5 in 10 MahaRERA registrations here have pushed their completion date back.

RERA projects252
Registrations261some projects hold several
Completion still due85176 past their date
Median extension12 months48% of registrations extended
Regulatory cases4on 4 projects
Mirabhayandar (M Corp.) market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

9 in 10 registrations run late here

261 MahaRERA registrations in Mirabhayandar (M Corp.)

15 not yet due70 extended, not yet due176 past even the latest date

Extended registrations moved their completion date by a median of 12 months.

Projects in Mirabhayandar (M Corp.)

252 projects registered with MahaRERA.

ProjectDeliveryMedian ₹/sq ftBooked
HKS SolaceM/s. HKS RealtyDue Apr 2027, extended 4 mo—0%
Imperial Heights Phase III - E WingAkshar Shanti Realtors Private LimitedDue Apr 2031, extended 4 mo—0%
Ramdev KhodiyarRamdev KhodiyarDue Jul 2029, extended 4 mo—0%
Hill Galaxy Phase IIGulamrasul Mohammed Ali ShaikhDue Oct 2030, extended 4 mo—0%
Oak Leaf TowersAxis Housing Private LimitedDue Apr 2031, extended 4 mo—0%
AyodhyaSeven Eleven Construction Pvt. LtdDue Mar 2030—0%
Forest VistaKashimira Ceramic Products LLPDue Dec 2036—0%
Annapurna AriesM/s. DWIVEDI CONSTRUCTIONDue Aug 2031, extended 4 mo—0%
Sea GreenSierra Infraproject LLPDue Mar 2029—0%
Vihang AtharvaReyanshp Realty LLPDue Apr 2030, extended 4 mo—0%
Madar SignatureMadar Builders & DevelopersDue Dec 2027—0%
Raj Ultimate E-WingS D U Tradelink Pvt Ltd.Due Apr 2027, extended 4 mo—76%
Vitthal HeightsBhoir DevelopersDue Apr 2028, extended 4 mo—0%
Unique Estate - IIUnique Shanti RealtorsDue Oct 2028, extended 4 mo—13%
Kasturi Vandana EmpireTirupati Estate Developers LLPDue Apr 2030, extended 4 mo—0%
Balaji InoxBalaji VenturesDue Apr 2028, extended 4 mo——
Prithvi Pride Building No 2Prithvi Land DevelopersDue Dec 2029, extended 1 yr——
Poonam Estate Cluster-II Building No 4,5,6Unique Shanti Ventures LLPDue Apr 2028, extended 4 mo—15%
Sky HeightsBalaji Realty LLPDue Apr 2030, extended 4 mo—31%
Masaakin HatimiyahIndus InfratechDue Jul 2029, extended 4 mo—12%
Vasudev RatnaKrisha BuildersDue Apr 2028, extended 4 mo—4%
Codename StarLifeJP Infra Realty Private LimitedDue Dec 2031—40%
Unique Estate Type-C Wing DSiddhivinayak DevelopersDue Jul 2027, extended 4 mo—14%
Pyramid HorizonPyramid ConstructionDue Apr 2028, extended 4 mo—0%
Panchvati ComplexNational AssociatesDue Dec 2027—9%

Most active promoters

  1. JP Infra Realty Private Limited10 projects
  2. RNA Builders (NG)9 projects
  3. Eversmile Properties Private Limited8 projects
  4. Ravi Developments6 projects
  5. Unique Shanti Realtors5 projects
  6. Shree Ostwal Builders Ltd4 projects
  7. Unique Shanti Developers LLP4 projects
  8. Seven Eleven Construction Private Limited3 projects
  9. Seven Eleven Construction Pvt Ltd3 projects
  10. Strawberry Constructions Pvt. Ltd.3 projects
Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Methodology