139 projects under 144 MahaRERA registrations, registered 2017–2026. 56% have a completion date extended beyond the one promised.

Locality
139RERA projects
144Registrationssome projects hold several
86Completion still due58 past their completion date
4 monthsMedian extension beyond promised date56% of registrations extended
4Regulatory caseson 4 projects
220Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
201735
20183
20198
20207
20217
202211
202315
202425
202515
202618

Projects in Kharghar

139 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Armaan ExoticaArmaan EnterprisesPR127000260230814 Oct 202631 Dec 2031—Not yet due0
The Domus MenarcoAramus Lifespaces Private LimitedPM127000260226312 Oct 202631 Dec 203231 Dec 2032Not yet due0
Madhuraaj KedarnathMadhuraaj Engineers And Builders & M. M. DevelopersPM127000260193515 Sep 202631 Dec 202931 Dec 2029Not yet due0
Gami Bhagwati OreliaGami Vision Private LimitedPR12700026017803 Sep 202630 Jun 203230 Jun 2032Not yet due0
The Crystal PalaceShreelaxminavkar Realty LLPPR127000260169331 Aug 202631 Dec 203031 Dec 2030Not yet due0
Bhagwati Gami AltairBhagwati EstatesPM127000260167627 Aug 202630 Jun 203130 Jun 2031Not yet due0
One Crest Wing ABMetrosatyam Realty LLPPR127000260151911 Aug 202631 Dec 203131 Dec 2031Not yet due0
Tharwani PristineaTharwani RealtorsPM12700026011119 Jul 202630 Jun 203030 Jun 2030Not yet due0
Soham ElysiumSoham Construction Private LimitedPM12700026010031 Jul 202631 Dec 203130 Apr 2032Extended 4 mo0
Krishna Aura NXGami and Krishna Enterprises LLPPR127000260076712 Jun 202630 Apr 203130 Aug 2031Extended 4 mo0
Capitor 11Life Good I-Smart Homes Private LimitedPR12700026006554 Jun 202631 Jan 203031 May 2030Extended 4 mo0
Dream HillsMajestic AbhinandanPM127000260025723 Apr 202631 Dec 202930 Apr 2030Extended 4 mo0
Mirai OneAhinsa Builders & DevelopersPR127000260007410 Apr 202631 Aug 202931 Dec 2029Extended 4 mo0
Satyam SkydeckGoldberry Realtors LLPPR12700026000326 Apr 202631 Dec 203030 Apr 2031Extended 4 mo0
One VaviyaNeelkanth DevelopersPR127000250277713 Mar 202631 Dec 202930 Apr 2030Extended 4 mo0
Shree Krishna KashtbhanjanChambaria EnterprisesPR127000250277913 Mar 202631 Dec 202930 Apr 2030Extended 4 mo0
Godrej VaranyaGodrej Properties LimitedPM1271012502176, PM127101250234323 Jan 202630 Jun 203430 Oct 2034Extended 4 mo0
RayaZorba GroupPR127000250181517 Dec 202530 Sep 203030 Sep 2030Not yet due0
Iland 27Today Royal DevelopersPR12700025016583 Dec 202531 Dec 203030 Apr 2031Extended 4 mo0
The Coastal BayPioneer VenturesPR127000250147714 Nov 202531 Oct 202828 Feb 2029Extended 4 mo0
Balaji Park C WingVarsha EnterprisesPR127000250135430 Oct 202531 Dec 202930 Apr 2030Extended 4 mo0
CelestiaQualcon S K Hi-Tech LLPPR127000250123715 Oct 202531 Dec 202930 Apr 2030Extended 4 mo0
Shreeji Space-IIIWhite Class Realty Private LimitedPR12700025005177 Aug 202531 Dec 202730 Apr 2028Extended 4 mo0
Shreeji Space IWhiteclass RealtyPR12700025004925 Aug 202531 Dec 202730 Apr 2028Extended 4 mo0
Shreeji Space-IIWhite Class Realty Private LimitedPR12700025004895 Aug 202531 Dec 202730 Apr 2028Extended 4 mo0

Other localities in Panvel

Most active promoters

By projects registered here, as named on MahaRERA.

  1. City And Industrial Development Corporation Of Maharashtra Limited3 projects
  2. Bhagwanji Dharamshi Minat2 projects
  3. Future Icon Builders LLP2 projects
  4. Shah Group Builders Ltd2 projects
  5. Skytech Infra2 projects
  6. Tharwani Realtors2 projects
  7. Today Royal Developers2 projects
  8. Tricity Realty LLP2 projects
  9. White Class Realty Private Limited2 projects
  10. Aavishkaar Realty1 project
Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology