Mirabhayandar (M Corp.), Thane
5 in 10 MahaRERA registrations here have pushed their completion date back.
RERA projects252
Registrations261some projects hold several
Completion still due85176 past their date
Median extension12 months48% of registrations extended
Regulatory cases4on 4 projects
9 in 10 registrations run late here
261 MahaRERA registrations in Mirabhayandar (M Corp.)
15 not yet due70 extended, not yet due176 past even the latest date
Extended registrations moved their completion date by a median of 12 months.
Projects in Mirabhayandar (M Corp.)
252 projects registered with MahaRERA.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| HKS SolaceM/s. HKS Realty | Due Apr 2027, extended 4 mo | — | 0% |
| Imperial Heights Phase III - E WingAkshar Shanti Realtors Private Limited | Due Apr 2031, extended 4 mo | — | 0% |
| Ramdev KhodiyarRamdev Khodiyar | Due Jul 2029, extended 4 mo | — | 0% |
| Hill Galaxy Phase IIGulamrasul Mohammed Ali Shaikh | Due Oct 2030, extended 4 mo | — | 0% |
| Oak Leaf TowersAxis Housing Private Limited | Due Apr 2031, extended 4 mo | — | 0% |
| AyodhyaSeven Eleven Construction Pvt. Ltd | Due Mar 2030 | — | 0% |
| Forest VistaKashimira Ceramic Products LLP | Due Dec 2036 | — | 0% |
| Annapurna AriesM/s. DWIVEDI CONSTRUCTION | Due Aug 2031, extended 4 mo | — | 0% |
| Sea GreenSierra Infraproject LLP | Due Mar 2029 | — | 0% |
| Vihang AtharvaReyanshp Realty LLP | Due Apr 2030, extended 4 mo | — | 0% |
| Madar SignatureMadar Builders & Developers | Due Dec 2027 | — | 0% |
| Raj Ultimate E-WingS D U Tradelink Pvt Ltd. | Due Apr 2027, extended 4 mo | — | 76% |
| Vitthal HeightsBhoir Developers | Due Apr 2028, extended 4 mo | — | 0% |
| Unique Estate - IIUnique Shanti Realtors | Due Oct 2028, extended 4 mo | — | 13% |
| Kasturi Vandana EmpireTirupati Estate Developers LLP | Due Apr 2030, extended 4 mo | — | 0% |
| Balaji InoxBalaji Ventures | Due Apr 2028, extended 4 mo | — | — |
| Prithvi Pride Building No 2Prithvi Land Developers | Due Dec 2029, extended 1 yr | — | — |
| Poonam Estate Cluster-II Building No 4,5,6Unique Shanti Ventures LLP | Due Apr 2028, extended 4 mo | — | 15% |
| Sky HeightsBalaji Realty LLP | Due Apr 2030, extended 4 mo | — | 31% |
| Masaakin HatimiyahIndus Infratech | Due Jul 2029, extended 4 mo | — | 12% |
| Vasudev RatnaKrisha Builders | Due Apr 2028, extended 4 mo | — | 4% |
| Codename StarLifeJP Infra Realty Private Limited | Due Dec 2031 | — | 40% |
| Unique Estate Type-C Wing DSiddhivinayak Developers | Due Jul 2027, extended 4 mo | — | 14% |
| Pyramid HorizonPyramid Construction | Due Apr 2028, extended 4 mo | — | 0% |
| Panchvati ComplexNational Associates | Due Dec 2027 | — | 9% |
Nearby: other localities in Thane
Thane (M Corp.) · 1,176 projectsNavi Mumbai (M Corp.) · 416 projectsMira Bhayandar (M Corp.) · 126 projectsBhayandar · 80 projectsPanchpakhadi · 26 projectsNerul · 18 projectsVartaknagar · 14 projectsAiroli · 11 projectsMajiwade · 11 projectsNavghar · 10 projectsKalwa · 9 projectsKolshet · 9 projects
Most active promoters
- JP Infra Realty Private Limited10 projects
- RNA Builders (NG)9 projects
- Eversmile Properties Private Limited8 projects
- Ravi Developments6 projects
- Unique Shanti Realtors5 projects
- Shree Ostwal Builders Ltd4 projects
- Unique Shanti Developers LLP4 projects
- Seven Eleven Construction Private Limited3 projects
- Seven Eleven Construction Pvt Ltd3 projects
- Strawberry Constructions Pvt. Ltd.3 projects
Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Methodology