Abc Palladium
Certificate SignedMahalunge, Pune 410501 |Promoter: Krish Realtors Private Limited
Project summary
As registered with MahaRERA and published on its project page
- Project type
- Commercial
- Status on MahaRERA
- Certificate Signed
- Buildings
- 1
- Unit types
- Shop48 units in all
- Address
- P 9 MAHALUNGE CHAKAN INDUSTRIAL AREA TAL KHED PUNE, Mahalunge, Chakahn Industrial Area, Tal Khed, PunePIN 410501
- Designated bank account
- 82
- Developed in phases
- No
Registered transactions
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion promised for 30 Sep 2023
The latest completion date on record passed 3 years and 1 month ago.
- Registered
- 11 Oct 2018
- Promised
- 30 Sep 2023
RERA registration
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100018163 | 11 Oct 2018 | 30 Sep 2023 | 30 Sep 2023 | Krish Realtors Private Limited | Project page |
1 building
Buildings and wings named in the registration
| Building | Sanctioned floors | Units |
|---|---|---|
| Abc Palladium | 3 | 48 |
Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.
Units and parking
2 of 48 units booked (4%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| Shop | 9.82 sq m · 106 sq ft | 1 | 0 |
| Shop | 13.5 sq m · 145 sq ft | 13 | 0 |
| Shop | 22.93 sq m · 247 sq ft | 1 | 0 |
| Shop | 29.5 sq m · 318 sq ft | 1 | 0 |
| Shop | 33.5 sq m · 361 sq ft | 8 | 2 |
| Shop | 33.8 sq m · 364 sq ft | 1 | 0 |
| Shop | 38.36 sq m · 413 sq ft | 1 | 0 |
| Shop | 40.5 sq m · 436 sq ft | 12 | 0 |
Show all 11 unit rowsShow fewer unit rows
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| Shop | 50.25 sq m · 541 sq ft | 8 | 0 |
| Shop | 50.7 sq m · 546 sq ft | 1 | 0 |
| Shop | 73.11 sq m · 787 sq ft | 1 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Documents
1 document held by Deedo, 61 filings listed on MahaRERA's project page
Legal
Migrated
- 1 Details of encumbrancesNil litigation krish.pdf · uploaded 27 Sep 2018Source
- 1 Copy of the legal title reportsearch titel report krishd.pdf · uploaded 29 Sep 2018Source
- 1 Copy of Layout Approval (in case of layout)layou.pdf · uploaded 29 Sep 2018Source
- 1 Building Plan Approval (IOD)Building Plan.pdf · uploaded 29 Sep 2018Source
- 1 Commencement Certificates / NA Order for plotted developmentKRISH PLAN APPROVAL LETTER-ilovepdf-compressed.pdf · uploaded 29 Sep 2018Source
Show all 62 documentsShow fewer documents
Migrated
- 1 Declaration in FORM BKRISH REALTORS FORM B REVISED (1).pdf · uploaded 29 Sep 2018Source
- 1 Certificates of CA (Form 3)new pdf.pdf · uploaded 29 Sep 2018Source
- 1 Proforma of Allotment letterREVISED Agreement FINAL 22 Sep18.pdf · uploaded 29 Sep 2018Source
- 1 Annual Audit Report of Statutory CA (Form 5)Form 5 Krish Realtors.pdf · uploaded 30 Sep 2019Source
- 2 Annual Audit Report of Statutory CA (Form 5)form 5 abc palladium.pdf · uploaded 24 Sep 2020Source
- 1 Disclosure of sold/ booked inventoryKrish Realtors Pvt Ltd - Rera Update 12-7-2021.pdf · uploaded 14 Jul 2021Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Krish realtors (ABC palladium).pdf · uploaded 5 Jan 2023Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)aRCHITECT CERTIFICATE MARCH 2023 ABC PALLADIUM.pdf · uploaded 8 Jun 2023Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Krish R P L engineer Certificate.pdf · uploaded 8 Jun 2023Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECT CERT.pdf · uploaded 11 Aug 2023Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate.pdf · uploaded 11 Aug 2023Source
- 2 Disclosure of sold/ booked inventoryKrish realtors - Sold Unsold inventory.pdf · uploaded 11 Aug 2023Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate.pdf · uploaded 13 Oct 2023Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate.pdf · uploaded 13 Oct 2023Source
- 3 Disclosure of sold/ booked inventorySold Unsold Inventory.pdf · uploaded 13 Oct 2023Source
- 2 Certificates of CA (Form 3)ABC Palladium Form 3 certificate 13 OCT 23 with Promoters sign.pdf · uploaded 14 Oct 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Krish Realtors - ABC Palladium FY 22-23.pdf · uploaded 25 Dec 2023Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Krish R P L Architect Certificate Dec 23.pdf · uploaded 8 Jan 2024Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Krish R P L - Engineer Certi.pdf · uploaded 8 Jan 2024Source
- 4 Disclosure of sold/ booked inventoryKrish R P L - sold unsold inventory.pdf · uploaded 8 Jan 2024Source
- 3 Certificates of CA (Form 3)Form 3 Krish R P L.pdf · uploaded 8 Jan 2024Source
- 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1.pdf · uploaded 15 Apr 2024Source
- 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Krish R P L Eng Certificate Mar 24.pdf · uploaded 15 Apr 2024Source
- 5 Disclosure of sold/ booked inventoryKrish Re P L Sold Unsold Inv Mar 24.pdf · uploaded 15 Apr 2024Source
- 4 Certificates of CA (Form 3)FORM 3.pdf · uploaded 16 Apr 2024Source
- 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1.pdf · uploaded 17 Jul 2024Source
- 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2.pdf · uploaded 17 Jul 2024Source
- 6 Disclosure of sold/ booked inventorystatement.pdf · uploaded 17 Jul 2024Source
- 5 Certificates of CA (Form 3)FORM 3.pdf · uploaded 17 Jul 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)krish rpl.pdf · uploaded 24 Oct 2024Source
- 1 Other – TechnicalDeclaration Krish R P L.pdf · uploaded 14 Nov 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Krish Architect Certificate.pdf · uploaded 9 Jan 2025Source
- 1 Certificates of CA (Form 3)CA Certificate Krish RPL.pdf · uploaded 9 Jan 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Krish Engineer Certificate.pdf · uploaded 9 Jan 2025Source
- 1 Disclosure of sold/ booked inventoryKirsh Sold unsold Letter.pdf · uploaded 9 Jan 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1- Krish RPL Architect Certificate.pdf · uploaded 18 Apr 2025Source
- 1 Certificates of CA (Form 3)Signed Form 3 krish realtors Pvt Ltd.pdf · uploaded 18 Apr 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 -Krish RPL Engineers certificate.pdf · uploaded 18 Apr 2025Source
- 1 Disclosure of sold/ booked inventoryKrish RPL sold unsold Letter.pdf · uploaded 18 Apr 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1.pdf · uploaded 16 Jul 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2.pdf · uploaded 16 Jul 2025Source
- 1 Disclosure of sold/ booked inventorySTATEMENT.pdf · uploaded 16 Jul 2025Source
- 1 Certificates of CA (Form 3)FORM3F.pdf · uploaded 19 Jul 2025Source
Technical
Technical (Architect)
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
Land
In Mahalunge, Khed taluka
Survey, CTS, gat or plot numbers
Boundaries
- North
- MIDC Road
- South
- MIDC Road
- East
- Plot No C-33
- West
- MIDC Road
Source: registration certificates and MahaRERA's project page, as stated there.
Professionals
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | s v kodre and associates | — |
| Chartered accountant | Ca Azam Mulani | — |
| Chartered accountant | Mahesh Khadekar | — |
Source: MahaRERA project page. Contact details are not shown.