAYRERA P53000029273
- Construction of 176 EWS and 56 LIG t/s at Gat no 425/2 part Kagal, Dist. kolhapur under PMAY schemeRERA P53000029274
- Construction of 96 EWS and 84 LIG T/s at Gat no 425/2 part area 1.2 ha Kagal Dist KolhapurRERA P53000028659
- Powar ComplexRERA P53000028421
All 16 projects in Kagal (M Cl) · Compare Sadguru Plaza with another project