Deedo IDDL-THN-KOLSHET7 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects25
Registrations31some projects hold several
Completion still due247 past their date
Median extension4 months48% of registrations extended
Regulatory cases0none on MahaRERA's lists
7 in 10 registrations run late here
31 MahaRERA registrations in Kolshet
10 not yet due14 extended, not yet due7 past even the latest date
Extended registrations moved their completion date by a median of 4 months.
Projects in Kolshet
25 projects registered with MahaRERA.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| V KantaTarang Developers | Due Dec 2032 | — | — |
| Regency Business ParkRegency Shelters LLP | Due Oct 2028, extended 1 mo | — | — |
| TraffordRoma Builders Private Limited | Completed | — | — |
| Villa CarinoRoma Builders Private Limited | Completed | — | — |
| Runwal Lands End- SkyeRunwal Construction Private Limited | Due Jan 2031, extended 4 mo | — | — |
Nearby: other villages in Thane
Thane (M Corp.) · 898 projectsNavi Mumbai (M Corp.) · 271 projectsMirabhayandar (M Corp.) · 225 projectsBhayandar · 118 projectsMira Bhayandar (M Corp.) · 106 projectsNaupada · 72 projectsPanchpakhadi · 65 projectsNerul · 58 projectsGhansoli · 57 projectsMajiwade · 43 projectsMumbra · 28 projectsOwale · 28 projects
Most active promoters
- Runwal Construction Private Limited4 projects
- Lodha Developers Limited3 projects
- Macrotech Developers Limited3 projects
- Raunak Avenue Realty2 projects
- Regency Shelters Llp2 projects
- Roma Builders Private Limited2 projects
- D. D. Associates1 project
- Oberoi Realty Limited1 project
- Purva Oak Private Limited1 project
- Purva Oak Private Limited1 project
Kolshet, in questions
How many projects in Kolshet run late?
7 in 10 MahaRERA registrations (21 of 31): their completion date was extended or has passed, data through 22 Nov 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Kolshet by Deedo. Medians on fewer than 3 deeds are not shown.
Data through22 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology