RERA projects in Vadghar (Ct)
421 projects under 422 MahaRERA registrations, registered 2017–2026. 19% have a completion date extended beyond the one promised.
421RERA projects
422Registrationssome projects hold several
61Completion still due361 past their completion date
18 monthsMedian extension beyond promised date19% of registrations extended
3Regulatory caseson 3 projects
9Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 1 |
| 2018 | 41 |
| 2019 | 151 |
| 2020 | 77 |
| 2021 | 55 |
| 2022 | 25 |
| 2023 | 25 |
| 2024 | 36 |
| 2025 | 10 |
| 2026 | 1 |
Projects in Vadghar (Ct)
421 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Siddhivinayak DarshanRiu Homes Private Limited | PM1270002600427 | 15 May 2026 | 31 Mar 2031 | — | Not yet due | 0 |
| Shree Sai ApartmentShreeji Developers | PR1270002501601 | 27 Nov 2025 | 31 Dec 2029 | — | Not yet due | 0 |
| Shree BallaleshwarVirat And Sanskar Group | PR1270002501446 | 11 Nov 2025 | 31 Dec 2028 | — | Not yet due | 0 |
| Chander NiwasShree Surya Developers | PM1270002501252 | 16 Oct 2025 | 31 Dec 2026 | — | Not yet due | 0 |
| Sai GaneshSai Ganesh Reality | PM1270002500972 | 26 Sep 2025 | 31 Dec 2026 | — | Not yet due | 0 |
| Sagar HeightsShree Sidhvasa Developers | PR1270002500525 | 11 Aug 2025 | 31 Jul 2028 | — | Not yet due | 0 |
| Siddhivinayak PlanetM/s Siddhivinayak Infratech | PM1270002500252 | 10 Jul 2025 | 31 Dec 2028 | — | Not yet due | 0 |
| J. K. ParadiseJ. K. Infracon | P52000080392 | 2 Jun 2025 | 31 Dec 2026 | — | Not yet due | 0 |
| Sai PrestigeSai Atharva Developers | P52000079716 | 21 Mar 2025 | 31 Mar 2027 | — | Not yet due | 0 |
| Matruchhaya HeightsShree Ganesh Infra | P52000079012 | 31 Jan 2025 | 31 Dec 2028 | — | Not yet due | 0 |
| Venkatesha AlankarVenkatesha Realty LLP | P52000078769 | 13 Jan 2025 | 31 Dec 2027 | — | Not yet due | 0 |
| Sai SolitaireGuru Sai Realty | P52000078609 | 27 Dec 2024 | 31 Dec 2028 | — | Not yet due | 0 |
| Satyam TridentSatyam Infracon Private Limited | P52000078461 | 12 Dec 2024 | 31 Dec 2026 | — | Not yet due | 0 |
| Yamuna NiwasM/s Vighnaharta Properties | P52000078446 | 12 Dec 2024 | 31 Jul 2027 | — | Not yet due | 0 |
| Sai SamarthSandhya Sachin Shah | P52000078299 | 4 Dec 2024 | 31 Dec 2026 | — | Not yet due | 0 |
| Royal ResidencyDestiny Realty | P52000078124 | 25 Nov 2024 | 31 Dec 2027 | — | Not yet due | 0 |
| Sai MauliChirag Deepak Gadge | P52000077914 | 13 Nov 2024 | 30 Jun 2026 | — | Promised date passed | 0 |
| Sirvi HilltopSirvi Infra | P52000077662 | 21 Oct 2024 | 31 Dec 2026 | — | Not yet due | 0 |
| Crystal PlazaSiddhivinayak Realty | P52000077625 | 17 Oct 2024 | 25 Dec 2027 | — | Not yet due | 0 |
| Sai PalaceSai Shlok Developers | P52000077254 | 31 Jul 2024 | 31 Dec 2026 | — | Not yet due | 0 |
| Kunda ResidencyEpsilon Realty | P52000077047 | 16 Jul 2024 | 31 Dec 2025 | — | Promised date passed | 0 |
| OpulencePramod Prakash Patil | P52000076868 | 3 Jul 2024 | 31 Dec 2027 | — | Not yet due | 0 |
| SahejanandPrasad Construction | P52000076845 | 28 Jun 2024 | 30 Nov 2026 | — | Not yet due | 0 |
| Vishwanath VaastuOm Vaastu Enterprises LLP | P52000076808 | 28 Jun 2024 | 31 Dec 2027 | — | Not yet due | 0 |
| Natha HeightsPrem Nandkishor Patil | P52000076667 | 20 Jun 2024 | 31 Dec 2027 | — | Not yet due | 0 |
| Patil ApartmentNavnath Hanuman Patil | P52000076658 | 20 Jun 2024 | 31 Mar 2027 | — | Not yet due | 0 |
| Sai ShrushtiAshtavinayak Infratech | P52000076662 | 20 Jun 2024 | 31 Dec 2026 | — | Not yet due | 0 |
| Shri DattaSudam Lahu Gharat | P52000076622 | 18 Jun 2024 | 31 Dec 2026 | — | Not yet due | 1 |
| KomalPrasad Construction | P52000056454 | 31 May 2024 | 30 Nov 2024 | 31 Dec 2025 | Extended 13 mo | 0 |
| Sai AshrayDoorva Construction | P52000056165 | 16 May 2024 | 31 Dec 2024 | 31 Dec 2025 | Extended 12 mo | 0 |
| Sai BalajiShree Ganesh Enterprises | P52000055807 | 22 Apr 2024 | 31 Mar 2027 | — | Not yet due | 0 |
| Shri ApartmentSantosh K Gharat | P52000055791 | 22 Apr 2024 | 31 Jul 2027 | — | Not yet due | 0 |
| Shankar OrchidMundkar Realty | P52000055761 | 16 Apr 2024 | 31 Dec 2026 | — | Not yet due | 0 |
| Sai MangalmurtiAvinash Damodar Naik | P52000055691 | 8 Apr 2024 | 29 Dec 2026 | — | Not yet due | 0 |
| Chaitanya PrideDipak Annaso Patil | P52000055640 | 5 Apr 2024 | 31 Dec 2026 | — | Not yet due | 0 |
| Swamini HeightsVivek Chandrakant Keni | P52000055659 | 5 Apr 2024 | 31 Mar 2029 | — | Not yet due | 0 |
| Shankar HeightsSirvi Infra | P52000055586 | 4 Apr 2024 | 30 Sep 2026 | — | Promised date passed | 0 |
| Sai AnnapurnaGns Infra | P52000055406 | 22 Mar 2024 | 31 May 2027 | — | Not yet due | 0 |
| Vitthal SparshDv Constructions | P52000055440 | 22 Mar 2024 | 31 Mar 2028 | — | Not yet due | 0 |
| Hills ParadiseBhuvanesh Dhondibhau Jagdale | P52000055272 | 14 Mar 2024 | 31 Mar 2027 | — | Not yet due | 0 |
| Infragate TajSharda Infra | P52000055309 | 14 Mar 2024 | 31 Dec 2026 | — | Not yet due | 0 |
| Shree PrasadShree Sai Enterprises | P52000055137 | 4 Mar 2024 | 31 Dec 2027 | — | Not yet due | 0 |
| Shreepati 171Siddhivinayak Homes | P52000054956 | 21 Feb 2024 | 31 Dec 2026 | — | Not yet due | 0 |
| JW PrideJW Infra | P52000054879 | 15 Feb 2024 | 31 Dec 2027 | — | Not yet due | 0 |
| Empire HeightsEmpire Buildcon | P52000054637 | 2 Feb 2024 | 31 Dec 2026 | — | Not yet due | 0 |
| Rudrashakti HeightsPrakash Maruti Gharat | P52000054636 | 2 Feb 2024 | 31 Mar 2027 | — | Not yet due | 0 |
| Mangalmurti Nitin IconMangalmurti Lifespaces | P52000054367 | 17 Jan 2024 | 31 Dec 2027 | — | Not yet due | 0 |
| Siddhivinayak EkdantKiran Narayan Pawar | P52000054146 | 29 Dec 2023 | 31 Mar 2027 | — | Not yet due | 0 |
| Sai BalajiChirag Deepak Gadge | P52000054019 | 19 Dec 2023 | 31 Dec 2024 | — | Promised date passed | 0 |
| Aai ResidencyGunwant Bhagawan Gowari | P52000053338 | 27 Oct 2023 | 30 Sep 2027 | — | Not yet due | 0 |
| Govind AmeyaMansarovar Constructions | P52000052924 | 5 Oct 2023 | 31 Oct 2026 | — | Not yet due | 0 |
| Tulshiram HeightsAjit Raman Gowari | P52000052900 | 5 Oct 2023 | 31 Dec 2026 | — | Not yet due | 0 |
| Ambaji ResidencyVishal Tukaram Patil | P52000052731 | 22 Sep 2023 | 31 Jul 2026 | — | Promised date passed | 0 |
| Zenisha CornerMahashakti Developers | P52000052354 | 21 Aug 2023 | 31 Dec 2026 | — | Not yet due | 0 |
| Chaitanya PlazaDipak Annaso Patil | P52000052340 | 14 Aug 2023 | 31 Dec 2025 | — | Promised date passed | 0 |
| Shankar HomesRahul Sawalaram Keni | P52000052186 | 27 Jul 2023 | 31 Mar 2027 | — | Not yet due | 0 |
| Apex ParadiseManoj Jaysing Dongare | P52000051824 | 7 Jul 2023 | 30 Jun 2026 | — | Promised date passed | 0 |
| Sai KiranRavi Kiran Homes | P52000051736 | 27 Jun 2023 | 31 Dec 2023 | 10 Apr 2024 | Extended 4 mo | 0 |
| Savitri PlanetSavitri Builders and Developer | P52000051510 | 23 Jun 2023 | 31 Dec 2025 | — | Promised date passed | 0 |
| Shree Siddhivinayak ResidencyJanabai Chandrakant Gharat | P52000051488 | 23 Jun 2023 | 31 Mar 2026 | — | Promised date passed | 0 |
| J.k. PrideJ.k.infracon | P52000051271 | 8 Jun 2023 | 30 Apr 2026 | — | Promised date passed | 0 |
| Parshu HeritageSuraj Pandharinath Keni | P52000051367 | 8 Jun 2023 | 31 Mar 2027 | — | Not yet due | 0 |
| Krishna CornerDhiraj Kisan Keni | P52000051045 | 22 May 2023 | 31 Mar 2026 | — | Promised date passed | 0 |
| Divesh Dishant ResidencyConcept Group | P52000051007 | 19 May 2023 | 31 Dec 2025 | — | Promised date passed | 0 |
| Royal Diamond ApartmentAmol Ashok Patil | P52000051010 | 19 May 2023 | 30 Jun 2024 | 30 Jun 2025 | Extended 12 mo | 0 |
| Divine Hill ViewDivine Enterprises | P52000050970 | 16 May 2023 | 30 Sep 2027 | — | Not yet due | 0 |
| Om NirmanNirman Infra | P52000050931 | 15 May 2023 | 31 Aug 2026 | — | Promised date passed | 0 |
| Sai SapphireM/S. Guru Sai Homes | P52000050925 | 15 May 2023 | 31 Dec 2024 | — | Promised date passed | 0 |
| Himanshu TaraVimal Homes | P52000050648 | 21 Apr 2023 | 31 Dec 2025 | — | Promised date passed | 0 |
| Nagibai HeightsAshok Vasant Dhamale | P52000050530 | 21 Apr 2023 | 31 Dec 2026 | — | Not yet due | 0 |
| Satyam CrescentSatyam Group | P52000050486 | 17 Apr 2023 | 30 May 2024 | 31 Dec 2024 | Extended 7 mo | 0 |
| Bhaveshwar CaasaShiv Infra | P52000049416 | 8 Feb 2023 | 31 Dec 2025 | — | Promised date passed | 0 |
| Matrubhumi HeightsShree Ganesh Developers | P52000048341 | 26 Dec 2022 | 16 Jun 2026 | — | Promised date passed | 0 |
| VighnahartaVighnaharta Developers | P52000048079 | 8 Dec 2022 | 31 Oct 2024 | — | Promised date passed | 0 |
| Mayanks Blue Diamond ApartmentMangesh Dattatrey Gharat | P52000047699 | 21 Nov 2022 | 31 Dec 2024 | — | Promised date passed | 0 |
| Nilesh PalaceVighnaharta Developers | P52000047748 | 21 Nov 2022 | 31 Dec 2026 | — | Not yet due | 0 |
| Shree Gurukrishna ResidencyBenchmark Construction | P52000047684 | 21 Nov 2022 | 31 Jul 2024 | 30 Jun 2025 | Extended 11 mo | 0 |
| Alankara HeightAmogh Developers | P52000047612 | 14 Nov 2022 | 31 Mar 2026 | — | Promised date passed | 0 |
| Dreesha ResidencyJagdish Namdeo Patil | P52000047624 | 14 Nov 2022 | 31 Dec 2023 | — | Promised date passed | 0 |
| Balaram ParadiseNishant Arun Patil | P52000047478 | 2 Nov 2022 | 31 Mar 2024 | 30 Mar 2025 | Extended 12 mo | 0 |
| Shree Samarth ResidencyMilestone Construction | P52000047456 | 2 Nov 2022 | 31 Oct 2026 | — | Not yet due | 0 |
| Jaguar HeightsRupesh Machhindranath Dhumal | P52000047363 | 27 Oct 2022 | 28 Feb 2024 | 31 Dec 2024 | Extended 10 mo | 0 |
| Dattu NiwasNew S D Infra Builders And Developers | P52000046840 | 14 Sep 2022 | 31 Dec 2025 | — | Promised date passed | 0 |
| Chaitanya PrabhatUday Mahesh Joshi | P52000046497 | 6 Aug 2022 | 31 Dec 2025 | — | Promised date passed | 0 |
| Shanaya ResidencyUday Bhagwan Gharat | P52000046317 | 22 Jun 2022 | 31 Dec 2023 | — | Promised date passed | 0 |
| Om Crystal OrchidS S Infra | P52000035113 | 10 May 2022 | 30 Apr 2024 | — | Promised date passed | 0 |
| Dev Residency - Part BRajendra Madhukar Joshi | P52000034937 | 28 Apr 2022 | 18 Mar 2024 | — | Promised date passed | 0 |
| Surya CornerKristal Enterprises | P52000034672 | 20 Apr 2022 | 31 Dec 2026 | — | Not yet due | 0 |
| Swastik ArunSwastik Builders And Developers | P52000034360 | 4 Apr 2022 | 31 Dec 2026 | — | Not yet due | 0 |
| DhruvaAnand Mukund Gindodiya | P52000033930 | 14 Mar 2022 | 31 Dec 2023 | — | Promised date passed | 0 |
| Goodwill DynastyKewat Buildcon Private Limited | P52000033729 | 8 Mar 2022 | 1 Dec 2023 | 30 Jun 2026 | Extended 30 mo | 0 |
| Jyoti ComplexManoj Kumar Singh | P52000033382 | 16 Feb 2022 | 30 Jun 2026 | — | Promised date passed | 0 |
| Jyoti ResidencyManoj Kumar Singh | P52000033261 | 10 Feb 2022 | 30 Jun 2023 | 1 Jun 2024 | Extended 12 mo | 0 |
| Shree Samartha HomesVarun Pandit Tandel | P52000033210 | 9 Feb 2022 | 31 Dec 2023 | 30 Dec 2026 | Extended 36 mo | 0 |
| Anand ViharSirvi Infra | P52000032897 | 2 Feb 2022 | 31 Dec 2023 | — | Promised date passed | 0 |
| Sai SankalpSwaraj Developers | P52000032775 | 29 Jan 2022 | 15 Dec 2024 | — | Promised date passed | 0 |
| Om Bhagwati ApartmentsAnnappa Umaji Dupargude | P52000032583 | 14 Jan 2022 | 31 Dec 2023 | — | Promised date passed | 0 |
| Eden ApartmentTushar Ramchandra Patil | P52000032152 | 14 Dec 2021 | 31 Dec 2021 | 31 Jan 2025 | Extended 37 mo | 0 |
| Sai SagarChirag Deepak Gadge | P52000032127 | 14 Dec 2021 | 31 Dec 2023 | — | Promised date passed | 0 |
| Savitri VillaRavindra Sadashiv Mahadik | P52000030875 | 20 Sep 2021 | 30 Jun 2023 | — | Promised date passed | 0 |
Other localities in Panvel
- Ulawe678 projects
- Panvel301 projects
- Wahal299 projects
- Karanjade250 projects
- Taloje Panchnad151 projects
- Dapoli142 projects
- Kharghar137 projects
- Kamothe86 projects
- New Panvel74 projects
- Kalamboli58 projects
- Taloje Majkur43 projects
- Koyana Velhe41 projects
Most active promoters
By projects registered here, as named on MahaRERA.
- Atharva Developers7 projects
- Apex Buildcon6 projects
- Guru Sai Developers5 projects
- Lakshadeep Developers5 projects
- Tushar Ramchandra Patil5 projects
- Alankara Developers4 projects
- Golden Stone Construction4 projects
- Lumbaram Modaram Patel4 projects
- Om Civil Constructions4 projects
- Pravin Narasi Manani4 projects
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology