9 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects72
Registrations72
Completion still due3141 past their date
Median extension4 months40% of registrations extended
Regulatory cases1on 1 project

9 in 10 registrations run late here

72 MahaRERA registrations in Naupada

8 not yet due23 extended, not yet due41 past even the latest date

Extended registrations moved their completion date by a median of 4 months.

Projects in Naupada

72 projects registered with MahaRERA.

ProjectDeliveryMedian ₹/sq ftBooked
SuchiparnaDimension SpacesDue Dec 2029——
Aurel Tower ECamrose Realtors Private LimitedDue Dec 2031——
Sontakke BuildingSNA Build-TechDue Feb 2031——
Neel KamalVividha Realtors Private LimitedDue May 2031, extended 4 mo——
Urban NestSuperlative Constructions LLPDue Oct 2029, extended 4 mo——
All 72 projects →
Naupada market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Aditya Associates4 projects
  2. Providence Realty Llp3 projects
  3. Ganesh Chandrakant Malvankar2 projects
  4. Govind Ojass Edifice Pvt. Ltd2 projects
  5. L. K. Realtors2 projects
  6. Magnum Homes2 projects
  7. Yash Govinda Build Infra Llp2 projects
  8. Aadarsh Developers1 project
  9. Aaradhana Builders And Developers Llp1 project
  10. Adarsha Co Operative Housing Society Limited1 project

Naupada, in questions

How many projects in Naupada run late?

9 in 10 MahaRERA registrations (64 of 72): their completion date was extended or has passed, data through 5 Nov 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Naupada by Deedo. Medians on fewer than 3 deeds are not shown.

Data through5 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology